LV Motor Protection - LS"I" Recommendations

LV Motor Protection - LS"I" Recommendations

Instantaneous Release setting recommendations:

Instantaneous Release setting in the MCCB is set to a value higher than the highest anticipated magnetizing inrush current, while switching-on the motor.

Lets Have a Generalized approach to evaluate best setting,

Staring Current (Ist) 

Motor rated current (IrM)

Tolerance on Starting current:

Ratio Ist/IrM is normally allowed to be 20 % higher than the rated value given by the manufacturer, this needs to be checked in datasheet furnished by manufacturer (The ratio Ist/IrM takes care of the saturation of the reactances of asynchronous motors).

Hence,

Maximum anticipated starting current:           = 1.2 x Ist

Transient inrush current (peak):                     = √2 x 1.2 Ist   = 1.697 x Ist

As per IEC 60947-2, there is a tolerance of +/- 20% in the values of current for tripping of the circuit breaker by short-circuit releases.

Hence,

Effective setting of the instantaneous release setting in the MCCB should be above this tolerance band

Suggesting Setting: 1.697 / 0.8 = 2.1213 Ist (peak value)

We should note that Instantaneous setting in the MCCB is in RMS value

Hence,

Suggesting Setting: 2.1213 / √2 = 1.5 Ist

Thus, the instantaneous setting in the MCCB has to be above 1.5 Ist

i.e; if Ist/IrM = 6 then Instantaneous stage setting should be set ≥ 9 x IrM

Reference: Paper by KSK on MCCB for LV Motor feeders

Abhijit Dasgupta

Independent Consultant at Garden Power Technologies Pvt Ltd

8 年

With a setting of 9X IrM, when would this protection operate? Would it be better for a lower setting that comes into operation only after the motor starts?

回复
Vijay Enjapelly

Senior MEP Engineer

9 年

what happens if we put over rated MPCB for motor/ motor rating is 7.5KW mpcb rating is 17-22Amps. waiting for your solution

回复

Thank you so much for this article.In your reference you mentioned KSK,what does that stand for?

回复
Suresh Kumar Vengali

Lead Electrical Commissioning Engineer | FPSO RAIA | Pre-Operations | Start-up | Engineering

9 年

Mr.Shailesh is dedicated electrical engineer. ...Great Job

回复
Davron Sharipov

Project Manager. The Commonwealth of Independent States Project PV Solar power plants in Uzbekistan.

9 年

Thank your for article ! Best regards !