How to fairly determine Contractor's EOT Claim - A guide for Employers and Engineers
Pragmatic Project Consilium
Counsel of Contract & Claim Specialists for EPC - Oil & Gas Construction Industry
Employers and Engineers must carefully evaluate EOT claims to determine their project validity, ensuring that contractual obligations are met while maintaining fairness. This guide provides a structured approach to assessing EOT claims systematically.
Step 1: Review the Contractual Provisions
Before assessing an EOT claim, it is crucial to understand the contractual framework governing time extensions.
1.1 Identify the Governing Contract
The first step is to determine which standard form of contract applies, such as:
Each contract has specific provisions regarding delays, notice periods, and entitlement to EOT.
1.2 Examine the EOT Clauses
Review the contract clauses that define:
For example, under FIDIC 2017 Clause 8.4, the Contractor is entitled to an EOT for completion in case of Employer’s delays, unforeseeable events, or force majeure.
1.3 Check Conditions Precedent
Most contracts require Contractors to provide timely notice of delay.
Proper documentation and adherence to contractual notice periods play a crucial role in EOT entitlement.
Step 2: Assess the Delay Event
Not all delays entitle a Contractor to an EOT. Employers and Engineers must classify delays into different categories:
2.1 Excusable vs. Non-Excusable Delays
2.2 Compensable vs. Non-Compensable Delays
Understanding these distinctions is crucial in determining entitlement.
Step 3: Establish Causation
The Contractor must demonstrate that the delay event directly caused an impact on the project schedule. Employers and Engineers should:
3.1 Verify Contemporaneous Records
3.2 Establish Direct Impact
A well-substantiated claim should clearly link the delay event to its effect on the completion date.
Step 4: Conduct Delay Analysis
To accurately determine the impact of a delay, Engineers must perform a delay analysis. Several methodologies are available:
4.1 As-Planned vs. As-Built Analysis
4.2 Time Impact Analysis (TIA)
4.3 Windows Analysis
4.4 Collapsed As-Built Analysis
Selecting the appropriate analysis method depends on project complexity and available records.
Step 5: Evaluate Mitigation Efforts
The Contractor is responsible for minimizing the delay’s impact. The Employer and Engineer should:
If the Contractor did not take reasonable steps to mitigate the delay, the EOT claim may be reduced.
Step 6: Assess Concurrent Delays
Concurrent delays occur when both the Contractor and the Employer contribute to project delays. Different contracts handle concurrency differently:
Clear contractual provisions must guide the decision on concurrency.
Step 7: Determine the EOT Entitlement
After evaluating all factors, the Employer and Engineer must determine:
The EOT determination must be well-documented and aligned with contract terms.
Step 8: Document and Maintain Transparency
To avoid disputes, the final decision must be transparent and well-supported. Key actions include:
Prepare a Detailed EOT Determination Report, including:
Communicate the Decision Formally
By maintaining transparency, Employers and Engineers can reduce disputes and ensure that EOT determinations are legally and contractually sound.
Final Note
Evaluating an EOT claim requires a structured approach involving contract review, delay event assessment, causation analysis, and proper delay evaluation methodologies. Employers and Engineers must ensure that claims are supported by robust evidence and that decisions are communicated clearly. A well-handled EOT determination process helps in maintaining fair contractual relationships while protecting project timelines and budgets.