How to Cost Plan Commissioning Management

How to Cost Plan Commissioning Management

Quality, Consequences and the Construction Industrial Complex (part 310).???

A project quantity surveyor (PQS) once told me, "you commissioning firms are like rhinoceroses, you are thick skinned and charge a lot".?

He was referring to the way commissioning costs on the project had escalated. I asked two questions:?

  1. Why was there was no cost plan for commissioning when the project was planned or started on site?
  2. Commissioning firms have no control over design, construction or factors of production, yet somehow, costs to get systems completed, running and verified as specified are "extra"?

It is the developers job to ensure that they and / or the design team, specify the commissioning scope of work in detail to ensure all costs can be accounted for at biding stage.?

Frustration, arguments and conflict are outcomes from a lack of clarity.

Some firms like to live in the 'grey areas" of ill defined scope and costs because that is where the extras to contract are found i.e. the ability to make more money due to other project players not doing their job.?

I have reviewed several cost models published in UK's Building Magazine and there is not one mention of building commissioning.

I believe that all project plans need to incorporate a cost plan for building commissioning and commissioning management. This would be my approach to cost plan commissioning management (CxM).

CxM Cost Plan Influences:?

  • Market forces i.e. boom or bust. There never seems to be any other market condition.
  • Financial viability and insurance capacity of CxM firms.
  • Skill shortages, which can be epic.
  • Building type & complexity.
  • Building use i.e. is it mission critical?
  • Green building certification target.

CxM Cost Plan Headings:?

RIBA Stage 2 - Concept Design

2.1 Review and contribute to owners project requirements (project design brief for design team).

RIBA Stage 4 - Design Phase Commissioning

4.1 Commissionability design documents review and report.

4.2 Commissioning, TAB, O&M, Systems Manuals & close out specification sections.

4.3 Design phase commissioning plan.

RIBA Stage 5 - Static (no power) Commissioning?

5.1 Factory acceptance testing (FAT).

5.2 Commissioning kick off meeting.

5.3 Commissioning logic networks & programme (schedule).

5.4 Construction phase commissioning plan using approved controls sequences of operation for FPT scripts.

5.5 Installation commissioning inspections on site (quantify number of inspections).

5.6 Review and comment on vendor plus contractor start-up & commissioning method statements.

5.7 Witness static installation tests (quantify number of tests).

RIBA Stage 5 - Dynamic (power on) Commissioning?

5.8 Manage commissioning process (time based activity).

5.8.1 Witness equipment & system start-up.?

5.8.2 Witness equipment & system pre-commissioning.

5.8.3 Witness CHW & HTG systems pipework flushing & cleaning

5.8.4 Witness equipment & system vendor commissioning.

5.8.5 Witness testing, adjusting & balancing.

5.8.6 Verify Functional performance testing (FPT).

5.8.7 Verify Integrated Systems Testing (IST).

5.8.8 Verify specialist systems training.?

5.8.9 Review O&M Manuals for general content & completeness.

5.10 Advise client on systems completion and building functional readiness.

RIBA Stage 6 - Handover & Close Out (12 months defects liability period)

6.1 Issue practical (substantial) completion commissioning report.

6.2 Complete seasonal and deferred testing.?

6.3 Loop and fine tuning controls systems.?

6.4 Review and advise status of commissioning related snags (defects) at 10 months.

6.5 Update & issue final commissioning report.

General CxM Cost Headings

  1. Site office
  2. P.I Insurance
  3. General Insurances?
  4. Allowable disbursements?
  5. Overhead and profit
  6. Contingency @ 10% to 15% (prolongation, disruption, out of hours working)
  7. Schedule of rates

CxM Procurement Notes:?

  • Appoint early, preferably during design phase. YES!, commissioning begins during design phase.?
  • Understand some commissioning actives are offsite and some are full time onsite.?
  • Lead times:?

â—‹ Pre-qualification - 1 month

â—‹ Bidding - 3 months

â—‹ Negotiation and appointment - 1 month

Are there rules of thumb to cost CxM based on building size and complexity? Yes, but I am keeping them to myself. However, the costs noted above exist on every project. The choice is to recognize them early or be surprised by them late in the project, when the money has run out.?

Your move PQS.

Related

BlueRithm Investor & Advisor

Edifice Complex Podcast

#edificecomplexpodcast #ProjectManagement #makingbuildingswork #podcast #CxM #drawings #property #bluerithm #Cx #Cxnomad #RICS #Costplan


Gabriel Iancu

MEP Manager CSI Europe SRL

3 å¹´

I need to download this and to have a nice discussion with our Client...??

赞
回复
Mike O'Mahony

Managing Director at HDR Commissioning

3 å¹´

A contact of mine said just the other day that commissioning is, “a process, not an event”. Processes take time and require development by experienced, talented and skilled personnel. In this industry we depend to an extent on the performance of third parties. There is an inherent risk. It is important that this is recognised in the procurement of the CxM and the contractors.

Byron McFee

MEPT Commissioning Provider | Problem Solver | 25 years in building construction and commissioning services | Solution oriented professional

3 å¹´

Well written, informative, and accurate. Nicely done.

要查看或添加评论,请登录

Adam Muggleton的更多文章

  • #100 Joseph Lstiburek – Meditations on Building Science

    #100 Joseph Lstiburek – Meditations on Building Science

    Quality, Consequences and the Construction Industrial Complex (part 455). Our guest this episode is Joseph Lstiburek…

    2 条评论
  • #99 Kishor Khankari - The Case for CFD & Human Centric Design

    #99 Kishor Khankari - The Case for CFD & Human Centric Design

    Quality, Consequences and the Construction Industrial Complex (part 454). Our guest this episode is Kishor Khankari, Ph.

  • #98 P.Eng Vs P.L.Eng Vs CET + Arctic Design Issues

    #98 P.Eng Vs P.L.Eng Vs CET + Arctic Design Issues

    Quality, Consequences and the Construction Industrial Complex (part 453). Our guest this episode is Niss Feiner…

  • #97 Dr. Matthew Marson - The Smart Building Advantage

    #97 Dr. Matthew Marson - The Smart Building Advantage

    Quality, Consequences and the Construction Industrial Complex (part 452). Our guest this episode is Dr.

    2 条评论
  • Introducing the Updated Building Services Notebook!

    Introducing the Updated Building Services Notebook!

    You Spoke, We Listened — Introducing the Updated Building Services Notebook! Thank you to everyone who shared feedback…

  • #95 Nate Adams The House Whisperer

    #95 Nate Adams The House Whisperer

    Quality, Consequences and the Construction Industrial Complex (part 450). Our guest this episode is Nate Adams, The…

  • #94 Craig Eadie - Data Center Cx

    #94 Craig Eadie - Data Center Cx

    Quality, Consequences and the Construction Industrial Complex (part 449). Our guest this episode is Craig Eadie…

  • #93 Victoria Burrows - Built Environment Venture Capitalist

    #93 Victoria Burrows - Built Environment Venture Capitalist

    Quality, Consequences and the Construction Industrial Complex (part 448). Our guest this episode is Victoria Burrows…

  • #66 Is Cx on the Critical Path?

    #66 Is Cx on the Critical Path?

    Quality, Consequences and the Construction Industrial Complex (part 447). Nobody asked but we are doing it anyway.

  • #65 is BMS/BAS Broken?

    #65 is BMS/BAS Broken?

    Quality, Consequences and the Construction Industrial Complex (part 446). Nobody asked but we are doing it anyway.

    1 条评论

社区洞察

其他会员也浏览了