"IDK how long it will take"
I followed all the right steps. Experts shared their views that my project plan was workable. The people doing the work agreed it was good. The resources were available... and yet, somehow... the longest duration task ran 50% longer than planned.
What went wrong? Insufficient work breakdown ("chunking") and poor measurement.
I learned my lesson. On the next project facing the same large task, I broke it down into smaller sections. I assigned an owner to each section and got all the same input and advice to ensure it was doable. I made something like a burndown chart and I scheduled weekly standup's to review progress. This time, the total activity ran even longer. Late again.
What went wrong? The smaller sections of work were iterative and never wrapped-up they way I expected; loose ends were everywhere and came back.
I learned my lesson. On the next project, I engaged by subject matter experts more heavily to review the quality of work and ensure the technical debt was reasonable. I asked them to subjectively assess the "pace of work" for each section, rather than driving towards specific deadlines. The result? Closer to on time, but still late.
What went wrong? I'm not sure. A dozen issues together, perhaps. Team friction, confusion, unnecessary rework, etc.
领英推荐
I learned my lesson. Some things just can't be measured or predicted well. There are too many variables, too many inputs, too many options.
In these situations, it's better to work at the fringes of the problem just much as you hit it directly. For example:
This isn't a great solution. But sometimes you just don't know how something will go so you can't predict it's duration. Just make the next best choice and maintain a sense of urgency.
密歇根软件实验室的联合创始人和管理合伙人。福布斯科技委员会成员。财富 500 强公司的 Frequest 作家和演讲者。
1 年I'm glad you are starting to write more helpful articles like this, Matt. And you are so right about being incremental in your work...the best way to eat an elephant is one bite at a time.