Inergystat- Renewable Energy Sector - March 2020 in Minutes

Inergystat- Renewable Energy Sector - March 2020 in Minutes

Check out the important news of the Renewable Energy sector happened during March 2020:

Along with this MNRE also finalized contours for setting up of 25 GW renewable energy park in the Khavada village of Gujarat.

The trend during previous years are: Rs 79,606 crore in 2018, Rs 81,080 crore in 2017, Rs 1,00,982 crore in 2016 and Rs 72,972 crore in 2015.

Now treating letter of comfort issued by PFC, REC, and IREDA would reduce procedural delay to seek bank guarantee for bidding for clean energy projects.

The ministry also ordered SECI and NTPC to pay safeguard and GST pass through on an annuity basis to further ease the financial stress being faced by RE investors.

This move is now the state’s first successful attempt to achieve greater load flexibility at its coal-based project to boost the integration of renewable power into its mix. According to the Greening the Grid (GTG) Program these low-load tests will allow the power generators to more easily adapt their generation when the need for integrating more renewable energy in their mix arises.

The low load test run was conducted under a pilot implemented under USAID’s GTG – Renewable Integration and Sustainable Energy (RISE) initiative in partnership with GSECL and Bharat Heavy Electricals Limited (BHEL), which is the Original Equipment Manufacturer.

The panel expressed concerns that the ministry may also find it difficult to achieve 175 GW target by 2022.

For the years 2017-18 and 2018-19, against the grid-connected renewable energy target of 14,445 MW and 15,355 MW, the Ministry could achieve 11,876.82 MW and 8519.52 MW, respectively. Similarly, during the year 2019-20 (up to January 2020), 8,004.64 MW could be installed against the target of 11,852 MW. it said.

On budgetary allocation for the renewable sector, the committee said an allocation of Rs 9,523.04 crore was sought by the Ministry for the year 2020-21, but only Rs 5753.00 crore have been sanctioned.

He further added that most of the grid-connected renewable energy projects are being implemented by private sector developers selected through a transparent competitive bidding process.

  • MNRE has issued a directive to SECI, NTPC, and state government departments, in which it is mentioned that there will be no tariff cap on renewable energy project auctions, with the government deciding to do away with the upper ceiling — a move it hopes will boost investment in solar and wind power projects.

The move comes after industry requested the government to remove the ceiling on the bidding. Several states and SECI have a capped tariff rate, beyond which companies cannot quote while bidding for solar and wind power projects.

The tariff caps ranged from Rs 2.9 per unit by SECI in some solar power tenders in 2019 to Rs 3.5 per unit by some states such as Maharashtra, Rajasthan and Uttar Pradesh. This led to a lot of tenders going undersubscribed or drawing no interest from industry which found the caps to be too low. An industry expert mentioned that the prevailing market conditions made the projects unviable for companies. 

In the same notice, MNRE also directed SECI, NTPC and the state power departments to procure renewable energy either through the single renewable source or various combinations of renewable sources with or without storage as per their procurement policies.

The India-Sweden Collaborative Industrial Research & Development Programme is co-funded by Indian Department of Science & Technology (DST) and Swedish Energy Agency.

The program aims to bring together companies, research organizations, academics and other collaborators from both countries for the joint development of innovative products or processes.

That takes total installed RE capacity according to MNRE, to 86.32 GW as of January 31, 2020. Wind leads with 37.61 GW, Solar power at 34.03 GW, with Bio-Power at 10 GW and small hydro at 4.68GW bringing up the rest.

On the expenditure front, the ministry reports spending Rs 3152 crores till January, which is 84.21 percent of the revised estimate for it for the year till March 2020.

The report also highlights projects of 35.09 GW under various stages of implementation, and a further 34.47 GW in the bidding pipeline.

Auctions have been completed for about 4.9GW of tenders. Moreover, about 364MW of new solar capacity and 107MW of new wind capacity is added.

The combined generation from solar, wind, small hydro, biomass, bagasse, and other sources stood at 10.647 BU in December 2019, as against 9.083 BU of green energy generation recorded for the same month in 2018.

India installed 2,308 MW of solar and 817 MW of wind energy generation capacity in the fourth quarter of 2019.


Register with us at Inergystat.com to receive daily news and important updates directly in your mail.

You can join us our Telegram group exclusive for Renewable Energy by clicking here

要查看或添加评论,请登录

Inergystat India的更多文章

社区洞察

其他会员也浏览了