Florida 404 Assumption: Policy & Practice
In the 15th episode of the Ecobot Webinar Series, we heard from experts about what preceded Florida’s 404 assumption, and how the permitting process plays out now.
Topics
Moderator
Jeremy Schewe , PWS, Chief Scientific Officer, Ecobot?
Presenters & Panelists
Susan Roeder Martin, JD, Partner, Nason Yeager
Heather Mason , PWS, Environmental Administer, Florida Department of Environmental Protection
Kerri MacNutt , Senior Manager, Environmental Consulting & Technology, Inc.
Permitting Requirements in Florida Before 2021
Susan Roeder Martin previously worked with the South Florida Water Management District, one of the five water management districts in Florida. These districts worked with the Department of Environmental Protections (DEP) and had input on the Section 404 process as it was assumed by the State. Now, as an attorney at Nason Yeager, she represents clients seeking 404 permits from the DEP.
Split of Permitting Review
Prior to 2021, Martin explains, a permit was required from the U.S. Army Corps of Engineers (USACE) under Section 404 of the Clean Water Act (CWA) for discharges of dredge and fill materials into a water of the United States (WOTUS). Florida also required a second permit from the State called an Environmental Resource Permit (ERP). ERPs can be granted by the Florida DEP or by one of the state’s five Water Management Districts (WMD), an authority granted to the state by Chapter 373 of the Florida statutes.?
Rather than have applicants go through both the DEP or a water district for a permit, the two organizations entered into an operating agreement that the WMDs process most ERP permits, but DEP maintains a supervisory authority over the WMDs and the districts rely heavily on DEP expertise.?
Florida’s Comprehensive Program to Protect Wetlands and Other Surface Waters
Florida has its own set of regulations in Chapter 373 Florida Statute, plus ERP rules, many of which overlap with those of the 404 program. The ERP rules protect three broad environmental categories:
Today’s discussion focuses on the first category.
“Surface waters” are defined as any water on the surface of the earth, whether contained in bounds created naturally or artificially or diffused. Water from natural springs shall be classified as surface water when it exits from the spring onto the earth’s surface. Permits are required for “works,” which are defined broadly as all structures, ditches, canals, culverts, and any construction that connects to, draws water from, drains water into, or is placed in or across waters in the state, unless the project is otherwise exempt. “So, just about any activity affecting surface waters is covered under the ERP program,” says Martin.
A 404 permit is required pursuant to the CWA for any activity that will discharge dredged or fill material into a WOTUS. Under the Navigable Waters Protection Rule, WOTUS includes:
Defined non-jurisdictional waters are set forth in 12 exclusion categories, such as features that contain water only from rainfall, groundwater, many ditches, prior converted cropland, and waste treatment systems.?
The definition of WOTUS and the navigable Waters Protection Rule have changed many times under different presidential administrations, and may be set to change again under Biden’s. For background, see our 12th webinar episode, Pitfalls of Ping Pong WOTUS Policy .
404 Assumption
The DEP in Florida estimated that the USACE permit and State ERP overlapped 85% of the time, meaning that most applicants processed two sets of permits for the same activity, incurring additional costs and delays. This overlap prompted the state, through DEP, to seek assumption. On December 2020, the Environmental Protection Agency approved the assumption by DEP. DEP enacted a new set of State rules designed for 404 state permitting, which can be found in Chapter 62-331 of the Florida Administrative Code. DEP also adopted a State 404 Applicant’s Handbook, which sets forth the roadmap for securing a permit, into the State administrative code. The Handbook must legally be followed by all applicants and the State agencies. DEP also entered into a memorandum of agreement with USACE and EPA, which set forth requirements for assumption and agreements with the wildlife agencies.
Challenges of the Assumption
In spite of the assumption, challenges still exist. For example, two sets of permits–an ERP and state 404– are still required for most activities. Additionally, there is a significant backlog of applications at the DEP, as some 591 pending applications where transferred to the DEP when the court reassigned the program. Review for these pending projects was restarted no matter how far along USACE was in its review process, since State rules differ.
领英推荐
Delegation of Permits
When DEP wrote the new state rule chapter, they placed provisions allowing for delegation by the EPA to the WMDs, which would allow permits to be issued by one state permitting agency. This additional layer of delegation has yet to go into effect.
USACE has retained authority over permits related to certain waters and activities, including:
The administrative boundary is a 300’ guideline established from the ordinary high watermark or mean high tide line of the retained water. The administrative boundary marks the adjacent wetlands over which USACE retains jurisdiction. IF a project involves discharges of dredged or fill material both waterward and landward of the 300-foot guideline, USACE will retain jurisdiction to the landward boundary of the project.?
To determine if USACE has jurisdiction over a project, Florida applicants can consult the following resources:
Current Processes
General Permits (GPs), Regional General Permits (RGPs), and Individual Permits
State 404 general permits were modeled after the 2017 USACE nationwide permits (NWPs), rather than the 2021 modifications. These are for projects with minimal adverse environmental impacts. Notice of GPs are sent to the State Wildlife Agency, the U.S. Fish & Wildlife Service (USFWS), and the Tribal Historic Office. Any of these agencies can request that the project be elevated to an individual permit. Seven regional GPs were also assumed by DEP.
Individual permits require public notice within 10 days of a project’s administrative completion. Notice is provided to adjacent property owners, interested parties, potentially affected states and tribes, and other affected agencies. Notice is posted on DEP’s local district website. There is typically a 30-day public comment period, where anyone can request a public meeting.
EPA Review
EPA will review certain categories of activities, with the review period beginning on the first day of a public notice. EPA also sends notice to USFWS, National Marine Fisheries Service (NMFS), and USACE, and then collects their comments to send to DEP. Within 30 days, EPA will comment, advise that it intends to comment, object, make recommendations, or reserve its rights to object.?
Modification of Existing 404
Under the current Memorandum of Agreement, USACE retains authority to process minor modifications to existing 404 permits. If the modification is not minor, it must be processed by DEP as a new permit. Any new delineations in Florida must be done under Florida; DEP cannot accept federal delineations.? Delineations must follow the Florida methodology found in the Florida Administrative Code. Any modification to a long-term USACE permit is limited to five years.
Mitigation Requirements
Applicants must continue to purchase both state and federal mitigation bank credits. DEP follows the mitigation hierarchy from the federal 404 permit, but this hierarchy can be overridden if there is acceptable mitigation which is environmentally preferable based on a watershed approach.
Project Lasting Over 5 years
Projects taking more than 5 years to complete may need to be divided into 5-year phases to fall under State permits. Applicants must submit information on any “reasonably related” activities using a long-term planning document so the entire project can be reviewed (see 62-331.051(2) & A.H. 5.3.2).
Listed Species Review
There is also opportunity for listed species review. Applicants must provide information regarding listed species that may be affected. DEP then provides the information to the Federal Wildlife Commission (FWC) and USFWS, requesting review and comment. DEP and USFWS developed a technical assistance process through a programmatic biological opinion (State 404 BiOp), and the Florida State and federal agencies collaborate on their review. The Florida Wildlife Commission will consolidate the state and federal review into a comprehensive response to DEP.?