Inside the Evaluation Room
SRMhub

Inside the Evaluation Room

It is important for suppliers to understand the adjudication process when one is responding to a Tender or Request for Proposal. The evaluation committee will largely be guided by these steps. Understand the process and you most likely will get a chance to proceed to the next round. Whether the process is manual or computerized, these stages will be observed.

Opening and recording of tenders

When tenders are opened, the features of each tender usually are announced and recorded include the name of the bidder, bid price. Tenders usually are endorsed and dated with the approved tender stamp of the organization.

Checking responsiveness

The evaluation officials will determine the whether or not tenders offers are complete by checking:

·        The tender complies with all the conditions of the tender or RFP;

·        The tender has been properly completed and signed;

·        The tender meets the minimum resource objectives;

Above are just some of the requirements that have to be met in order for your response to advance in the tender process. Any tender that does not meet the stipulated requirements will be regarded as being non-responsive and eliminated at this stage. All responsive tenders will proceed to the next stage.

Price Review

The prices of all responsive tenders are checked for errors. Bidders who have tendered an unrealistically low price can be interviewed to determine whether there is a valid reason for its tender price being unrealistically low. If the bidder cannot supply a valid reason, the tender would most probably be eliminated.

Award of points for Functionality

Tenders that remain in contention will be awarded points for functionality (technical review) based on a pre-set criteria.

Awarding of points for Price

At this stage the points for price will be awarded according to a pre-set criteria. Prices are usually adjusted to a common base so that it can be comparable with each bidder’s price.

Summation of points

The points awarded for price will be added for each tender and, subject to satisfactory risk analysis; the tender which has been awarded the highest total number of points will be recommended for acceptance.

Risk Analysis

An Organ of State will do a risk analyses and due diligence before acceptance of any tender to ensure that it would, if accepted, not place the organization or the tenderer, at undue risk.


Iyaya Kiveu

Supply Chain Management Specialist |MKISM| CPSP-K

6 年

At what stage does due diligence come in? Is it at the preliminary stage before proceeding to financials?

回复

要查看或添加评论,请登录

Franklin Njeru的更多文章

  • ESGs - We All Have a Role to Play

    ESGs - We All Have a Role to Play

    The greatest threat to our planet is the believe that somebody else is going to do it. In the last few months, all our…

  • Is procurement getting better?

    Is procurement getting better?

    There were traces of procurement in 3000BC with some bit of materials management that was needed during construction of…

  • Simplify Your Purpose for Resilience

    Simplify Your Purpose for Resilience

    Why am I here? This is the simple question we try to answer with our life purpose except it gets complicated when we…

  • Let Us Build a Taxi App Business in 400 Words

    Let Us Build a Taxi App Business in 400 Words

    Taxi service apps are fast replacing the traditional cab services, they are here to stay. If you are wondering if there…

    1 条评论
  • How to monetize your application - Revenue models

    How to monetize your application - Revenue models

    Many people have asked us how they can monetise the software projects they are working on. Our quick answer is usually…

  • easy contracts Features for Success

    easy contracts Features for Success

    easy contracts offers tangible benefits to organizations, enabling the tracking and management of full contract…

  • Benefits of Digital Contract Management System

    Benefits of Digital Contract Management System

    Last year I overheard a conversation between CEO and operations manager from one of our clients’ organization that went…

  • Using Contracts to Prevent Maverick Spend

    Using Contracts to Prevent Maverick Spend

    Procurement spends a lot of time agreeing contracts with suppliers. Despite of all procurement’s effort, staff often…

    1 条评论
  • How to Solve Contract Management Problems

    How to Solve Contract Management Problems

    Not so long ago, I sent a copy of contract we have with one of our clients after a request from their office. The…

    2 条评论
  • KISM Members Obligation When Electing Leaders

    KISM Members Obligation When Electing Leaders

    The members of KISM (Kenya Institute of Supplies Management) the body governing procurement profession in Kenya shall…

社区洞察

其他会员也浏览了