How Long Are Permits Taking?
Milrose Consultants secures approvals in all 50 states

How Long Are Permits Taking?

Keep in mind that durations can change quickly and the process involves initial submittal preparation, first review duration, multiple rounds of review, additional outside departments required, fee payments, and city or client delays.

It’s important to have a team that doesn't miss steps and information to avoid unnecessary delays.

This is critical to meet project schedules.


Register Here for LA Fire Rebuild Updates:

https://www.milrose.com/la-fire-resources?hsCtaAttrib=185584473268

++++

Milrose Consultants is the #1 building permit expert in the United States, with over 500 professionals achieving municipal approvals in all 50 states. The only truly national consulting service in the United States for building compliance, maintenance, and permitting needs.Serving clients nationally for Commercial, Residential, Retail, Hospitality, Industrial, Institutional, Mixed Use and Life Science projects.


CITY, DURATION IN WEEKS:

Akron: 14 weeks

Albuquerque: 10 weeks

Amarillo: 12 weeks

Anaheim: 16 weeks

Anchorage: 12 weeks

Arlington: 12 weeks

Atlanta: 3 weeks

Augusta-Richmond County: 14 weeks

Aurora: 11 weeks

Austin: 10 weeks

Bakersfield: 16 weeks

Baltimore: 12 weeks

Baton Rouge: 16 weeks

Beverly Hills: 14 weeks

Birmingham: 14 weeks

Boise City: 10 weeks

Boston: 16 weeks

Brownsville: 6 weeks

Buffalo: 16 weeks

Cape Coral: 18 weeks

Chandler: 16 weeks

Charlotte: 12 weeks

Chattanooga: 16 weeks

Chesapeake: 16 weeks

Chicago - Self Cert: 2 weeks

Chicago - Standard Plan: 11 weeks

Chula Vista: 14 weeks

Cincinnati: 14 weeks

Cleveland: 10 weeks

Colorado Springs: 12 weeks

Columbus: 10 weeks

Corpus Christi: 14 weeks

Dallas: 12 weeks

Denver: 10 weeks

Des Moines: 10 weeks

Detroit: 14 weeks

Durham: 10 weeks

El Paso: 12 weeks

Elk Grove: 12 weeks

Fayetteville: 10 weeks

Fontana: 20 weeks

Fort Lauderdale: 14 weeks

Fort Wayne: 12 weeks

Fort Worth: 12 weeks

Fremont: 20 weeks

Fresno: 16 weeks

Frisco: 10 weeks

Garden Grove: 16 weeks

Garland: 12 weeks

Gilbert: 16 weeks

Glendale: 16 weeks

Grand Prairie: 12 weeks

Grand Rapids: 16 weeks

Greensboro: 16 weeks

Henderson: 12 weeks

Honolulu: 19 weeks

Houston: 16 weeks

Huntington Beach: 14 weeks

Huntsville: 16 weeks

Indianapolis: 14 weeks

Irvine: 19 weeks

Irving: 11 weeks

Jacksonville: 14 weeks

Jersey City: 16 weeks

Kansas City: 16 weeks

Knoxville: 10 weeks

LA County: 19 weeks

Laredo: 16 weeks

Las Vegas: 12 weeks

Lexington-Fayette: 14 weeks

Lincoln: 12 weeks

Little Rock: 14 weeks

Long Beach CA: 15 weeks

Los Angeles: 16 weeks

Register Here for LA Fire Rebuild Updates:

https://www.milrose.com/la-fire-resources?hsCtaAttrib=185584473268

Louisville: 16 weeks

Louisville/Jefferson County: 13 weeks

Lubbock: 12 weeks

McKinney: 12 weeks

Memphis: 12 weeks

Mesa: 14 weeks

Miami: 26 weeks

Miami: 24 weeks

Milwaukee: 10 weeks

Minneapolis: 14 weeks

Mobile: 14 weeks

Modesto: 18 weeks

Montgomery: 16 weeks

Moreno Valley: 15 weeks

Nashville: 14 weeks

Nashville-Davidson: 13 weeks

New Orleans: 14 weeks

Newark: 17 weeks

Newport News: 10 weeks

Norfolk: 12 weeks

North Las Vegas: 12 weeks

Oakland: 12 weeks

Oceanside: 16 weeks

Oklahoma City: 11 weeks

Omaha: 14 weeks

Ontario: 18 weeks

Orlando: 10 weeks

Oxnard: 18 weeks

Philadelphia: 12 weeks

Phoenix: 12 weeks

Pittsburgh: 16 weeks

Plano: 12 weeks

Port St. Lucie: 16 weeks

Portland: 20 weeks

Providence: 16 weeks

Raleigh: 15 weeks

Rancho Cucamonga: 12 weeks

Reno: 16 weeks

Richmond: 15 weeks

Riverside: 17 weeks

Sacramento: 16 weeks

Saint Paul: 3 weeks

Salt Lake City: 10 weeks

San Antonio: 12 weeks

San Bernardino: 16 weeks

San Diego: 18 weeks

San Francisco CA (Intake): 18 weeks

San Francisco CA (OTC): 2 weeks

San Jose: 14 weeks

Santa Ana: 12 weeks

Santa Clarita: 18 weeks

Santa Monica: 16 weeks

Scottsdale: 16 weeks

Seattle: 18 weeks

Shreveport: 8 weeks

Sioux Falls: 14 weeks

Souix Falls: 13 weeks

Spokane: 12 weeks

St. Louis: 14 weeks

St. Paul: 16 weeks

St. Petersburg: 16 weeks

Stockton: 16 weeks

Tacoma: 16 weeks

Tallahassee: 14 weeks

Tampa: 18 weeks

Tempe: 15 weeks

Toledo: 15 weeks

Tucson: 13 weeks

Tulsa: 14 weeks

Vancouver: 12 weeks

Virginia Beach: 15 weeks

Washington DC: 10 weeks

West Hollywood: 12 weeks

Winston-Salem: 14 weeks

Worcester: 17 weeks

Yonkers: 11 weeks

Josh Hibbits

Director of Development

2 周

Is this just for building permits or is site/civil permits built into these timeframes?

回复
Robert Pile, MRED, CCM

Portland Proud, Sustainability Centered, Real Estate Development

2 周

Casey McCormick Can you give some more context for this list? Are these permit duration averages across ALL types of permits? Or is this residential, commercial? Thanks!

Tim Berneche

Architect at Berneche2 Architecture

2 周

Great info thanks. I am an IDPH pre-qualified swimming pool architect and first reviews for pools are approximately 12 weeks for FIRST reviews. Typically 3-5 months total.

要查看或添加评论,请登录

Casey McCormick的更多文章

  • How Long Are Permits Taking?

    How Long Are Permits Taking?

    Keep in mind that durations can change quickly and the process involves initial submittal preparation, first review…