Hidden Risks Behind Sending an Improper Claim Notice
Ilamparithi BoologaSundaraVijayan
45K Followers | Expert International Contracts | Construction Claims | Disputes | Forensic Delay Analysis |Techno Legal | Arbitration | EPC | Oil & Gas | Power & Energy | Mentor | Key note Speaker | Author | Entrepreneur
Claim notices are often seen as routine paperwork in construction projects, but their importance cannot be overstated. These formal documents act as the gateway to preserving a contractor’s rights to compensation, extensions of time (EOT), or other contractual reliefs. A poorly drafted or improperly timed claim notice can render a valid claim ineffective, jeopardizing the contractor’s entitlements and creating operational, financial, and legal risks.
In construction contracts, where disputes can escalate quickly, claim notices are not mere formalities but crucial tools for risk management and dispute avoidance. Despite this, contractors and subcontractors often fail to prioritize claim notices, resulting in significant hidden risks that surface later in the project lifecycle.
In this article, we will explore:
By the end of this article, construction professionals—contractors, subcontractors, and claims managers—will better understand how to mitigate risks associated with improper claim notices and protect their entitlements.
1. The Role and Importance of Claim Notices
Definition of a Claim Notice
A claim notice is a formal notification issued by a contractor or subcontractor to the Employer (or Engineer/Project Manager) to:
Claim notices serve two primary purposes:
What Does a Proper Claim Notice Include?
To comply with standard construction contracts, a proper claim notice must include:
Significance in Standard Contracts
Different standard forms of contracts emphasize the importance of timely and compliant claim notices:
Failing to comply with these clauses—whether through delays, vagueness, or incomplete information—can result in severe consequences for contractors.
2. Hidden Risks of Sending an Improper Claim Notice
While contractors may be aware of the need to send claim notices, they often overlook the risks of sending notices that are:
These improper notices create risks that may not be immediately visible but can escalate into significant issues.
a. Loss of Entitlement to Claims
Failure to issue a proper claim notice—especially within the prescribed timeline—can lead to forfeiture of the claim. Many contracts, including FIDIC, have strict “time-bar” clauses.
Example Under FIDIC Red Book (Sub-Clause 20.1): If a contractor experiences delays due to unforeseen ground conditions and fails to notify the Engineer within 28 days, the claim can be rendered invalid.
b. Rejection of Claims for Lack of Detail
Employers and Engineers have the right to reject claim notices that are vague or lack sufficient details. A claim notice that fails to:
... may be considered invalid or “non-compliant.”
Example Scenario: A subcontractor submits a claim for delays caused by design changes but provides no supporting documentation or evidence. The Employer rejects the notice, and the claim is never recognized.
c. Escalation of Disputes
Improper claim notices increase the likelihood of disputes. When Employers reject vague or late notices, the contractor may escalate the matter through formal dispute resolution mechanisms such as:
领英推荐
Risks of Dispute Escalation:
d. Financial Risks and Cash Flow Problems
Improper notices can delay or invalidate claims for payment, putting significant financial strain on contractors:
Case Study: A contractor submits a claim notice for material price escalation but fails to include supporting invoices or price indices. The Employer rejects the claim, forcing the contractor to absorb the rising costs.
e. Damaged Relationships with Employers and Subcontractors
Improper claim notices can lead to distrust and strained relationships with Employers, Engineers, and subcontractors. In back-to-back contracts, the failure to submit proper notices can cause cascading effects:
This can create a ripple effect across the project team, resulting in delays, reduced productivity, and legal disputes.
3. Real-World Case Examples
Case 1: Contractor Loses EOT Due to Late Notice
In a project governed by FIDIC Yellow Book, the contractor experienced delays due to unforeseen weather conditions but submitted a claim notice 40 days later—12 days beyond the 28-day requirement. The Employer rejected the claim, arguing that it was time-barred under Sub-Clause 20.1.
Case 2: Subcontractor Dispute in Back-to-Back Contracts
A subcontractor relied on the main contractor to submit a claim for additional costs due to scope changes. However, the main contractor submitted an incomplete claim notice with insufficient documentation. The Employer rejected the claim, and the main contractor could not pass down compensation to the subcontractor.
4. Best Practices to Avoid Risks
To prevent the hidden risks of improper claim notices, contractors should adopt the following best practices:
a. Review and Understand Contract Provisions
b. Develop a Robust Claim Management System
c. Provide Accurate and Timely Information
d. Use Standardized Templates
Implement templates for claim notices to ensure clarity, consistency, and compliance.
e. Engage Claims Specialists
For complex claims, seek the support of claims consultants to ensure proper preparation and submission.
5. Take Away
Improper claim notices can create significant risks in construction projects, including the loss of entitlements, financial strain, damaged relationships, and costly disputes. Contractors must recognize the importance of timely, clear, and compliant claim notices to preserve their rights and mitigate disputes.
By understanding contractual requirements, adopting robust processes, and engaging professional support when necessary, construction professionals can protect their entitlements and achieve smoother project outcomes.
Remember: A well-prepared claim notice is not just a formality—it’s a crucial step in safeguarding your contractual rights.
Maintenance Manager
2 个月Thank you for sharing
Senior Project Control Specialist with expertise in Project Management at AJI - PMO of Riyadh Municipality.
2 个月Useful tips I have question if the notice period all time make EOT not entitled regardless the contractor’ right.