Learn Commissioning Project Management
Paul Turner, P.Eng, PMP
Commissioning Project Manager | Electrical Engineer | CEO of the Industrial Commissioning Association
Technical commissioning is not actually what’s missing on projects. There are lots of smart people working on projects, and they’ll get the testing done one way or the other.
What’s missing on projects are the project management aspects that are supposed to go “around” the technical commissioning. What’s missing are the systems and controls to manage commissioning starting much earlier in projects.
Your projects may have one or more of these problems:
And I’m willing to bet it’s because you’re making one or more of these mistakes:
领英推荐
This is due to a gap in the construction industry. Project managers must know how to complete capital projects during commissioning. However, commissioning project management is not included in any of the project management literature that exists. When such a critical process (completing projects during commissioning) is not explained to people working on projects, it’s no wonder 9 out of 10 projects are late and over-budget.
That’s why we created the Commissioning Academy – to help project managers and commissioning managers understand commissioning project management, so they can complete projects during commissioning, using systems and controls to lead/manage commissioning, with much better outcomes to meet project cost and schedule objectives.
Join our next live webinar to learn more about Commissioning Project Management. Get the Zoom link here.
Co-Founder & Principal Director at FNVI Ltd I Experienced Project Manager I Corporate Commissioning Manager I Successful in creation and the Management of International Business in Oil & Gas, Nuclear & ORE Industries.
1 年Good words Paul, written by someone who is an expert and master of his chosen field. Looking forward to catching up with you over the coming weeks.
CEO, SESC Group
1 年Paul, spot on.. technical commissioning is often offered up as the reason "project handover is late" when late and poor installations are the main reason technical commissioning starts late and why the setting to work of major plant and equipment is delayed.(waiting for the rectification of none compliant systems). Unfortunately sh.. in = sh.. out..(no pun intended). In the end quality always counts.
Commissioning & Completions Manager
1 年Well said?
Senior Commissioning Manager leading complex commissioning projects globally.
1 年Can you send us the link to the webinar, I couldn't attend it yesterday. Thanks in advance.
Project Manager at Catalyst Commissioning Group LLC
1 年Most don’t understand that Commissioning is not testing. Testing is testing. Commissioning is a quality process. If you follow the process, you will see the quality increase in so many ways. If you remove pieces of the process, you remove quality as well. Think of it like an assembly line of attainable quality steps and goals. If you break the cycle, the end result is not as it was meant to be