Great way to prepare Recovery/Revised time schedule when Activity % complete is duration type-Rev-01
Ahmed Abouelnaga, PSP, PMP,PRMG
Sr. Planning and Risk Manager at Egis, PMP, PSP | Forensic analysis | Construction Management | Primavera | Power bi | Project controls | Reporting
The Propose of this paper is specified for recovery/Revised schedule issues when dealing with activity % complete type equal Duration as the strong relation between duration and Activity % complete distracts the earned value and All progress % complete.
The paper completed the common method when using physically % complete type.
When you have EOT approval or delays occur and requested to submit Recovery/revised schedule, the following steps is the fastest way for prepare the new Baseline:
1-????Firstly solve out-of-sequence activities according to the new methodology with any method of solving, to make sure that all relationships are satisfied.
2-????Add activity Code with name “Splitting Activities” then assign the In Progress activities to the New Activity Code (Completed one), further to easy work or review.
?3-?Export the in progress activities to excel sheet with the following fields and filter in progress activities (Activity ID, Activity Status, WBS Code, Activity Name, Activity % complete, Duration Type, Any assigned Activity codes). Make sure that you filtered the In progress activities
4-????Open the excel sheet then Copy the activities to new cells. (Save a copy for the sheet to be used later).
5-????Change the New activity % complete to subtract 100%-Actual % complete.
6-????Using CONCATENATE Function you can change the Activity ID and Activity Name: - Add “Rem” to Activity ID, Add % complete to in progress activities with actual % complete, Add Remaining % complete to new activities.
领英推荐
7-????Change the In progress activities from in progress to Completed and change the new activities to Not Started.
8-????Import the excel sheet to primavera File.
9-????Apply the filter of Activity ID contain “Rem” activities and assign splitting Activities code (Remaining).
?
10-??Apply the Filter on the Activity Code “splitting Activities” Completed ones, Make the finish date = Data Date-1.
11-??Assign the Old activity to be the predecessor for the new one (Same split activities)
12-??In my opinion the program is considered a revised or recovery one so there's must be a new sequence to catch you new milestones dates so the old relationships between activities is still not valid, but If you need to Assign the Same successors for the new activities from the old activities (be in the old activity successor tab, select all Successors, press assign, be on the new activity press assign). Note: take in your consideration that the successor activities to be the "Not started" activities. Maybe find more easy solution in the next revision.
13-??Please Check/solve the few new out of sequence if any and adjust the new relation if any.
14-??Now you have Recovery plan with only two activity status (Completed or Not started), use the new activities to start your critical/non critical paths.
15-??For modify the Cost/Weight/man-hour or any assigned resources follow the below steps:
SR.Contracts Engineer
3 年Brilliant
Planning & Control Manager ‖ MCIOB?, MCIArb?, RICS (Expert Witness), MICCP?, PMO-CP?, PMI-PMOCP?, MSc, BTEC L7 Forensic Delay Analysis, CMAD? (AUC), FIDIC Modules?‖ Claim Specialist.
4 年good job
Sr Planning & Projects Control Engr
5 年Great effort Ahmed Abouelnaga, PSP.. Salute to your efforts..?????????????? I'm big fan of doing this approach for dor my revised and recovery schedule.. At times I have even used for EOT schedule the same approach..
Contract Administrator, Planning Engineer, EOT, FIDIC Contracts, Variations, Claims, Delay Analyst, Dispute Adjudication Board (DAB)
6 年Good Post!! I took a little different approach for 500 in progress activities it took about 15 minutes...