Managing Schedule Risk (Part 2)

Managing Schedule Risk (Part 2)

This is Part 2 from Part 1 of Managing Schedule Risk Cost

Schedule risk management is a topic that must be addressed for any project's success. If the project schedule and cost estimates have no margin, you are late and over budget before starting.

Here are some clips from a recent week-long training session on a defense program for getting the Control Account Managers up to speed on what Program Controls do while developing the Performance Measurement Baseline (PMB).

Let's start with the fundamental principle of programmatic risk management. We must clearly understand the risks and how to deal with them. This means seeking out all possible risks, from the Known obvious ones (which are likely to be issues instead of risks) to the Unknown risks. Only if the risk is Unknowable do we stop searching for possible risks on mission-critical projects. If you say there are Unknown Unknowns, the project better have a fail-safe mode. This is usually "handled" by the cancellation and a project restart.

No alt text provided for this image

There are many kinds of programmatic risks, along with all the technical risks. Seeking the technical risks and managing them is for another time. But here is a start at the programmatic risks.

No alt text provided for this image

When we place these programmatic risks in the Integrated Master Schedule (IMS), they look like this. This example looks at the duration risk. Remember that any single point is correct with a statement of the variance. (Hence the single point estimate). Developing the upper and lower limits of the defined probability distribution is another topic as well. For now, let's assume we have all three pieces of information.

No alt text provided for this image

When we run the Monte Carlo simulator, we get outputs that look like this. This is the Probability Distribution Function (PDF) of the possible task durations generated from the Monte Carlo tool. The Cumulative Distribution Function (CDF) shows the probability of completing the "on or before" date and that probability value.

No alt text provided for this image

So now we need to define a schedule margin to "protect" the deliverable. This is done by running the Monte Carlo tool with all the schedule margins removed - a zero slack deterministic schedule - and watching the desired deliverable date to see where it says the probability of completion is. In the world we work, an 80% confidence of completing "on or before" the desired date is common. The duration between the probabilistic date (80% confidence) and the deterministic date (zero slack) is the needed margin (probabilistic value) to "protect" that date.

This margin can be placed "in line." Or if there is a named risk in the Risk Registry, then the Plan B for that deliverable is placed in the IMS once the risk is accepted by the Risk Management Board (RMB). This is shown below.

No alt text provided for this image

When Plan B is turned to "execute," the IMS must have already planned for this, as shown above. But if the margin is not used - the Risk, although planned, never came true, the IMS needs to absorb the unused risk margin for the future. This means moving unused margin forward. If this margin can not be moved forward, then the IMS probably needs to be better structured, and some re-planning is needed.

No alt text provided for this image
Dan Lynch

Senior EVMS/IPM Consultant

1 年

Well done Glen! Straight narrative, plain English! When someone like myself can grasp the points I’m certain those more versed will benefit from this!

AlAmir Mohamed Hassan ,PSP?,PMP?,M.Eng ?,P3O?, IPMA?,PRMG?

Senior MEP Planning Engineer at El-Haram Expansion Projects

1 年

Excellent, thanks for sharing. But is it applicable to add activity and named it margin at time schedule?, or add this margin as a lag between activities, or increase the duration of activities !

要查看或添加评论,请登录

社区洞察

其他会员也浏览了