Mastering Project Management: A Deep Dive into the Estimate Activity Duration Process
Sunil Zarikar
Accomplished Data & Delivery Leader | 17+ Yrs in Digital Transformation, Data Governance & Quality | Agile Practitioner | Data Analytics Expert | Risk Management Strategist
Introduction
Accurately estimating the duration of activities is a critical process in project management. The time it takes to complete project tasks directly impacts the overall project schedule and completion date. Underestimating activity durations can lead to schedule overruns, resource constraints, and cost escalations. Overestimating can build in unnecessary schedule slack and may lead to perceptions that the team is not working efficiently. Therefore, effective techniques for estimating realistic but aggressive activity durations are essential for project success.
This article provides an overview of activity duration estimation in project management. It covers key concepts and definitions, reasons for accurate estimates, commonly used estimation techniques with examples, and best practices for developing quality estimates.
Defining Activity Duration Estimates
Activity Duration Definition
An activity duration estimate defines the number of work periods required to complete a project activity. Activities are the individual tasks that must be performed to create project deliverables. Activity duration measures the elapsed time from start to finish of each task. Common units for measuring duration include hours, days, weeks or months.
The duration estimate attempts to quantify how long the work effort for an activity should take. Estimating activity duration is often described as predicting “how long something will take”. Duration estimates should consider the scope of work involved and the resources assigned. Accurate estimates require an understanding of the work effort needed as well as factoring in risks and unknowns.
Purpose of Duration Estimating
There are several key reasons why accurately estimating activity durations is important in project management:
Reasonable but Aggressive Estimates
Project managers should seek “reasonable but aggressive” activity duration estimates from teams. This means realistic appraisals of the work effort involved without excessive contingency padding. Activity duration targets should promptly communicate expectations while being achievable for workers assigned.
Padding estimates builds in unnecessary slack whereas overly idealistic targets cause teams to miss key dates. Well-crafted duration estimates balance attainability and a sense of urgency to support project success.
Types of Duration Estimating Methods
Project managers have several techniques available for predicting task durations. Each approach has advantages and drawbacks. Applying multiple estimations methods helps improve accuracy. Common techniques include:
Commonly Used Techniques
Expert Judgment
Expert judgment techniques leverage inputs from seasoned resources with deep knowledge and prior exposure with the type of work involved in an activity. Subject matter experts can draw on their specialized experience performing similar tasks to predict upcoming effort and duration.
The project manager should document the credentials and background that qualify identified experts. This helps establish their credibility and why their projections warrant validity. Expert judgment works best when experts have executed highly comparable activities within the recent past. Estimates derived longer ago under materially different circumstances become less relevant.
To apply an expert judgment approach:
Example:
A project manager is estimating how long it will take two architects to create preliminary drawings for a 40-story downtown office tower residential conversion. An expert judgment technique would have the PM interview senior architects within the firm who have led similar residential conversion designs in the past. Their prior experience with comparable projects helps estimate the effort and duration for the new endeavor.
Analogous Estimating
With analogous estimation, durations are predicted by comparing the current activity to a similar past activity in terms of size, scope, complexity, or effort. The key to analogous estimating is identifying a past baseline project where detailed actual durations were recorded. This baseline project serves as a proxy benchmark for mapping out estimates on the current work.
The advantage of this technique is its simplicity. By benchmarking against historical precedence, analogous estimating provides a straightforward way to quickly quantifying estimates. It also provides a built-in data-driven analysis based on prior achievements. However, finding perfectly comparable precedents can be challenging. Apply judgment in determining how closely aligned the baseline example truly is.
To utilize analogous estimating:
Example:
领英推荐
If a prior software enhancement involved 4 developers taking 6 weeks to add 5 new user interface screens, this analogous data could estimate how long it would take 3 developers to add 7 new screens now. Scaled proportionally, 9 weeks would be a plausible resulting estimate.
Parametric Estimating
Parametric estimating leverages quantifiable parameters about an activity to calculate its duration. This technique utilizes established parametric models tied to measurable activity attributes. Variables such as work effort hours, development team size, lines of code, or function points are fed into standardized formulaic models. The models output corresponding duration estimates based on proven correlations. A simple example would be
Duration = Effort Hours / Team Size.
The advantages of parametric models are their analytical objectivity versus subjective guesses. However, developing useful parametric models requires abundant relevant historical data. Parameters interacting in models must demonstrate stable causal relationships across projects for reliable extrapolations. Models need periodic auditing to confirm outputs match actual subsequent results. If underlying project work substantially changes over time then the model grows stale.
To implement parametric estimating techniques:
Example:
A basic parametric estimation model uses work effort hours divided by team size to estimate software project task durations. Extensive analysis of prior projects shows tasks involving 350 – 550 programming hours by teams of 4 – 6 developers take 6 - 10 weeks. Using regression analysis a formula is created enabling new task inputs for effort and team size to produce projected durations.
Three-Point Estimating
Three-point estimating leverages inputs from multiple experts stating their optimistic, pessimistic, and most likely duration estimations. Statistical techniques are then applied to the 3 data points to approximate a final blended analysis that helps offset inherent human biases. This aims to capture a realistic range informed by practical implementation experience.
The advantages of three-point estimates are tapping multiple perspectives to frame the duration possibilities, identifying outlier positions, while ultimately landing on an objective data-driven duration. Challenges can come from influencing experts to provide candid projections during data collection. The final statistical analysis also introduces further interpretation subjectivity if not applied carefully.
To construct three-point estimates:
Example:
An engineer provides estimates of 4 weeks (optimistic), 12 weeks (pessimistic), and 8 weeks (most likely) for a technical design activity. Applying PERT analysis yields: (4 + 4x8 + 12) / 6 = 34/6 = 6 weeks blended estimate for that expert.
After gathering 3+ such mixed sets of estimates and running PERT calculations, average the resulting blended durations.
Reserve Analysis
Reserve analysis aims to buffer activity duration estimates by applying contingency reserves amounts. Reserves help account for known activity threats and risks as well as unplanned events that often delay tasks. Reserve determination methods size contingencies as a percentage of initial predictions or use historical delay data to quantify typical overruns for analysis.
Building reserve buffers directly into estimates helps mitigate against variability concerns not addressed otherwise. By acknowledging risks and unknowns upfront duration targets become attainable. If no delays materialize the resulting schedule slack also provides flexibility to absorb emerging issues later on. However, excessive contingency padding also builds inefficiency into project plans and reduces urgency to perform. Finding data-driven optimal reserve sizing is crucial for balancing these tradeoffs.
To properly incorporate reserve buffers:
Example:
Initial bottom-up estimates show testing a module will require 4 weeks. Past data indicates on average testing slips 2 weeks typically and up to 4 for more complex elements. After evaluating module complexity a 3 week testing contingency is added to the estimate. The final duration target thus builds in buffer by stating testing should take 4 weeks + 3 week reserve = 7 week estimate.
Best Practices for Quality Duration Estimates
Project managers overseeing activity duration estimate creation should enforce best practices to help achieve reasonable and achievable targets including:
Conclusion
Estimating realistic and reliable activity durations is pivotal for project schedule development, resource planning, execution monitoring, and overall management credibility. Underestimating durations leads to missed milestones whereas overestimating causes inefficiencies. A variety of estimating techniques are available. Applying multiple methods helps pressure test estimates converged on through an analytical data-driven approach. Duration targets should additionally include carefully derived contingency reserves sized reasonably to tasks’ risk exposures. Institutional use of top activity duration estimating practices ensures projects have a sound foundation for on-time successful delivery.
Business Leader Offering a Track Record of Achievement in Project Management, Marketing, And Financial.
8 个月Looking forward to diving into your comprehensive guide on estimating activity durations! #KnowledgeSharing