Measurement Audit Procedures For Vendors

?

The result of measurement audit is to determine acceptance based on ANSI/ASQC Z1.4 (MIL-STD-105E) Normal Single Sampling Plan, Level II, AQL 2.5 for major & minor defects.

?

·?????Major defect – A POM that jumps a size, i.e measures as the next size, bigger or smaller, or more is to be marked with a ? “Triangle”.

·?????Minor defect - A POM that is out of spec tolerance but does not exceed the next size, bigger or smaller is to be marked with a ○ “Circle”.

?

Pre-production meeting

Factory must check samples (pp samples, jump size sets) for all measurement points listed in Kohl’s measurement specifications and keep a record of the details prior to pre-production meeting as these will be review by a responsible Vendors ?QA to ensure any out of specs measurements are rectified before pilot run starts.

Pilot Run audit?

During pilot run, a factory must measure at least 2 pieces of garments per size for all available colors on all points listed in measurement specification and keep a proper record which should be analyzed for any recurring out of specs measurement trend. Any recurring out of tolerance measurement points are to be rectified prior to bulk production.

Vendors QA must review and monitor for rectification of the recurring issue/s and that factory is following through in bulk production.

?

Inline measurement audit

For non-wash items - at least one piece per size per color must be measured on all measurement points from the first output from bulk production.

For garment-washed items - measurement must only be taken after 1st Bath washing and pressing ie after a garment is finished. At least one piece per size per color must be measured on all measurement points.

Measurement results taken from inline measurement audits may be consolidated into final measurement audits at shipment.

Final measurement audit



The acceptance of a final shipment measurement audit is based on ANSI/ASQC Z1.4 (MIL-STD-105E) Normal Single Sampling Plan, Level II, AQL 2.5 for major & minor defects.

The following table provides details on sample size to be audited at final shipment audit:

ANSI/ASQC Z1.4 (MIL-STD-105E) Normal Single Sampling Plan, Level II,

* Note

1.????All colors & sizes must be covered within the sample size.

2.????If all colors and sizes cannot be covered by the 1st sample size, the auditor must select the next sample size. Please see example as follows :

?

Example 1

Shipment has 2 colors and 5 sizes. Auditor will pick sample size as follows:

Color 1 - 2 pieces x 5 sizes = 10 pieces

Color 2 - 2 pieces x 5 sizes = 10 pieces

Total sample size is 10pieces + 10 pieces = 20 pieces

?

Example 2

Shipment has 2 colors and 6 sizes. Auditor will pick a sample size as follows:

Color 1 - 2 pieces x 6 sizes = 12 pieces

Color 2 - 2 pieces x 6 sizes = 12 pieces

Total sample size is 12 pieces + 12 pieces = 24 pieces.

Therefore the auditor must pick a sample size of 32 pieces to be compliant to the standard.

?

Example 3

Shipment has 5 colors and 4 sizes. Auditor will pick a sample size as follows:

Color 1 - 2 pieces x 4 sizes = 8 pieces

Color 2 - 2 pieces x 4 sizes = 8 pieces

Color 3 - 2 pieces x 4 sizes = 8 pieces

Color 4 - 2 pieces x 4 sizes = 8 pieces

Color 5 - 2 pieces x 4 sizes = 8 pieces

Total sample size is 8 pieces x 5 = 40 pieces

Therefore the auditor must pick a sample size of 50 pieces to be compliant to the standard.

hasan samir

Heather Tex EGYPT

1 年

Hello. We are the manufacturer of readymade garments in Alexandria. We are looking for a customer for the Alexandria factory

回复
Md. Junayed nahid

Resarch and Development Wash Technician

1 年

Good work

回复
????. ?????? ?????????? ????????

MBA In Fashion Design & Technology . Armani Exchange || DIESEL|| GAS || OAKLEY || BATA

1 年

Thanks for sharing sir?? Inspiring!

要查看或添加评论,请登录

MOHAMMAD SHAMIM HOSSAIN的更多文章

  • Never Give UP

    Never Give UP

    Turn your hopes and dreams always into action. The Future belongs to the dreamer.

  • TE- Technical Audit

    TE- Technical Audit

    TE (technical Evaluation) /Factory audit? TE is the most important event for starting the production in the factory. If…

  • Habits

    Habits

    3 Habits can change QA life: HABIT1: Be Proactive - We need to be set up our plan based on our Goal. Example: 1)Before…

    6 条评论
  • To Understating Lean in a short

    To Understating Lean in a short

    To Understating Lean in a short Lean : A road map to achieve Zero wastage. Lean Manufacturing is a set of tools and…

    1 条评论
  • Garment Washing

    Garment Washing

    GARMENT WASHING Definition :- The technology which is used to modify the appearance, out look comfortability & fashion…

  • SOP for Cutting

    SOP for Cutting

    · All Knit and woven with elastane must be relaxed 24 hours. · Fabric will transfer to the cutting section only after…

  • Hard-goods - Sample Check Procedure

    Hard-goods - Sample Check Procedure

    Contract Seal Sample Check Procedure : 1) First Need to Collect the style information & photo reference of contract…

  • Let's learn how to denim shades Control

    Let's learn how to denim shades Control

  • Trimcard -Protocols

    Trimcard -Protocols

    To assure Fabric & Trims which are going to be used for production are approved by the Buyer / Merchandiser .Every Trim…

  • Carton Audits -SOP

    Carton Audits -SOP

    Carton audit is the last process for a factory to review the final appearance of the product & SKU. This is the…