Dear All

This blog is to explain you how to post goods receipt reversal even after put-away is confirmed for the EWM IBD.

Normally SAP does not allow to reverse goods receipt from EWM if put away has already been confirmed. SAP EWM sets delivery status DCO to 9 for items, 9 means completed.

System won't allow you to do confirmation correction as well, because of the same reason, DCO status set to 9.

now question is- if there is a need to reverse goods receipt after put away is done, then how we can process GRR.

There are few system settings that we need to perform to allow EWM to post GRR after final put away. All the needed system setup, I will document in the next part of this blog.

After changes have been done, below is how system will react once we try to post GRR after final put away.

I will cancel GRN for below IBD for which GR and put away both are completed.

Important point to consider here is, DCO status is now set to 1 after configuration changes.


system won't allow you to do full GR cancelation in one shot at header level.

You need to correct confirmation at WO item levels.

I created new IBD with 2 items to see how to correct confirmation for all items together.

You can correct the QTY for each item- of course, you can set QTY as zero if you need to fully reverse the GRN.

This works perfect. System was able to post 102 MVT and it got updated at S4 side.



What is the different system setup and how DCO status will be set to 9 - completed and other details, I will cover in the next part of the blog.

Thanks for reading and your time.

Regards,

Aslam Ansari


you must be using "delayed update of completion status for inbound deliveries" status profile change

回复
Le Trong Trung (Darius)

SAP Logistic Consultant (MM, SD, WM, EWM)

6 个月

Waiting your part 2

回复
Sampath Dasarathi

SAP EWM || SAP ABAP on HANA || SAP UI5/Fiori || SAP ABAP & Workflows || IC Agile Certified Professional

8 个月

when is part 2 coming ..

回复
Daniel R.

Manager SAP Logistics bei leogistics GmbH

8 个月

Hi Aslam, do you already know by when you can provide the Part 2? Very interesting! Thanks!

回复

要查看或添加评论,请登录

Aslam Ansari的更多文章

  • Synchronous goods receipt for Purchase orders in S4 HANA 2020 Embedded EWM

    Synchronous goods receipt for Purchase orders in S4 HANA 2020 Embedded EWM

    Objective: Objective of this blog is to showcase new functionality made available in S4 HANA 2020 for synchronous goods…

    6 条评论
  • EWM-TM ASR Integration-Part 1

    EWM-TM ASR Integration-Part 1

    With S4 HANA 2020 FPS 01, SAP has improved the integration between SAP TM and SAP EWM. Now SAP EWM can communicate…

    1 条评论
  • Consolidate Stock

    Consolidate Stock

    SAP has provided one nice functionality for day to day work for the warehouse clerk to consolidate stock in warehouse…

  • Pack Warehouse Stock

    Pack Warehouse Stock

    Hello All, This blog will put lights on FIORI app 'Pack Warehouse Stock'. In the warehouse, there could be many loose…

    2 条评论
  • Packaging items posting: EWM Inbound process

    Packaging items posting: EWM Inbound process

    System : S4 HANA 2020 FPS 02 Embedded EWM This blog will list down the important settings that we need to perform to…

    2 条评论
  • GR Communication to S4 CORE from EWM- Solution

    GR Communication to S4 CORE from EWM- Solution

    Solution for the blog https://www.linkedin.

  • GR communication to S4 CORE from EWM

    GR communication to S4 CORE from EWM

    This blogs is the first informative blog before we look for the solution to have one GR document posting when we have…

    1 条评论
  • Manage Inbound process with FIORI Apps in SAP EWM

    Manage Inbound process with FIORI Apps in SAP EWM

    In this blog we will see the potential usage of using FIORI apps for managing inbound process in EWM. We will also…

社区洞察

其他会员也浏览了