Mitigation of Damages in the Construction Contracts
Ramasubramanian FCIArb
Arbitrator / Counsel | Expert Witness | Advocate| Mediator | Member IBA | ODR Neutral | PoSH ICC| WIPO Neutral | Co-Author - Handbook on ARBITRATION by ICSI.
Section 73 imposes a duty on the party seeking damages to mitigate its loss. In Murlidhar Chiranjilal v. Harish Chandra Dwarkadas (1962) 1 SCR 653, the Supreme Court of India has set out two principles on which damages are calculated in case of breach of contract of sale of goods.
The first is that the injured party has to be placed in as good a situation as if the contract has been per formed. He who has proved a breach of a bargain to supply what he has contracted to get, is to be placed so far as money can do it in as good a situation as if the contract has been performed. This is qualified by a second principle - the injured party is debarred from claiming any part of damages arising out of his neglect. The onus is on him to mitigate losses consequent to the breach of contract.
The Supreme Court of India has decided that the principle of mitigation does not give any right to a party in breach of contract but it is a circumstance to be borne in mind in assessing damages. (M. Lachia Setty & Sons Ltd v. Coffee Board Bangalore (AIR 1981 SC 162) It must be added that in the latter case, the Supreme Court has not taken into consideration its previous judgment and the explanation to section 73.
However, Supreme Court judgments are binding unless set aside or modified by other Supreme Court Benches. In the circumstances, parties to the contract are required to mitigate their losses in case of breach. For ready reference, the three Sections - 73, 74 and 75 of Indian Contract Act 1872, are reproduced below.
Section 73 Compensation of loss or damage caused by breach of contract When a contract has been broken, the party who suffers by such breach is entitled to receive, from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from such breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it
Such compensation is not to be given for any remote and indirect loss or damage sustained by reason of the breach. Compensation for failure to discharge obligation resembling those created by contract: When an obligation resembling those created by contract has been incurred and has not been discharged, any person injured by the failure to discharge it is entitled to receive the same compensation from the party in default, as if such person had contracted to discharge it and had broken his contract. Explanation: In estimating the loss or damage arising from a breach of contract, the means which existed of remedying the inconvenience caused by non-performance of the contract must be taken into account.
Illustrations (a) A contracts to sell and deliver 50 maunds of saltpetre to B, at a certain price to be paid on delivery. A breaks his promise. B is entitled to receive from A, by way of compensation, the sum, if any, by which the contract price falls short of the price for which B might have obtained 50 maunds of saltpetre of like quality at the time when the saltpetre ought to have been delivered.
(b) A hires B's ship to go to Bombay, and there takes on board, on the first of January, a cargo, which A is to provide, and to bring it to Calcutta, the freight to be paid when earned. B's ship does not go to Bombay, but A has opportunities for procuring suitable conveyance for the cargo upon terms as advantageous as those on which he had chartered the ship. A avails himself of those opportunities, but is put to trouble and expense in doing so. A is entitled to receive compensation from B in respect of such trouble and expense.
(c) A contracts to buy of B, at a stated price, 50 maunds of rice, no time being fixed for delivery. A afterwards informs B that he will not accept the rice if tendered to him. B is entitled to receive from A, by way of compensation, the amount, if any, by which the contract price exceeds that which B can obtain for the rice at the time when A informs B that he will not accept it.
(d) A contracts to buy B's ship for 60, 000 rupees, but breaks the promise. A must pay to B, by way of compensation, the excess, if any, of the contract price over the price which B can obtain for the ship at the time of breach of promise.
(e) A, the owner of a boat, contracts with B to take a cargo of jute to Mirzapur, for sale at that place, starting on a specified day. The boat, owing to some unavoidable cause, does not start at the time appointed, whereby the arrival of the cargo at Mirzapur is delayed beyond the time when it would have arrived if the boat had sailed according to the contract. After that date, and before the arrival of the cargo, the price of jute falls.
领英推荐
The measure of the compensation payable to B by A is the difference between the price which B could have obtained for the cargo at Mirzapur at the time when it would have arrived if forwarded in due course, and its market price at the time when it actually arrived.
(f) A contracts to repair B's house in a certain manner, and receives payment in advance. A repairs the house, but not according to contract. B is entitled to recover from A the cost of making the repairs conforming to the contract.
(g) A contracts to let his ship to B for a year, from first of January, for a certain price. Freights rise, and, on the first of January, the hire obtainable for the ship is higher than the contract price. A breaks his promise. He must pay to B, by way of compensation, a sum equal to the difference between the contract price and the price for which B could hire a similar ship for a year on and from the first of January.
(h) A contracts to supply B with a certain quantity of iron at a fixed price, being a higher price than that for which A could procure and deliver the iron. B wrongfully refuses to receive the iron. B must pay to A, by way of compensation, the difference between the contract price of the iron and the sum for which A could have obtained and delivered it.
(i) A delivers to B, a common carrier, a machine, to be conveyed, without delay, to A's mill, informing B that his mill is stopped for want of the machine. B unreasonably delays the delivery of the machine, and A, in consequence, loses a profitable contract with the Government. A is entitled to receive from B, by way of compensation, the average amount of profit which would have been made by the working of the mill during the time that delivery of it was delayed, but not the loss sustained through the loss of the Government contract.
(j) A, having contracted with B to supply B with 1, 000 tons of iron at 100 rupees a ton, to be delivered at a stated time, contracts with C for the purchase of 1, 000 tons of iron at 80 rupees a ton, telling C that he does so for the purpose of performing his contract with B. C fails to perform his contract with A, who cannot procure other iron, and B, in consequence, rescinds the contract. C must pay to A 20, 000 rupees, being the profit which A would have made by the performance of his contract with B.
(k) A contracts with B to make and deliver to B, by a fixed day, for a specified price, a certain piece of machinery. A does not deliver the piece of machinery, at the time specified, and, in consequence of this, B is obliged to procure another at a higher price than that which he was to have paid to A, and is prevented from performing a contract which B had made with a hired person at the time of his contract with A (but which had not been communicated to A), and is compelled to make compensation for breach of that contract. A must pay to B, by way of compensation, the difference between the contract price of the price of machinery and the sum paid by B for another, but not the sum paid by B to the third person by way of compensation.
(l) A, a builder, contracts to erect and finish a house by the first of January, in order that B may give possession of it at that time to C, to whom B has contracted to let it. A is informed of the contract between B and C. A builds the house so badly that, before the first of January, it falls down and has to be rebuilt by B, who in consequence, loses the rent which he was to have received from C, and is obliged to make compensation to C for the breach of his contract. A must make compensation to B for the cost of rebuilding of the house, for the rent lost, and for the compensation made to C.
(m) A sells certain merchandise to B, warranting it to be of a particular quality, and B, in reliance upon this warranty, sells it to C with a similar warranty. The goods prove to be not according to the warranty, and B becomes liable to pay C a sum of money by way of compensation. B is entitled to be reimbursed this sum by A.
(n) A contracts to pay a sum of money to B on a day specified. A does not pay the money on that day. B, in consequence of not receiving the money on that day, is unable to pay his debts, and is totally ruined. A is not liable to make good to B anything except the principal sum he contracted to pay together with interest up to the day of payment.
(o) A contracts to deliver 50 maunds of saltpetre to B on the first of January, at a certain price. B, afterwards, before the first of January, contracts to sell the saltpetre to C at a price higher than the market price of the first of January. A breaks his promise. In estimating the compensation payable by A to B, the market price of the first of January, and not the profit which would have arisen to B from the sale to C, is to be taken into account.
Empowering early stage growth companies with tailored and scalable sales enablement solutions
11 个月Looking forward to diving into the details. ???
Become an AI Speaker/Trainer/Consultant - message me for details
11 个月Demonstrating mitigation measures is key to reinforcing your entitlement. Happy reading.
FCIARB, FIITARB, FIE, FIV, LLM( Pro), PGD NALSAR , Diploma in Arbitration Practice, MA Mediation, A construction contract and ADR expert
11 个月Thanks sir Rama Subramanian B E LLB FCIArb for such useful content.
Senior Project Manager | Aspiring General Manager | Delivering Complex Infrastructure Projects | Driving Business Growth | Proven Expertise in Road & Bridge Construction, Team Leadership, and Strategic Project Execution
11 个月Thanks ??