Grove Developments Ltd v Balfour Beatty Regional Construction Ltd

Grove Developments Ltd v Balfour Beatty Regional Construction Ltd

Grove Developments Ltd v Balfour Beatty Regional Construction Ltd [2016] EWHC 168 (TCC)

In Grove Developments Ltd v Balfour Beatty Regional Construction, it was held that a contractor will have no contractual right to be paid for a submitted additional interim payment application where a contractually binding schedule for interim payments has been agreed.

Therefore, any project complications resulting in the expiration of the agreed payment schedule would potentially render a contractor unable to request any further interim payments until practical completion is achieved. At this point the final payment mechanism would be utilised, to allow the contractor to obtain outstanding payments.

The facts

Grove Developments Ltd (the “Employer”) and Balfour Beatty Regional Construction Ltd (the “Contractor”) entered into a JCT Design and Build Contract, 2011 with bespoke amendments, to a value of approximately £121 million. The Contract incorporated amendments which had been made to the standard form payment provisions which resulted in the parties opting for staged payments resulting in agreement of a payment schedule comprising of 23 interim payment applications, to be made between September 2013 and July 2015, the expected contract life.

The Contractor did not reach practical completion on the completion date within the contract and although the parties had tried to reach agreement on a revised schedule in advance of the expiry of the payment schedule , they failed to do so in time.

In August 2015 the Contractor issued an interim payment application no 24 for the sum of approximately £23.16 million. This application was made despite no agreement having been made as to the mechanism for making future payments beyond the 23 interim payment applications provided for under the Contract.

The Employer argued that the Contractor was not entitled to issue any interim applications beyond no 23 under the contract payment schedule.

The Contractor, anticipating the validity of their 24th payment application consequently contended that the Employer had not served a payment notice or a payless notice within the required time frames and therefore as a result, it was owed the amount referred to under interim payment application 24.

The decision

In a Part 8 declaratory relief proceedings, the court held that the Contractor had no contractual right to make or be paid for any interim payment application beyond the 23rd application provided for under the Contract, concluding that:

  • such a future payment provision could not be implied into the Contract, because the possibility of providing for further interim payments as a consequence of a delay in reaching practical completion, was something which the parties could have negotiated prior to agreeing to the original payment schedule; and
  • the payment procedures as set out in the Scheme for Construction Contracts 1998 could not apply to future payments due to the parties having already agreed a schedule pursuant to which payments would be made. Further interim payments to the Contractor was subject to the parties agreeing the terms upon which they would be made, which they had already been unable to do.

Comments

This decision is interesting in that those contractors who have already agreed a set of payment terms that include the provision of a fixed payment schedule should have this decision in consideration. If the contract does not adequately foresee the possibility of project overruns or delays, then additional negotiation will be required to ensure adequate payment protection in the future. Those Contractors who are in negotiation should ensure that all scenarios in regards to payment are considered

  • https://www.bailii.org/ew/cases/EWHC/TCC/2016/168.html
  • Comment

要查看或添加评论,请登录

Colin Tomlinson的更多文章

  • The Commercial Manager

    The Commercial Manager

    A review of the job market boards reveals that there are a variety of different commercial management pseudonyms in the…

  • COMMERCIAL MANAGEMENT IN CONSTRUCTION.

    COMMERCIAL MANAGEMENT IN CONSTRUCTION.

    There are a variety of different commercial managers in the various industries requiring an assortment of different…

    5 条评论
  • NEC Clause 10.1 The obligation of Mutual Trust and co-operation and Good faith.

    NEC Clause 10.1 The obligation of Mutual Trust and co-operation and Good faith.

    Obligation of Mutual Trust and Co-operation and Good Faith? In the recent decision of Costain Ltd v Tarmac Holdings…

  • CAN PUBLIC SUPPORT STOP THE EXECUTION OF RICHARD GLOSSIP?

    CAN PUBLIC SUPPORT STOP THE EXECUTION OF RICHARD GLOSSIP?

    THE CASE OF RICHARD GLOSSIP I very rarely get emotive about subjects that I cannot influence, but the application of…

    2 条评论
  • Adjudication, Simple steps to getting it right:

    Adjudication, Simple steps to getting it right:

    GENERALLY Commercially start off as you mean to go on, follow the conditions stipulated in the contract. Ensure you…

    5 条评论
  • CONSTRUCTION LAW UPDATE ISG CONSTRUCTION LTD v SEEVIC COLLEGE

    CONSTRUCTION LAW UPDATE ISG CONSTRUCTION LTD v SEEVIC COLLEGE

    A Review of the High Court Decision in ISG Construction Ltd –v- Seevic College [2014] EWHC 4007 (TCC) In deciding this…

  • FIXED FEE ADJUDICATION

    FIXED FEE ADJUDICATION

    The HGCRA 1996 incorporated statutory adjudication as the preferred method of resolving construction disputes in the…

  • “A PERSON WHO REPRESENTS HIMSELF HAS A FOOL FOR A CLIENT”

    “A PERSON WHO REPRESENTS HIMSELF HAS A FOOL FOR A CLIENT”

    Dunn v Glass Systems (UK) [2007] EWHB B2 (QB) Although this is an old case it really does show the worst of practices…

  • Enforcement of an Adjudicators decision.

    Enforcement of an Adjudicators decision.

    Enforcement of an Adjudicators decision. So the adjudication has been completed and the decision has been communicated,…

  • CAN YOU AFFORD NOT TO?

    CAN YOU AFFORD NOT TO?

    The predicament is somewhat different but the root cause is the same, the parties have failed to understand and…

社区洞察

其他会员也浏览了