Labor Cost Overruns - What contractors don't mention

I have been fortunate to work in several cities across the U.S. working with a large variety of workers. As a Project Manager, I have been delivered Change Orders and invoices for labor cost overruns from subcontractors who standby their costs. I am a fair person, I know that underpaying a contractor can get you sued.

I don't believe in paying for someone else's mismanagement of labor, and I spend extra time clearly defining issues along the way, just in case I get billed for additional labor hours that were "pissed away".

Depending on which company a PM works for he or she may also be the site Superintendent. Good superintendents pay attention to "where" the workers are at on the property, what time they started work, the length of their breaks, and what time they stopped working. Some might call this micromanaging subcontractors, and it probably is. However, when a Superintendent logs this sort of information known as abuse of paid time, it helps counter requests from those subcontractors for additional funds to complete the project.

Often subcontractors do not have their own on-site superintendent on the job site for the entire day. This plagues projects with cost and completion problems for both the GC and subcontractors.

Workers are fantastic story tellers when it comes to conversations with their boss. When the boss is on the phone they believe that the worker is telling a valid story. This is why GC Superintendents should take a lot of photos to document issues.

I always review the parking area to identify whether my subcontractors showed up or left early. There are many unscrupulous acts performed off-site during paid hours. Workers sneak off to go fishing, shopping, meet up with friends, or just hang out at their truck. The work that wasn't performed and the amount of hours it should have taken to complete that days work is later represented in a request for a Time Extension, Change Order, or a Post-Fulfillment Invoice.

When a superintendent pays close enough attention to who is actually working the "whole" day, the likelihood of labor cost overruns is reduced.

Improperly prepared for the task is another reason for labor cost overruns. Concrete saw cutters that don't bring new blades, or enough blades for the project, sometimes will try to sharpen what they have to avoid buying new blades like they were supposed to do in the first place. The contractor will be billed for the time spent sharpening blades if the Superintendent doesn't photograph and log the fact that the event happened.

Other tradesmen also waste time on-the-clock by showing up without the proper tools or materials and then head out to go shopping. This is where communication with the subcontractor's office needs to be very clear as to what you need when you request work, and another call in the event that you are billed for "shopping".

Long winded workers can also burn down the clock on paid time. When workers aren't provided a daily quota of work completion they generally don't care what they don't get done.

Workers taking additional paid breaks from working to smoke cigarettes or have cell phone call conversations can spend up to five hours or more per person a week being unproductive.

Lunch breaks are another problem area if the employer hasn't set exact leave and return times for workers. It isn't just that there is a loss of production time, the worker believes that they should be paid for the time they were not in their work area working. Workers that decide to not take a break, but do eat at the work area are still stopping work to gobble down their lunch. Employers are held to labor laws and it really doesn't pay nor is it productive to allow workers to eat and work at the same time if they are in construction or manufacturing.

Often these time abusers have a sense of entitlement and expect to be paid when they aren't working and instead smoking, talking to their family/friends, waiting in a restaurant line, working out at a gym and even sleeping on the job.

All work hours that are wasted are still needed to complete the work. This is a good reason why I don't fraternize very long with any worker.

When job site workers take note that the GC Superintendent is documenting unproductive time and forwarding it to all of the subcontract holders, the workers tend to act more responsibly at the site. Especially when it's accompanied by a disclosure that reads "lost time = ( ) this week, no additional hours or time extension will be granted for associated subcontracts".

When a superintendent is not aware of the root cause of labor cost overruns, he simply isn't paying much attention to what is happening at his site.

Documenting issues by photographing, logging, and emailing issues that could create a cost overrun has resulted in contractors pushing their employees to work more efficiently on the job site to meet time and cost constraints as outlined by their contract.

The benefit to being aware of your job site labor output on an hourly basis, reduces labor cost overrun liens as the project closes up.



要查看或添加评论,请登录

Laura A.的更多文章

  • Mental Health in the Workplace

    Mental Health in the Workplace

    MENTAL HEALTH IN THE WORKPLACE If you've been paying attention to society's problematic issue with getting along and…

  • Everything I learned from my cats

    Everything I learned from my cats

    Everything I learned from my cats: Five years ago I adopted an older cat who was timid at first and then warmed up to…

  • This little thing called equity

    This little thing called equity

    This thing called “equity” I grew up in southern California, streets lined with houses and crowded apartments. People…

  • This little thing called "fair"

    This little thing called "fair"

    This little thing called “fair”. By the age of two or three I was hit by a car and I was fortunate to be thrown into…

  • Should "race" be replaced with "ethnicity"?

    Should "race" be replaced with "ethnicity"?

    Be sure to scroll down to see the USA Population of PEOPLES Separating people into groups to figure out which group is…

  • Business Soup - Aftermath of Riots

    Business Soup - Aftermath of Riots

    2019 was a great financial year for most people until 2020 rounded the corner with COVID19, law enforcement officer…

  • America's workplaces - Surviving Hardships

    America's workplaces - Surviving Hardships

    Workplaces are filled with people with various cultural background experiences. The person next to you could have been…

  • What is Fair?

    What is Fair?

    Fair - A Word That Often Is Shunned If there is a word that fuels opinion more than any other word it’s the word…

  • Know your history - Why Women Are Paid Less

    Know your history - Why Women Are Paid Less

    Why have women traditionally been paid less and why do some males and females think it’s acceptable? We have to delve…

    4 条评论
  • Women in the Workplace - Should they win the equality fight?

    Women in the Workplace - Should they win the equality fight?

    Companies throughout the U.S.

    2 条评论

社区洞察

其他会员也浏览了