The Importance of a Basis of Estimate (BOE) in Estimating
Andrew Kleimola
Every successful construction project starts with a GREAT estimate!
In the world of construction estimating, accuracy is key—but numbers alone don’t tell the whole story. Every estimate is built on a foundation of assumptions, methodologies, and defined scope, which must be communicated clearly to ensure all project stakeholders are on the same page. This is where the Basis of Estimate (BOE) plays a vital role.
An estimate is much more than a number; it’s a comprehensive document that helps project stakeholders make well-informed decisions. Without the supporting narrative of a BOE, those numbers could be misleading, leading to poor decision-making, project delays, or budget overruns. A BOE provides clarity, transparency, and a detailed breakdown of how the estimate was constructed, what assumptions were made, and what risks were considered. It is a critical communication tool that transforms the estimate into a valuable resource for all stakeholders involved.
Why is the BOE Essential?
1. An Estimate is More Than Just a Number
One of the most critical misconceptions in construction is that an estimate is simply a figure—an end result that tells the project cost. In reality, an estimate is a living document that represents much more than just the cost projection. It provides the framework for key decisions, including scope adjustments, resource allocation, and risk management.
Without a Basis of Estimate (BOE), stakeholders run the risk of making decisions based on "numbers" that don’t reflect the reality of the project. For instance, a stakeholder might assume certain contingencies or allowances are included in the estimate when they are not. This can lead to inaccurate cost projections and unrealistic expectations. By providing a transparent, detailed explanation of how the estimate was built, a BOE ensures that everyone understands what the numbers truly represent and can make decisions accordingly.
2. Clarity and Transparency
A well-prepared BOE brings transparency to the estimating process by explaining the methods, assumptions, and data behind the numbers. This clarity reduces the chances of misunderstandings or disputes down the line. When changes or questions arise during the project, stakeholders can refer to the BOE to understand exactly what was included, excluded, or assumed during the estimating process.
For example, if unforeseen conditions lead to cost increases, the BOE can help determine whether these were accounted for in the initial estimate or if additional adjustments are required. Without a BOE, these discussions become speculative and open to interpretation, which can lead to project delays or costly disputes.
3. Documenting Assumptions
Assumptions are unavoidable in any estimating process. Whether it’s assumptions about material prices, labor availability, or weather conditions, they play a critical role in shaping the final estimate. A well-documented BOE clearly lays out these assumptions so that they are transparent to all stakeholders. This way, if circumstances change—such as a fluctuation in material costs—the BOE provides a reference point for what was originally assumed, making adjustments easier and more straightforward.
Without this documentation, changes in the project environment can lead to confusion, miscommunication, and a misalignment of expectations between the project team and the client.
4. Risk Management
Risk is inherent in any construction project, but by incorporating risks into the estimate and documenting them in the BOE, the estimator can ensure that stakeholders are aware of potential challenges. Whether it’s accounting for material price volatility or potential project delays, including risks in the BOE helps stakeholders anticipate and plan for these uncertainties.
The BOE not only highlights what risks have been considered but also explains how they were addressed in the estimate, such as through contingencies or allowances. This helps stakeholders manage risk proactively, rather than reacting to problems as they arise.
5. Estimate Validation and Reconciliation
Estimates often undergo validation and reconciliation, either between project teams or with third-party consultants. A BOE provides the essential context needed to validate the numbers. It explains how quantities were measured, what pricing data was used, and what assumptions were made, making it easier to compare different estimates and reconcile discrepancies.
When multiple parties are involved, such as during value engineering or project audits, a BOE ensures that all parties understand the foundation of the estimate, preventing disagreements and fostering productive discussions.
6. Project Control and Accountability
Throughout the course of a project, the BOE serves as a reference point to monitor cost changes and ensure accountability. As scope changes or unexpected conditions arise, the BOE can be consulted to determine how the initial estimate was built and whether adjustments are necessary. By having a documented BOE, the project team can hold themselves accountable to the original estimate and justify any deviations with data and rationale.
A BOE also helps maintain control over the project’s budget. As cost estimates are revised, the BOE helps stakeholders understand how and why changes were made, ensuring that budget discussions remain anchored in the original scope and assumptions.
7. Improved Communication
A BOE is more than a technical document for estimators; it’s a communication tool for the entire project team. By providing a clear narrative that explains how the estimate was developed, the BOE helps both technical and non-technical stakeholders understand the complexities behind the numbers. This is particularly important when communicating with clients or investors, as it bridges the gap between the cost estimate and the decision-making process.
SAMPLE Basis of Estimate (BOE) TEMPLATE
Prepared by: [Estimator Name]
Date: [Insert Date]
Estimate Type: [Conceptual/Schematic/Design Development/Final]
Estimate Level of Accuracy: [+/- X%]
1. Project Scope
2. Assumptions and Clarifications
3. Inclusions and Exclusions
4. Methodology
5. Contingency
6. Cost Breakdown
7. Risk Factors
8. Escalation
9. Schedule Considerations
10. Allowances
Conclusion
A Basis of Estimate (BOE) transforms a simple number into a powerful communication tool that enables better decision-making, manages risk, and provides transparency. It ensures that all stakeholders understand the assumptions, methodology, and scope behind the estimate, making it easier to reconcile cost discrepancies and maintain control over the project’s budget.
In today’s fast-paced construction environment, having a well-documented BOE is more than just a best practice—it is a necessity. By adopting and consistently using a structured BOE, estimators and project teams can protect themselves from misunderstandings, ensure accountability, and drive project success.
Passionate about program planning / cost
2 周an excellent article on the importance of both having a BOE and getting concurrence that the client understands it. you are hired!
Sr. Estimator at Langston Construction Company
4 周Well put, thanks for sharing!
I am now located in New Jersey & looking to continue to build relationships with clients on the East coast.
1 个月It's a key element of determining any estimate and its value. Great narrative, which sadly many don't often appreciate, or in some cases even want to consider.
Well stated. Spread the word. It’s important to communicate and manage expectations
Passionate about program planning / cost
1 个月Insightful. Everyone focuses on the number and seldom do they look at the Basis. Estimate number should also be thought of as a range; when you get bids, it’s not one number. It’s an accumulated risk profile.