How to Create a Work Breakdown Structure
Work Breakdown Structure

How to Create a Work Breakdown Structure

In project management, a Work Breakdown Structure (WBS) is a deliverable-oriented breakdown of a project into smaller components. Sometimes project managers have a hard time getting a WBS started because they are not sure what to put at the very top, and they are uncertain about how to break the work down from there. Although there are many ways that the WBS can be started, the ultimate focus is on objectives. The top level is the overall project goal, and then the next level describes the main objectives. After the objectives are described, all the activities can be defined that are required to build the objectives. The project schedule is ultimately made up of activities, but the activities need to be listed in the context of the objectives they are helping to build. The WBS should follow the same logic used in the design of the project (the logical framework) that describes the cause-effect relationship of the project.?Level 1 is to describe the project main goal, the next level will identify the project objectives (outcomes), level 3 the project outputs, and level 4 the project activities.

When the team is creating the WBS, there are usually questions about how detailed the activities should be. The answer determines when to stop breaking the work down into smaller activities. Part of the answer is to utilize an overall estimating threshold. Other things to take into account include:

  • The activity can contain sub-activities that are related and continuous. For instance, if you had an activity called 'Create Learning Strategy and Training Strategy', it probably should be broken down further, since the Learning Strategy and Training Strategy are not necessarily related, and they are not necessarily continuous.
  • The activity should be able to be completed by one person, or one group of people. If you have an activity that requires different people for different sub-activities, then it should be further broken down into the sub-activities so that a person or the same group of people can complete the entire activity.
  • The activity needs to be fully understood by the team creating the WBS. If you have an activity that is not understood by the team, it should be further broken down into its sub-activities to provide further clarity.
  • The work should be broken down to a level that makes sense for the project manager to control. A common rule is to break the activities that are larger than 80 hours and not break those that are less than 8 hours.

It is important that the WBS doesn't get too tall or too deep. Depending on the WBS approach, it may take three to four levels to get all the defined activities. The general rule of thumb is that the number of levels should not exceed five. Smaller projects may not need more than two or three levels for each objective. For a large project, the levels might be deeper. However, there is a point where the detail will be too complex to manage. If the WBS has five or more levels for an objective, the project may be defining the work at too low levels (tasks that take less than 8 hours to accomplish). Another issue is when the objective is defined too broadly. In that case, the objective can be broken up into two or three sub-objectives that are smaller but integrated.

Want to learn more? Register for the next session of our online course, Adaptive Project Management for Development Organizations and NGOs. Register now and obtain a 20% discount with the promo code 20APM. Click on the link to find out more about this course. https://www.pm4dev.com/elearn/ecourses/eapm.html??

Maria Msoni

Community Mobilization/Development Expert, Project Management Official, Behavior Change Officer, Social Scientist

2 年

very informative. Thank you

回复

要查看或添加评论,请登录

Rodolfo Siles, PMP, MScM, BSc Eng.的更多文章

  • Do You Know the Difference Between Risks and Issues?

    Do You Know the Difference Between Risks and Issues?

    Risk and issue are two words that are often confused when it comes to their usage. The word ‘risk’ is used in the sense…

  • What are the phases of the Information Management Cycle?

    What are the phases of the Information Management Cycle?

    Information Management is the channeling of the information resources and information capabilities of the project to…

  • Managing Quality to Meet Stakeholder Expectations

    Managing Quality to Meet Stakeholder Expectations

    Quality management (QM) is the process for ensuring that all project activities necessary to design, plan and implement…

  • Why you need a project marketing plan?

    Why you need a project marketing plan?

    The goal of marketing your project is to raise awareness and build strong stakeholder support by saying how your…

  • How to do an Effective Project Close

    How to do an Effective Project Close

    The practice of project close-out finalizes all project activities completed across all phases of the project to…

  • The Adaptive Project Management Cycle

    The Adaptive Project Management Cycle

    A project management methodology follows a cyclical approach throughout the life of the project. The cycle represents a…

    2 条评论
  • Who is Responsible for Project Quality?

    Who is Responsible for Project Quality?

    While the project manager has overall responsibility for the quality management process, some projects may also have…

    3 条评论
  • Making the Right Presentations

    Making the Right Presentations

    Here are some tips to help you prepare for your next project presentation. The purpose of any presentation, written…

  • The Problem with Project Management in Development Organizations

    The Problem with Project Management in Development Organizations

    The problem with project management in development organizations is that all too often it is seen as an afterthought…

  • Five Tips for Productive Meetings

    Five Tips for Productive Meetings

    Productive and engaging meetings need a clear objective, an open dialog, and a strong leader as well. This will assure…

社区洞察

其他会员也浏览了