Managing Supply Chain Issues in Process Skid Fabrication - White Paper
Managing Supply Chain issues in Process Skid Fabrication. Photo: UFDF Skid for a Biopharma Customer

Managing Supply Chain Issues in Process Skid Fabrication - White Paper

Author: Ian Shanahan, BSc, Chem.Eng

Managing Supply Chain Issues in Process Skid Fabrication?

Current State of the Supply Chain

Many industries across the globe are experiencing unprecedented demand, all competing for finite resources in the supply chain, causing lead times and prices to rise. Many factors are contributing to this:

  • Some industries are still trying to ramp up production following the COVID-19 Pandemic.
  • Energy and cost of living increases are adding to supply chain costs.
  • Zero Covid strategies are still ongoing in crucial Chinese trading ports and industrial cities, which has continued to cause disruption.
  • The invasion of Ukraine has caused further turmoil, with energy and nickel prices rising globally.?

For the fabrication of process systems for our life science customers, we have seen this manifest itself in the following ways:

Vessels

We have seen increases of between 12-15% in vessel pricing in the last 6 months. Quote validity durations are now down to 2-3 days due to pricing fluctuations from steel mills. Our suppliers advise us that we should see things stabilise over the rest of the summer and slightly decrease in September, but these are predictions at an unpredictable time.?

Team discussing Process Vessels at Flow Technology Workshop

Valves & Instrumentation.

Notifications of price increases have been trickling in from various suppliers in the past quarter. The level of increase varies, but in general we can expect to see increases of between 5-12%, effective from September and October. This is in addition to similar levels of increases already implemented at the end of spring.?

Heat Exchangers

Expecting increases of 3-5%, with pricing validities now subject to change without notice.

Block Valves

We’re seeing 6-10 weeks from drawing approval for blocks in 316L Stainless Steel (1.4435), but this is up to 20 weeks for blocks in higher alloys such as AL6XN (UNS designation N08367). Prices have increased between 6-8% on 316L valves, with higher alloy prices increasing by up to 14%

Hygienic Pumps

Similar to Block valves, we’re seeing single digit to low double digit increases in 316L SS pumps. “Special Pumps”, made in AL6XN or C22 Hastelloy (2.4602 / UNS designation N06022), are resulting in price increases up to 17%.

Panel Hardware?

No alt text provided for this image

As the industry is well aware, there is massive demand globally for electrical componentry, leading to dramatic increases in lead times, and price increases between 8-12%. We’re seeing lead times of 30-40 weeks for DI modules, managed switches, VFD and servo drives.


Pipes & Fittings

There are still significant backlogs from steel mills. American mills are implementing PIE (Price in Effect), which greatly affects ASME BPE tube manufacturers. Shipping costs are still three times the pre-pandemic rates, with Zero Covid strategies at strategic Chinese ports causing backlogs. International drives for Green Steel, steel produced from less carbon-intensive energy, is also being sighted as driving up costs of production, though the level of this effect is undetermined. Lead times and costs are much worse for higher alloys (C22, AL6XN).?For one filter housing in AL6XN from a major supplier, we saw a price increase of 114% over a period of 2 months.?

Initial stages of piping fabrication on a process skid

Optimising Skid Lead-times

At the proposal stage of process skid packages, we focus heavily on building a detailed project schedule, to allow us to identify critical path items, and to devise and propose a mitigation strategy. We treat this as being just as important as ensuring our proposal is technically compliant and commercially competitive.?We present this strategy at the proposal stage because effective execution requires understanding and collaboration between the supplier and the customer, to align priority items and approval timelines.?

Process Engineering Director, David Greer.

Vessel sizing

No alt text provided for this image

If vessels are required, these can often be the longest lead item on a project. It is critical to agree on vessel volumes and dimensions as early as possible so the fabricator’s capacity can be booked, and the dished ends can go into production.

Nozzle schedules and locations do not have to be finalised to accomplish this.?

IO Count

The other leading culprit for longest lead times is panel hardware. As early as possible in the detailed design, we endeavour to finalise our IO count within 90% accuracy so panel sizing and hardware can be ordered. We will often bump up our spare IO capacity from 20% to 30% just to ensure we have breathing space to order early. Having a slightly oversized panel is often preferable to our customers than a late skid delivery.?

MCC (Left Panel) & Instrumentation IO (Right Panel) on a Biopharmaceutical Skid, Flow Technology Workshop

MCC (Left Panel) & Instrumentation IO (Right Panel) on a Biopharmaceutical Skid, Flow Technology Workshop

Collaboration on Early Submittals

As outlined previously, it is critical that these key items are identified and discussed at the proposal stage of a package, or at the kick-off meeting at the latest. Getting ahead of possible supply chain delays relies on agreement and alignment on quick turnarounds for approvals on key agreed items. At Flow Technology we work hard to ensure our lead engineers have an open, honest and collaborative relationship with their customer counterparts to facilitate this exchange and ensure the project stays on track. A breakdown in communication leads to delays.?

Agreement on early submittals and approvals also helps to protect the customer from supplier increases, which they may not have been able to protect themselves from contractually due to the instability in the market, and the resulting necessity for a sharing of risk. At Flow Technology we’re in regular contact with our key suppliers and are well-informed of upcoming price increases. This helps us plan to have our POs issued in advance of increases, where possible.?

To aid in this process, particularly when multiple packages are being delivered, we have adopted a staggered approach to the design and drafting process.

No alt text provided for this image

This means that while our customer is reviewing a submittal for one package, our team is working on the 30/60/90% design of another package, preparing it for submittal. This is in contrast with the conventional model where multiple design submittals might be transmitted at once.

While this does increase the number of discrete approvals, this approach helps ensure that our team, and the customer’s team, isn’t overloaded at any one time and ensures that approved designs are moved forward quickly.

3D Model Review at Flow Technology, Cork

Supplier Flexibility

Many of our customer’s standardise on certain OEMs for their instrumentation, valving, and pumping needs across a site. This is done to avail of simplified maintenance, reduce the cost of spares inventory, quality assurance, cost savings through framework agreements with OEMs, etc.

No alt text provided for this image

In cases where our customer’s have these relationships with large global OEMs, we will often lobby through the customer, for the OEM to prioritise supply to our customer’s project. This can yield positive results in reducing lead times.

On other occasions, we will explore alternative proven suppliers in the market for comparable components. It has occurred several times in the past year, where we’ve been able to secure better lead times from non-standard suppliers for a customer’s project. Availing of this requires flexibility and pragmatism on the customer’s part to work with their wider team to have the alternative supplier approved in their system. Flow Technology work with the customer to vet any alternative suppliers.

Specification Flexibility

As is the case in many industries, life science projects make a great effort to ensure the correct and appropriate materials of construction, surface finish, IP rating, etc., are used when selecting components. The conventional focus has always been to match the specifications to the process, but to always be mindful not to over specify, and buy expensive attributes that you don’t need.?

No alt text provided for this image

There is no need to buy a C22 Hastelloy pumps if a 316L SS pump is perfectly appropriate for the fluids being handled. This approach is sensible and sound, but in recent months we have found that it can be challenged in certain scenarios to avail of more favourable lead times, and even better pricing.?

Recently we had an example where an AL6XN pump was correctly specified for a process system. While AL6XN is typically a less expensive higher alloy, compared to C22 Hastelloy, it’s not as popular, or produced at such a large scale as Hastelloy. We found we were getting better lead times and pricing to buy our pump in the higher-than-needed C22 Hastelloy, than in AL6XN.?

It’s an interesting aspect to explore when trying to creatively manage supply chain hurdles.?

These are just some of the approaches that can be utilised to manage supply chain issues in a project. The keystone supporting all these approaches is trust and understanding between the customer and the skid designer/builder. On this solid foundation, creative and collaborative approaches can keep projects on time and on budget.

No alt text provided for this image

About

Flow Technology is an Irish process engineering company specializing in the design, build, testing and delivery of highly-customised process solutions. Although our expertise spans the pharma, beverage, dairy and datacentre industries, we are known internationally for the delivery of bespoke process systems for biopharmaceutical manufacturing. Expertise includes Filtration (UFDF/TFF, Viral, Nano, Depth), Chromatography Liquid handling, Inline Dilution & Conditioning systems, CIP, TCUs, and more.?

We work with 8 of the world’s top 10 biopharmaceutical companies delivering quality process systems to meet their exacting requirements.?

Learn more at: https://flowtechnology.ie/bio-pharmaceutical


No alt text provided for this image

Author: Ian Shanahan, BSc, Chem.Eng.

Chemical Engineer working with the Process Engineering team to grow Flow Technology’s customer base internationally. Ian has been a regular speaker at Clean Utility events, and a contributing author to the ISPE Baseline Guide for Water and Steam Systems, 3rd Edition. Email: [email protected]

Viviane Costella

Sales Director at BARDIANI VALVOLE SPA

2 年

Quite interesting approach and analysis!

要查看或添加评论,请登录

社区洞察

其他会员也浏览了