How Long Does It Take To Design + Fitout A Medical Facility?

How Long Does It Take To Design + Fitout A Medical Facility?

Top of mind for many medical professionals that want to refurbish, expand, or build a medical facility is the duration between the initial consultation, to the day of opening and accepting patients.


At Focusplan, we understand the importance of every day from start to finish, which is why we are committed to creating a timeline that is tailored to your needs.

In this article, we will share our typical timeline for the interior fitout of medical projects, and how we work to accelerate the process for a superior project experience.


Q) How long does it take?

No alt text provided for this image
East Care Specialist Centre

While we can’t give the specifics without getting to know you and your needs, we can offer a general estimate of the timeline for your project. This can assist you in generating initial thoughts on redirecting surgical procedures to alternative clinics or determining when to hire additional surgical staff.

Our fitout process is broken into distinct stages:


Initial Engagement (2-4 weeks): Typically, this phase takes about a month, within which we conduct a site visit, explore an initial concept plan, and discuss the logistics of the project ahead. This includes understanding potential leasing arrangements, project brief + scope, milestones + program, funding requirements, and construction contract selection options.

Technical Review (2-4 weeks): After confirming that we are ready to engage, our Technical Review team steps in to thoroughly assess the existing base build and proposed fitout. This is to ensure that no major design considerations or budget costs are overlooked before the Pre-Construction phase commences.

Pre-Construction (1-3 months): After the Technical review is confirmed, we complete the Developed Design and Building Consent documentation, while preparing for the final Contract signoff.

Building Consent (4-6 weeks): Apart from minor interior alterations, most construction projects necessitate obtaining building consent. The process involves filing for consent, responding to any council RFI’s, (requests for information), and obtaining the final consent. This timeline depends on the council's scrutiny and perception of design details regarding their compliance with the Building Code.

Construction (2-6 months): During the construction period we will update you on the schedule in weekly progress meetings, so you can see the progress made and address any discussion points as they arise. The end of the construction period is known as Practical Completion. This is when major contract works are complete, excluding any minor outstanding works.

Opening Date (2-4 weeks after Practical Completion): After Practical Completion, additional client-based commissioning work, such as specialist equipment installation, is required to ensure the facility is ready for its intended use. This work ensures that all systems are functioning correctly before the official opening for patients.

Total Average Project Duration (4-12 months): The project timeline depends on the project’s complexity and how promptly you provide us with the necessary details for the design and construction of your facility. Please keep in mind that the timeline provided is an estimate and your project may be completed sooner or later than expected.

No alt text provided for this image
Canopy Cancer Care Tauranga

?

Q) What steps does Focusplan take to accelerate the process?


1.???Detailed Feasibility Review: To prevent unforeseen delays and expenses, we prioritize a thorough review of the proposed fitout in the initial stages. This minimizes the need for additional approvals and checkpoints later.

2.????Defining the Decision-Makers: To ensure a smooth and efficient sign-off process, we agree on a list of key decision-makers from your company. These decision-makers include those from the Finance, Operational, IT, and Marketing departments.

3.????Clear Milestones: Our aim is to guide you towards a successful completion by outlining a transparent and concise plan. We offer expert advice from start to finish, including the opening date and important milestones. To optimize efficiency, we emphasize key points requiring your approval before proceeding, allowing you to expedite the process by responding promptly.

4.????Weekly Meetings: We will schedule regular meetings during the project to keep you informed about the timeline and fitout costs. During the construction phase, these meetings are held weekly.

?

We trust that this article has been helpful.

While we acknowledge that a medical fitout is a time-consuming task, taking the time to plan it out meticulously can bring about long-lasting advantages, including improved revenue, staff and patient contentment, and reduced expenditure on future repairs and upkeep.

要查看或添加评论,请登录

Focusplan的更多文章

社区洞察

其他会员也浏览了