How To Convert Tender to Contract

How To Convert Tender to Contract

Crash Topic Series

I will commence a set of single posts each one cover comprehensive topic in project management niche, when you gathering its category to be a crash course in related subject, let's start.

Take this scenario/ Case, potential contractor submits their offer of your TOR or RFP and include their timeframe with high level schedule as mentioned in tender requirement documents, what there:

Root Causes

  • Proposed offer includes timeframe schedule include that the access to site to begin after 4 weeks of project commence date;
  • But document appendix to tender still include that the access to site within 2 weeks only;
  • Employer release LOA based on winning tenderer offer, without mention to site possession topic;
  • While the Planning specialist reviewing the proposed baseline schedule submission, the Project Manager notifying his/her Planner to ensure that contractor reflect the mobilization planned start to be not less than 4 weeks as contractor mentioned in their offer, which not happened as the planned start date was adapted to Appendix To Tender Document.

The Crash Topic

Care Preventative actions taken with existing controls in place by both parties during convert tender documents to Contract.

Crash Topic Description

Continue Reading ... Click Here

要查看或添加评论,请登录

Hady Shendy的更多文章

  • How To Script Your Lesson Learned

    How To Script Your Lesson Learned

    Upon you finished a stage, milestone or major task in your project, Review and analysis resources performance and the…

  • Returned Risk & EOT Assessment

    Returned Risk & EOT Assessment

    Yes there is a set of relations of Risks and EOT assessment affect your fairness and honesty of your EOT decision for…

    4 条评论
  • A New Approach to Manage Project' Schedule

    A New Approach to Manage Project' Schedule

    Any project initiative to deliver a facility contain elements (trades) Engineer/Contractor integrate them to end to…

    5 条评论
  • uniWBS? Cube Schedule Tool

    uniWBS? Cube Schedule Tool

    Each time I create or review any Project Management topics I manage it like a new mind came with new or elaborate my…

    1 条评论
  • Selfie QA QC 4 HSE

    Selfie QA QC 4 HSE

    Vision Ease the procedure of HSE for all Business Unit's Employee assigned to achieve core business task(s) might be…

  • Road Construction

    Road Construction

    three processes: Setting Out Earthworks Paving Construction Setting Out 312313 Subgrade Preparation 312316 Excavation…

    1 条评论
  • Universal Project's WBS

    Universal Project's WBS

    How many projects schedules created with bias work breakdown structure layouts some of them loss its meaning and make…

  • Where are you from RIP?

    Where are you from RIP?

    RIP mean Risk, Issue & Problem, which they are the situation of event(s) with your project (R) Event not yet occurs and…

  • Deliver The Impossible

    Deliver The Impossible

    I enjoyed by radio listening to Albert Camus drama "Caligula" the roman emperor who tried to deliver impossible but he…

    5 条评论
  • Contractors Always Wrong!

    Contractors Always Wrong!

    When they assigning their construction site staff to be acting the rolls of Project Manager and their capablities…

    1 条评论

社区洞察

其他会员也浏览了