How Long Does it Actually Take to Develop, Design and Deliver a Commercial Solar PV System?
If, like most businesses, you’ve been hit with a 30, 40 or even 50% increase in?the cost of electricity - or perhaps your current contract is coming to an end - you’re probably looking at the various ways you can?reduce your electricity consumption.
By far one of the most popular – if you have the roof-space/land available – is solar PV.
A solar PV system on or near your business is a tried and tested way of reducing your reliance on the grid but also a great way of cutting your carbon emissions.
Unfortunately, whilst you may have seen your energy prices increase almost overnight, developing a solar array correctly will not happen quite so fast.
Step 1 - Preliminary Proposal - Week 1
The first step on the journey is to establish whether or not a solar PV system meets the short, medium and long-term goals of the business.?
In order to understand this - without either party committing too much time - we will produce a preliminary proposal based on some conservative?assumptions for the site as well as some electricity data supplied by the business.
A preliminary proposal will cover the approximate system size, layout (and why), likely cost, payback and, most importantly, carbon reduction.
Step 2 - Grid Application - Week 3 - 17
After some internal deliberation, the next step will be to apply to your local District Network Operator (DNO) and request permission to connect your?proposed array to their network.?
Owing to the fact the grid have the right to veto the project - either via flat no or via uneconomical charges to connect - it’s advisable to tackle this?element of the project early on.
The grid have up to 65 working days in which to issue their response to an application.?
Step 3 - Structural/Land and Site Surveys - Week 20 - 25
After some further internal deliberation, next up is the structural/ground survey as well as a site survey.?
Solar panels need to stay anchored to the building or land for over 25 years so it’s important that they can withstand the weight of the equipment plus?everything that mother nature can throw at it.
It’s also important for us to measure all of the site variables so that our formal proposal provides all of the detail needed so that you can make an informed?decision on whether or not to proceed with the project.
领英推荐
A site visit to carry out the?structural survey?plus the site survey will take 6 weeks to arrange, carry out and then interpret the data collected.?
Step 4 - Formal Proposal - Week 26
At this point - roughly 6 months from starting the process - we will be in a position to provide a formal proposal with fixed costs.?
Our formal proposal will also cover likely site disruption (if any), inverter locations and delivery timescales.
Step 5 - Permitted Development/Planning Permission - Week 32-39
After some further, final, deliberation – as well as finalising the funding of the project – we will agree and sign commercial terms.?
With this we will set the wheels in motion on the permitted development/planning permissions?
Timescales here vary but 8 weeks to draft, submit and secure the correct permissions is typical.
Step 6 - Project Delivery - Week 40 - 52
As soon as the correct permissions are in place from the local council, we will progress to the final phase of this journey - project delivery.?
Clearly timescales are subject to system size, complexity and the weather but most projects are delivered within 4 - 8 weeks, with bigger projects taking up?to 12 weeks.
In Summary - Don't Rush but Don't Wait
From start to finish, a solar PV project – developed, designed and delivered in a logical step-by-step manner – takes up to 1 year.?
This will reduce significantly if the internal deliberation process is quick, if the local DNO does not take the full 65 working days or if you decide to undertake the structural/site?surveys whilst the grid application is progressing. If this happens then a project can be delivered within 8 months of commencing discussions.
If your energy contract is coming up for renewal in the next 18 months don’t delay.?Contact BeBa?Energy (01442 220 100)?today to start your journey and mitigate the impact of the rising cost of electricity.
Sales Leader - Providing the Construction Industry with the Tools to do the Job
3 年This pic clearly illustrates how “dead space” can be converted to support a greener and cleaner future while also brining much needed cost benefits to companies ??????