How to close out maintenance work orders
Erik Hupjé
Escape the vicious cycle of reactive maintenance: less downtime, less work, lower costs and less stress
In the?Maintenance Planning & Scheduling process , close out work is the phase where we capture the information needed for continuous improvement.
We collect data on:
What went well?
What can be improved?
What didn’t produce good results?
Sadly, close out is often seen as an admin burden.
A waste of precious time.
Something you don’t want to hassle your technicians and supervisor with.
But that’s plain wrong.
Closing out your work orders is essential to your long-term success.
Without close out, it becomes near impossible to achieve the continuous improvement that we’re after in Planning & Scheduling.
The 4 aspects of closing out your work orders?
In my experience, if you want to effectively close out your work, there are 4 things that you need to consider:?
Let’s discuss each one in a bit more detail.?
Job History?
The first thing you need to do for a proper close out is to capture the basic information and history in your CMMS. This might include:?
And you capture these information for two main reasons: To improve equipment reliability, and to reduce your lifecycle costs.?
Now job history is clearly the domain of your maintenance technicians.??
They know what was done, and they need to make sure that the job history is accurately captured in the CMMS. But make sure that your supervisor reviews the quality of all technical history entered.??
If your crew enters no history, incomplete history, or simply incorrect history… well guess what? Your planners or reliability engineers can’t draw any conclusions from that. Or worse, they’ll make the wrong ones.??
And that is why you want to make sure that your supervisor does a quality check on all the technical history that is entered by your technicians.?
Planner Feedback?
Now, the second part of the close out phase is making sure you capture feedback on the job plans as prepared by your planner.??
The best way to do this is to use a standard feedback form which the crew uses to provide feedback on things like:?
Normally, I recommend that you don’t use a feedback form for every single job. Only those jobs where the planner believes feedback is required such as new jobs or complex high-risk tasks.??
And make sure that it’s easy for the crew to use those feedback forms and to give feedback on other job plans when they might want to.??
Most importantly, you need to make sure that your planner acts on the feedback in a reasonable timeframe.?
It lets the execution crew know that action has been taken.??
As soon as the crew sees that their feedback is not used, they will stop giving it. And I’ve seen that way too many times, and that really undermines your drive to a continuous improvement culture.?
领英推荐
Trigger Root Cause Analysis?
The third thing you need to do is to have your maintenance supervisor assess if any of the work you’ve completed should trigger a root cause analysis.??
The point is to make sure that your frontline can flag certain failures for an RCA to avoid repeat failures.?
Now, maybe this is the second time in a relatively short period of time the same failure has occurred.??
Your crew are likely to pick this up faster than if you wait for the analysis of the technical history to tell you that you had a whole bunch of repeat failures.??
Or it could be that the crew has just completed the repairs for a very significant failure and you want to make sure it doesn’t occur again.??
So you initiate a root cause analysis.?
Having your front line involved in this step helps to create ownership and can speed up the detection of repeat failures and bad actors.??
But make sure you have some predetermined thresholds or criteria so that the decision is as objective as it can be.?
Finalise Payment??
Finally, the last thing you need to consider is the on time and accurate payment of your vendors and contractors.?
Making sure you have been charged the right amount is an important step too. Something that needs to be done close to where the work is done.?
The people in the back office have no idea whether all the parts were consumed in an overhaul or whether the job really took two days longer.??
They’ll rely on that information being captured by the front line.??
So what needs to happen in this step really depends on your company’s policies and procedure.??
As a minimum, you want to make sure you have these details in order:?
Summary?
The accurate entry of something as mundane as man hours and meaningful history is often seen by your technicians as an admin burden, something that is a nuisance and not really that important.??
But as you’ve seen, that couldn’t be further from the truth. Without that data, you will struggle to make improvements. So you need to make sure that for every job you complete, all four aspects of close outs are addressed properly:?
If you want to create a system where you can:?
Then check out our Maintenance Planning & Scheduling course where you can learn about closing out your work in more detail… and so much more.?
P.S. Whenever you're ready, here are 3 ways we can help you on your Road to Reliability:
1. Want to train your team on how to improve your plant's maintenance reliability?
Enroll your team in one of our most popular online training courses:
Implementing Maintenance Planning and Scheduling —increase your maintenance workforce by 35% without hiring anyone. Reduce costs, improve safety and increase morale.
Developing and Improving Preventive Maintenance Programs —achieve higher reliability and availability whilst doing less maintenance. Acquire the knowledge and tools needed to create a highly effective and efficient Preventive Maintenance Program.
2. Want to know how effective your Planning & Scheduling really is?
Use our Planning & Scheduling Scorecard ?to assess your performance and receive a personalised PDF report with recommendations on how to improve.
Use our Wrench Time Calculator ?to easily calculate how much value your organisation is missing out when you neglect your Planning & Scheduling.
3. Want to start your journey on the Road to Reliability??
Download the Road to Reliability? eBook ?and discover a simple, proven framework that you can use to achieve a highly reliable plant for your organisation. Unlike other overly complicated models that use 10 to 20 elements, the Road to Reliability framework only uses 4 elements to achieve great results.
Operations Manager
1 年The article is very comprehensive and informative.
Head of Maintenance & Project Manager 15 KTPA Debot - Soda Ash Business at ICI Pakistan Ltd.
1 年Great post! Closing out work orders is a critical phase in the Maintenance Planning & Scheduling process, enabling continuous improvement. It's unfortunate that close out is often seen as an administrative burden or a waste of time. However, neglecting this crucial step hinders long-term success and makes achieving continuous improvement nearly impossible. Your article on closing out maintenance work orders and the four aspects for a successful close out will undoubtedly provide valuable insights. Thank you for highlighting the importance of this often overlooked process.
Thanks for sharing
Engenheiro mecanico reformado,consultor de engenharia,planeamento,manuten??o,controle de custos,analista de manuten??o,treinamento do pessoal(Freelance),fleet management,disponível para trabalhos em part time
1 年Its very difficult to have good results when management don't understand the purpose of work orders and related information
?? Reliability & Project Engineer| Plant commissioning| Maintenance Planning & Supervision| Lean manufacturing| Operation Management| Utilities & Process Engineering|
1 年Thank you for sharing. Found insightful.