Hon Minister Judith Nabakooba Press Statement on the status of performance of the USMID Program
USMID - Additional Financing Program
A Program implemented by the Ministry of Lands, Housing and Urban Development.
Uganda Support to Municipal Infrastructure Development (USMID) is a Program for Results (PforR) operation that initially run for 5 years (September 4, 2013 to December 31 2018) but was later extended to December 31, 2023 upon receipt of Additional Financing (AF). The initial phase of USMID had a total funding of US$ 138M, and all the funds were allocated to 14 Program participating Municipal Local Governments which was used for infrastructure development and capacity building. The 14 beneficiary Local Governments were (Entebbe, Moroto, Kabale, Mbarara, Masaka, Fortportal, Hoima, Gulu, Mbale, Tororo, Jinja, Arua, Lira and Soroti).?10 of these as you may be aware have since been turned into Cities, because of the achievements they made during the USMID program.
The Ministry started implementing the Additional Financing phase (currently ongoing) on April 11, 2019 and its total funding was US$ 360 million of which US$25Million was a grant. The funding was also from the World Bank.?The Objective of the program did not change from the original USMID phase, and so was the lending instrument which remained as a PforR (Program for Results). This lending instrument means that the disbursement of finances to the local Governments is based on the performance of the said local government- this means, that getting money to implement is not guaranteed, but the local government must work for it. This current phase of the program is expected to close this year, December 31, 2023.
From 14 Municipalities, the additional funding phase extended the geographical scope to an extra 8 Municipalities of (Busia, Apac, Ntungamo, Kasese, Lugazi. Kamuli, Kitgum, and Mubende). Due to the presence of the grant in the funding, there was also a Government decision that some of the district local governments that faced a high influx of refugees would be supported. These are (Isingiro, Kamwenge, Kiryandongo, Obongi, Lamwo, Terego, Madi-Okollo, Arua, Adjumani, Moyo, and Yumbe). This means that right now, the Ministry is implementing USMID in 10 Cities, 12 Municipalities and 11 Refugee Hosting District. The Ministry support to the RHDs is in three fold;- infrastructure that enhances social cohesion between refugees and the host communities, physical planning of the land of the host communities and systematic land adjudication and titling of the same land.
The implementation structure for the USMID program includes a steering committee chaired by the Permanent Secretary/ Secretary to the Treasury-MoFPED, a program technical committee chaired by MLHUD, as the executing agency, and the 33 program Local Governments as the implementing agencies. The team which forms the program technical committee is drawn from about 16 different Ministries Departments and Agencies, to manage the policy supervision of the technical team. This is from the Ministry of Finance Planning and Economic Development, Ministry of Local Government, Ministry of Works and Transport, Ministry of Gender Labour and Social Development, OPM, NEMA, PPDA, Uganda Road Fund, NPA, The Association of Urban Authorities, and the Local Government Finance Commission.
What is the current implementation status
1. The cities/ municipalities have been able to:
2. The central government has provided capacity building through trainings, meetings, and hands-on technical support in;
3. The capacity of the Ministry of Lands, Housing and Urban Development as the supervising Ministry for urban service delivery has been improved through staff training, provision of office equipment, and development of systems for example;
Status performance on infrastructure implementation in the Cities/ Municipalities (USMID &USMID-AF)
The table summarizes all the sub-projects that were implemented under the first phase of USMID and those implemented under the Additional Financing. It shows that at the end of USMID, a total of 217.3km of roads and the associated infrastructure will have been constructed.
Roads
The road infrastructure subprojects that have been completed so far, are in 6 cities and 6 municipalities and they are ready for commissioning. These roads cover a total of 51.8km (Arua 3.5km, Entebbe 2.1km, Gulu, 9.5km, Jinja 5.9km, Kamuli 1.5km, Kitgum 7.1km, Lugazi 2.5km, Masaka 6.3km, Mbale 6km, Mubende 2.8km, Soroti 3.3km, Tororo 1.4km) and they are all 2-lane equivalent length.?
Execution of road infrastructure subprojects is ongoing covering in 9 cities and 11 municipalities with the exception of Soroti City and Kitgum Municipality whose road infrastructure subprojects have all been completed. The roads under execution cover a total of 87.1km (2-lane equivalent). These roads will be completed by the end of December 2023.
Standalone solar streetlights
Three cities and three municipalities have successfully installed a total of 2,980 solar streetlights (Gulu 500, Mbarara 704, Masaka 1,380, Lugazi 203, Ntungamo 77, Kabale 93) along paved roads that were constructed by other agencies, not Ministry of Lands.?The installation of 250 solar streetlights is still pending in Lugazi Municipality and an extra 107 in Kabale Municipality.
Local Economic Development Infrastructure
Local economic development subprojects have been implemented in three cities (Mbarara, Lira, and Hoima) and four Municipalities (Moroto, Entebbe, Mubende, and Busia). Lira City, Moroto, and Entebbe Municipality undertook completion activities on subprojects that were implemented during the first phase of USMID. ?
Moroto Municipality also completed the bus terminal while for Lira City, ongoing is the completion work on the Coronation Park and Childrens Park, while Entebbe Municipality is completing the Kitoro Taxi Park building by adding on a floor on top of the first floor that was constructed under USMID.?
The new local economic development subprojects are the construction of the Taxi Park and beautification of the Mayor's Garden in Mubende, the beautification of the Rwebikoona market parking area in Mbarara City, the construction of an animal slaughterhouse in Hoima City and the Taxi Park in Busia Municipality. These sub-projects will be ready for commissioning by the end of December 2023.?
领英推荐
USMID-AF SUPPORT TO THE 11 REFUGEE HOSTING DISTRICTS
The refugee hosting districts are implementing a number of static infrastructure sub-projects that include leisure parks (1No), markets (17No.), playgrounds fields (7No.), resource centers (21No.), taxi parks (1No.), bridges (4No.) and drainage channels (3No.).
These sub-projects are intended to improve the coexistence between the refugees and host communities. The earliest implementation start date for these subprojects was April 2022 while the latest end date is December 30, 2023.
The Ministry has since prepared physical development frameworks for all the 11RHDs, and ongoing is the preparation of physical development plans
The Ministry commenced SLAAC activities with sampling Kamwenge district- Kaberebere in Nkoma sub-county and out of the 1208 parcels mapped, 23 land titles were issued in October 2021, the rest of the titles (194) are ready for issuance while the remaining 908 LAFs have been approved by the district Land board.?
The SLAAC process continues in the other District Local Governments and all the planned parcels should be concluded and issued out by December 31, 2023 the program closure date.
Table showing static sub-projects in the 11 RHDS?
USMID Implementation has faced the following major challenges?
Relocation of utilities (power, water, telecom lines, and security installations) along the right of way during the construction of roads and local economic infrastructure. A lot of time is wasted on negotiations with the service providers before the relocations are done. On average 5% of the contract price is given to utility companies for the relocation of their service lines by the program participating local governments.? To ease this, the Ministry has prepared a paper on this issue and will be seeking a harmonized policy approach for the location of utilities within the right of way as a mitigation measure and clear modalities for dealing with the issue of relocation.?
Cash flow challenges resulting from the treasury single account operation in which funds are swept from the program participating local governments at the end of the financial year. The delayed revoting of the swept funds to the program participating local governments has caused implementation challenges with the local governments failing to meet their contractual obligations and some contractors have claimed for interest over delayed payments which money is not provided for in the credit.?The Ministry is now seeking a sub-treasury single account in which funds are devoted to the program participating local governments as soon as the new financial year starts without any further delays.
What next after December 31, 2023?
Preparation of a follow-on program to USMID
The Midterm review conducted by the Ministry in May 2022 on the performance of the USMID-AF pointed out the ever-increasing high demand for urban infrastructure in urban areas because of rapid urbanization, especially in the newly created cities with exponentially extended boundaries to which the institutional capacities to deliver such services remain inadequate.?
The midterm review, therefore, recommended a five-year follow-on program estimated at US$ 750 million.?Based on this recommendation the Ministry has since prepared a concept for a follow-on program named -Uganda Cities and Municipalities Infrastructure Development (UCMID) Program. The concept note was approved by the Development Subcommittee- MoFPED, and so have they approved profile and feasibility studies. The Ministry is currently conducting feasibility studies.
The geographical scope of the program (UCMID) will include all the Local Governments under USMID-AF (10 cities, 12 municipalities) and an additional 15 Municipalities that are not currently under the program and these shall be; Mityana, Iganga, Masindi, Rukungiri, Bushenyi-Ishaka, Kumi, Nebbi, Koboko, Kisoro, Kapchorwa, Ibanda, Njeru, Bugiri, Sheema, and Kotido. ?
Urban roads of 116km, 22 local economic development, and 57 km of primary drainage channels have been designed and are ready for implementation in the next phase, once the Government and the world bank sign the financing agreements.
The Ministry is now in the process of preparing engineering designs for additional urban roads of 197km, primary drainage channels of 33km, and 6 local economic subprojects in the 10 cities and 12 municipalities under the current phase. Preparation of engineering designs for the additional 15 municipalities that will join the program will be done after they the program has been approved.