Great way to prepare Recovery/Revised time schedule when Activity % complete is duration type-Rev-01

Great way to prepare Recovery/Revised time schedule when Activity % complete is duration type-Rev-01

The Propose of this paper is specified for recovery/Revised schedule issues when dealing with activity % complete type equal Duration as the strong relation between duration and Activity % complete distracts the earned value and All progress % complete.

The paper completed the common method when using physically % complete type.

When you have EOT approval or delays occur and requested to submit Recovery/revised schedule, the following steps is the fastest way for prepare the new Baseline:

1-????Firstly solve out-of-sequence activities according to the new methodology with any method of solving, to make sure that all relationships are satisfied.

2-????Add activity Code with name “Splitting Activities” then assign the In Progress activities to the New Activity Code (Completed one), further to easy work or review.

No alt text provided for this image

?3-?Export the in progress activities to excel sheet with the following fields and filter in progress activities (Activity ID, Activity Status, WBS Code, Activity Name, Activity % complete, Duration Type, Any assigned Activity codes). Make sure that you filtered the In progress activities

No alt text provided for this image
No alt text provided for this image


4-????Open the excel sheet then Copy the activities to new cells. (Save a copy for the sheet to be used later).

5-????Change the New activity % complete to subtract 100%-Actual % complete.

6-????Using CONCATENATE Function you can change the Activity ID and Activity Name: - Add “Rem” to Activity ID, Add % complete to in progress activities with actual % complete, Add Remaining % complete to new activities.

No alt text provided for this image
No alt text provided for this image


7-????Change the In progress activities from in progress to Completed and change the new activities to Not Started.

8-????Import the excel sheet to primavera File.

9-????Apply the filter of Activity ID contain “Rem” activities and assign splitting Activities code (Remaining).

No alt text provided for this image

?

10-??Apply the Filter on the Activity Code “splitting Activities” Completed ones, Make the finish date = Data Date-1.

11-??Assign the Old activity to be the predecessor for the new one (Same split activities)

12-??In my opinion the program is considered a revised or recovery one so there's must be a new sequence to catch you new milestones dates so the old relationships between activities is still not valid, but If you need to Assign the Same successors for the new activities from the old activities (be in the old activity successor tab, select all Successors, press assign, be on the new activity press assign). Note: take in your consideration that the successor activities to be the "Not started" activities. Maybe find more easy solution in the next revision.

13-??Please Check/solve the few new out of sequence if any and adjust the new relation if any.

14-??Now you have Recovery plan with only two activity status (Completed or Not started), use the new activities to start your critical/non critical paths.

15-??For modify the Cost/Weight/man-hour or any assigned resources follow the below steps:

  • 15.1. Assign the Cost/Weight/man-hour to the new split activities
  • 15.2. Export the activity that under activity code “split Activities” as activities and Recourse assignment.
  • 15.3. Adjust the completed activities budget units by multiply the Actual % complete with original budget unit.
  • 15.4. Adjust the new activities budget units USE VLOOKUP function.
  • 15.5. Adjust the new activities budget units by multiply the remaining % complete with original budget unit.
  • 15.6. make sure that the total budget unit equal the original total budget units.
  • 15.7 Finally apply global change equal planned values with actual for the complete activities.(PL start=start, PL finish=Finish and OD=AD)

Ahmed Kamel, B.Sc,MSc

SR.Contracts Engineer

3 年

Brilliant

Samy Hassanin

Planning & Control Manager ‖ MCIOB?, MCIArb?, RICS (Expert Witness), MICCP?, PMO-CP?, PMI-PMOCP?, MSc, BTEC L7 Forensic Delay Analysis, CMAD? (AUC), FIDIC Modules?‖ Claim Specialist.

4 年

good job

Great effort Ahmed Abouelnaga, PSP.. Salute to your efforts..?????????????? I'm big fan of doing this approach for dor my revised and recovery schedule.. At times I have even used for EOT schedule the same approach..

Ali Raza, BSc Civil Engineer, AssocRICS, PMP?

Contract Administrator, Planning Engineer, EOT, FIDIC Contracts, Variations, Claims, Delay Analyst, Dispute Adjudication Board (DAB)

6 年

Good Post!! I took a little different approach for 500 in progress activities it took about 15 minutes...