Key Insights on Easements in Subdivision Design

Key Insights on Easements in Subdivision Design

Purpose and Importance of Easement Regulations

Easements are essential for protecting public utilities and ensuring access. The Brisbane City Council’s Subdivision and Development Guidelines and the Queensland Urban Drainage Manual (QUDM) both emphasize the importance of easements. Key purposes of easements include:

  • Protection of critical infrastructure
  • Ensuring accessibility for maintenance
  • Supporting sustainable development


Project Considerations Regarding Easement Standards

In this subdivision development project, easements were required for certain areas along the rear and side boundaries. Specifically, the rear boundary required a 3.0m-wide easement, and the side boundary required a 1.0m-wide access easement.

Roofwater Pipe Side Boundary Easement Width Requirements (BSD-8111)

First, I analyzed the design contours to identify lots with a rearward grade, determining which areas needed easements. The rear easement area accommodates both Roofwater and Sewer pipes, so I designed it with the 3.0m offset requirement for Sewer pipes to ensure adequate space for both utilities.

While following the assignment workbook’s guidelines would have sufficed, I consulted the Brisbane City Council (BCC) Subdivision and Development Guidelines for further insight.

The workbook suggested a 1.0m width for side easements, but BCC guidelines specify that 225mm to 300mm pipes require a 1.5m easement in favor of the Council.

Excerpt from Brisbane City Council (BCC) Subdivision and Development Guidelines

Therefore, I concluded that applying a 1.5m width along the side boundary from the front road to the rear of the lot would be more appropriate for standard compliance. However, in areas where Sewer and Roofwater pipes run together, a wider easement would be advisable.

Additionally, using the Queensland Urban Drainage Manual (QUDM) Roofwater Guidelines, I calculated that the appropriate pipe diameter for Level III drainage would range from 225mm to 375mm, confirming that a 3.0m easement for the rear boundary was suitable.

Using Design Contour Xref in CAD to Calculate Pipe Diameter for Level III Drainage
Calculation for Roofwater Pipe Dimensions in My Project

Note: QUDM is a paid resource, so specific tables are not reproduced here.


Applying Urban Utility Guidelines for Sewer Infrastructure

In this project, sewer infrastructure was assumed to be managed by Urban Utility (U.U.). Therefore, I reviewed U.U.’s requirements for sewer easements and access points for maintenance. Based on manhole type, the following easement standards were applied:

  • Access to sewer maintenance structures: A 1m-wide access route along the side boundary
  • G-type manhole: A 1.5m x 1.5m centered easement
  • F-type manhole: A 1.7m x 1.7m centered easement
  • X-type manhole: A 1.7m x 1.7m centered easement

This experience emphasized the need to recognize the different standards of each utility authority (CoGC, LCC, RCC, UQQ, UW, etc.) and to ensure minimum requirements are met in easement drawings.


Comparing Standards of Various Utility Management Authorities

In subdivision projects, several authorities, such as CoGC, LCC, RCC, UQQ, and UW, each have unique easement standards and requirements. Thus, designers need to identify the managing utility authority for each region and adjust designs accordingly.


Lessons Learned and Future Applications

This project helped me gain a solid understanding of what easements are and their purpose. It was rewarding to gain hands-on experience with multiple standards, such as those of the City Council, SEQ Code, and various service management companies, when preparing drawings.