How to optimize Horizontal Directional Drill (HDD) and Jack Bore Installation Pipeline Projects

How to optimize Horizontal Directional Drill (HDD) and Jack Bore Installation Pipeline Projects

Pipeline construction by trenchless methods including horizontal directional drill (HDD) and Jack and Bore have become increasingly prevalent to minimize pavement cuts, maintain surface traffic, and reduce restoration costs.?Some entities, especially railroads, have valid concerns of these installations with regards to inadvertent mud returns during HDD installations and risks for settlement under their facilities resulting from HDD and Jack and Bore projects.

It is critical to consider the HDD or Jack and Bore at the appropriate depth of cover and soil layer. Using software and engineers with experience in the design of HDD’s, analysis of the risk of the inadvertent mud returns and recommendations of mud pressure limits can reduce the chance of these to occur.?

Soil conditions for HDD’s Jack and Bores can also be evaluated to determine if there are concerns that could cause more soils to be excavated from the boring process and that could result in the settlement or collapse of the ground at the crossing.?The performance of engineering studies of the soil or rock layers can determine the collapsing risks during the drilling and installation process of the crossings. This is, in many cases, a recommended approach for early stages.

As part of construction planning, a soil monitoring plan can be developed to understand the soil that is being excavated from beneath key facilities, to verify that an over-excavation is not occurring.?The plan should list the expected soil removal in regular increments, associated with the boring machine capabilities and method for measuring the soil removed from the Jack and Bore excavation, compared to the expected value.?

Geotechnical engineers can also evaluate the soil or rock being excavated, or the amount of ground water that is being extracted from these crossings, to determine if conditions are different from the soil borings and rock cores.?These findings are then evaluated to determine if there are concerns that could affect the crossing to be completed safely as designed.

Another feedback measure gathered during the installation process and typically a required practice for rail crossings, are surveys for elevation monitoring of the crossing area. These are completed to identify any impact to the grade elevation above the bore, particularly for the rails.?These measurements would identify if there are any changes in grade elevation during the construction of the pipeline bore, that could cause a concern.

The above, are all detailed but key considerations that will allow the progression of project completion in safe conditions, for which an investment with the right expertise, will avoid downstream unexpected costs.


Robert Brunetti, PE, VMA

Solution Oriented Capital Programs and Strategic Growth Executive

2 年

Very insightful Jeremiah! You and the rest of the Patrick team have done a great job in integrating our civil/geotech, railroad engineering, and pipeline expertise for HDD and Jack and Bore, and have been particularly successful around sensitive properties. We've had more than a few projects where we were brought in to correct a situation for a client under emergency conditions. Through these experiences we have develop a number of different means and methods for better planning, monitoring and management of such projects.

Christopher Baldwin

Construction Inspection Observation

2 年

Oops. Sorry. Great Article Jeremiah!

回复
Christopher Baldwin

Construction Inspection Observation

2 年

Matt. Great article.

回复
Brian Walsh

Vice President of Business Development at ICC Group

2 年

Great article Jeremiah!

回复

要查看或添加评论,请登录

社区洞察

其他会员也浏览了