How long does the production cycle of a sweater order take?

How long does the production cycle of a sweater order take?

For example an order of 1500-2000pcs sweaters from Shanghai to Hamburg?

  • Yarn time

Stock yarn, the factory will receive the yarn 3-5 days after placing the order

Yarn to order , lab dip 7-10 days, after lab dip confirmation, bulk yarn time 7-20 days for conventional yarn, 30-45 days for special yarn

No alt text provided for this image

  • Proto sample

After receiving the T/P, and the initial sample yarn is in place: 7-10 days, expedited for special cases: 3 days.(The complexity of the style has an impact on the proofing time)

This time also applies to modification samples, PP samples, size samples, test samples, etc.

No alt text provided for this image

  • SMS

Proto sample, the same time as above.

Lab dip, same time as above.

Yarn, same time as above

After receiving the customer's confirmation,?It takes 15-30 days to make sales samples according to different styles.

  • EXPRESS

The three most commonly used international express DHL , UPS , FEDEX

Shipping time: Regular 3 days, post-epidemic period 8-10 days

No alt text provided for this image

  • Bulk time

After receiving the PP sample comments and bulk yarn, it will take 30-45 days to produce bulk

During this production cycle, we also made bulk materials, plastic bags, boxes and other packaging materials

According to the customer's request, arrange the inline inspection and final inspection before deliery

Remarks: Generally shipment sample will be sent two weeks before shipment

No alt text provided for this image

  • Shipping

Book one week in advance, and book 2 weeks or more in advance as needed in the post-epidemic era

The time from factory to ship is generally about a week

3 days by air, fast speed and high price

16-18 days by train , medium speed, medium price

28-33 days by sea, slow speed, affordable price

Customs clearance 3-7 days

No alt text provided for this image

  • Finally we get the conclusion as below:

In the case of use stock yarn,the overall time required to make an order, because of?the difficulty of the style and the shipping method are different. The time from ordering to customs clearance is about 64 days - 145 days.

No alt text provided for this image

The above is the entire production process, and the following mind map is attached to facilitate review and understanding

?