Five ways HDD contractors can improve their contract hygiene in 2020
Ted Roberts
Lawyer steering horizontal directional drilling (HDD) contractors through contracts, project claims, and lawsuits.
This article describes five rules or practices that contractors can implement that will improve their odds of getting paid all they're owed without a fight. Following these rules should radically reduce both the amount and expense of any disputes on an HDD project (or any other construction project for that matter):
- Write down the important stuff.
- Treat your contract as a rulebook, not something to be signed and filed away.
- Thoroughly document any extras now, not later.
- Preserve your lien and bond rights.
- Make sure the contract you want is the contract you get.
1. Write down the important stuff.
Easy to remember and easy to do: get into the habit of recording important communications and events in writing, when they happen. It is no exaggeration to say that many lawyers would be out of a job if more contractors lived by the principle that, “if it’s not in writing, it never happened.”
While most of us know that contracts should be in writing, many contractors find themselves fighting over incidental agreements and commitments made during the project that neither side bothered to document. Here are examples of the “small things” that should be memorialized in writing:
- Agreements about any defective work or property damage.
- Commitments to pay for extra work or changes in the work.
- Agreements to accept non-conforming work or a substitute performance.
- Agreements to modify the original contract, including agreements to ignore (that is, “waive”) certain contract provisions.
- Agreements to modify the schedule or project deadlines.
Unless the contract requires something different, written documentation need not be lengthy or formal: a quick email can be enough, or a hand-written note signed by both sides.
2. Treat your contract as a rulebook, not something to be signed and filed away.
Good construction contracts anticipate and address the issues most likely to cause problems on an HDD project. These include what are commonly known as “project risks” or “construction risks”: delays and differing site conditions. The occurrence of one of these events should trigger an immediate review of the contract. Chances are, the contract will state how the contractor should respond, especially if the contractor intends to ask for additional time or money as a result. More often than not, the contract will require written notice and other documentation within a short period of time. A contractor who ignores these requirements is at risk of losing any rights it had to additional time or money (or both).
Events that impact a project’s schedule and cost are not the only reason to take a second look at your contract. Refer to your contract whenever:
- The parties want to modify the contract’s terms or the scope of work.
- One of the parties has defaulted—that is, failed to perform—on one of its obligations.
- One of the parties wants to terminate or abandon the contract before its completion.
All of the above assumes that your contract actually has something to say about these issues. Good construction contracts will address these issues and most do.
Some contracts, especially lower-tier subcontracts, do not. I have encountered more than one subcontract limited to a one-page proposal, without much else. If you are dealing with such a contract, then proceed with caution and consult a lawyer.
3. Thoroughly document any extras now, not later.
It is not uncommon for a contractor to incur additional, unexpected costs on a project through no fault of its own. Delays, contract changes and extras, and differing site conditions may all negatively impact the bottom line. And a contractor may have the right to be reimbursed for these costs. But a right to payment is only half the battle. The legal right to be paid means nothing if the contractor is unable to show what its actual costs were.
You may have heard this in math class: “Show your work.” This is also a good rule to follow when documenting any extras on a job. A contractor who is incurring extra costs should keep two goals in mind. The first goal is to segregate the extra costs so they can be easily distinguished from costs related to the work under the contract. The second is to show that the extra costs were the result of a specific cause; for example, extra costs attributable to delayed site access.
Detailed contemporaneous documentation can only help your cause. Paper the file. Was your work or equipment damaged? Assign a separate job-cost accounting code and document the damage and repairs with photographs and daily work records. Did you attempt to limit or contain your costs? Document that. If your schedule was impacted, make any necessary changes to your schedule. Was the matter discussed? Any discussions, agreements, and resolutions should be noted in writing when they happen.
Here’s what NOT to do. Do not wait until the end of the project and attempt to “guesstimate” your extra costs. Back-of-the-envelope cost calculations are rarely acceptable, either to those paying the bill or to a judge and jury sitting in a courtroom.
If you find this article interesting or helpful, please slap that "like" button. Also consider sharing it with someone who might also like it. Thinking about taking action based on something you read here? Please don't without first speaking to an attorney. This article is not legal advice.
4. Preserve your lien and bond rights.
Mechanic’s liens and payment bonds are among the most valuable tools available to an unpaid contractor. This is so for two primary reasons. First, lien and bond claims allow a contractor to recover its attorneys fees in most cases. Second, both offer another source of payment—a second set of pockets—to pursue when your customer is either unwilling or unable to pay. And if your customer is insolvent, or declares bankruptcy, a lien or bond may be your only way to get paid.
Liens and payment bonds are often not treated with the respect they deserve. The leverage and power of a lien or bond claim should not be underestimated. A contractor with a valid lien or bond claim is a lot harder to ignore and a lot more expensive to fight. The threat of attorney’s fees, or the pressure exerted by the owner of property that has been liened, may be enough to motivate the other side to drop its objections and resolve a payment claim sooner.
Here’s a rough guide for contractors wanting to keep these two weapons in their arsenal. Before starting work on a project, a contractor should, either by itself or with the help of a lawyer, answer these three questions:
- Do I have the right to file a lien or a payment bond claim if I am not paid?
- If so, are there any notice or filing requirements I must satisfy before starting the work?
- If I am not paid, what are the notice and claim requirements I must follow after completing the work?
Of these three, the third is the one most often bungled. Know this: many lien and bond laws impose strict deadlines upon a contractor wanting to assert a claim. Many contractors allow these remedies to lapse as they continue to negotiate with their customer. For this reason, I suggest that contractors know what they need to do before starting the work and, as they close out their project, calendar any deadlines for filing a lien or taking action against a payment bond.
5. Make sure the contract you want is the contract you get.
Expensive claims and lawsuits do not happen simply because something goes wrong on a project. Even if a project’s costs suddenly increase because of the unexpected—bad geotechnical conditions, for example—an expensive lawsuit is unlikely if the issue has been addressed by the parties’ contract.
The seeds of a lawsuit are often planted before the work is even started, when the contract is formed. This can happen when both sides believe they have entered into a contract but harbor different understandings about their rights and obligations. Unfortunately, many contractors do not fully appreciate the risks posed by the contract formation process until it is too late.
In my experience, this problem—both sides having conflicting ideas about the nature of their agreement—is present in a lot of disputes that end up in litigation. Here are three ways I’ve seen this happen on HDD projects:
- In the middle of a project, Contractor A subcontracts with Contractor B to complete some HDD crossings. Contractor A’s contract with the project’s general contractor incorporates the project’s specifications. Contractor A’s subcontract with Contractor B is silent on this issue. After things go wrong, the two contractors litigate the question of whether Contractor B and its work is, like Contractor A, bound by the project specifications.
- In the middle of a project, Contractor A hires Contractor B to complete some HDD crossings. After a telephone conversation about the conditions that Contractor A has encountered so far, the parties sign a contract consisting of little more than a description of the work and price. After mobilizing to the project, Contractor B discovers that neither water nor lodging is available within 60 miles. To make matters worse, Contractor B encounters geotechnical conditions inconsistent with what Contractor A had described. After things go south, the parties litigate the issue of whether Contractor A had misrepresented the project’s subsurface conditions and whether Contractor B had a right to assume that water and lodging would be nearby.
- Contractor provides Owner with a price proposal for HDD work. The proposal includes a term sheet that includes provisions that entitle Contractor A to be paid for stand-by time and to adjust its price upwards if the geotechnical conditions are different than those indicated. Owner asks Contractor to sign a contract that reflects Contractor’s price but does not include the contractor’s term sheet. If Contractor signs the contract, there is a substantial risk that its term sheet has been nullified. As a result, the Contractor has effectively agreed to take on greater risk during the project, without an increase in its price.
Here's the point: a contractor’s mishandling or misunderstanding of the contract formation process can be financially disastrous if things go wrong. Contractors can manage risks they know about and price their work accordingly. On the other hand, any risk that a contractor unknowingly agrees to amounts to a blind spot and leaves the contractor vulnerable.
Here are some ways to make sure the contract you want is the contract you get:
- Anything important to you or your price should be in writing, in your contract. “In your contract,” means the written documents that both sides have agreed to. It does not mean your bid or proposal, unless the contract expressly says it does.
- Do not rely or depend upon agreements and statements that precede your contract, unless they also find their way into the written contract.
- Do not rely on industry “customs” and “practices” to get what you want. A judge or jury will not care if it’s customary to pay stand-by time, or that no money is paid for an incomplete crossing, if neither issue is addressed in the contract.
- Make sure your set of contract documents is complete. This is a bigger problem than many contractors realize. Most subcontracts contain “flow down” clauses, provisions that incorporate the terms in an upstream contract; for example, the agreement between the general contractor and the project’s owner. The two contracts are not always consistent and, in some cases, the terms in the upstream contract may override or nullify the terms in the subcontract. If your contract incorporates other agreements or documents, it is important that you obtain and review these documents before signing the contract.
- Increase your contract literacy. Given that most contracts are signed without the involvement of a lawyer, most contractors would benefit from a better understanding of how contracts work and, especially, how to spot and understand terms most likely to get them in trouble. Such terms include those that limit a contractor’s right to recover losses caused by the other side, indemnity clauses, warranty provisions, and disclaimers. To be honest, I have no idea how contractors wade through the legal mumbo-jumbo that passes for contract drafting these days, other than to learn from trial and error. However they do it, contractors should empower themselves to understand the terms commonly included in construction contracts and the business purposes they are meant to serve.
Closing thoughts
While there are more ways to prevent claims than what is discussed here, I have tried to discuss things that a contractor can do without much trouble or expense. All five rules are distilled from my experience litigating claims on HDD projects. Any contractor who implements these practices should see three benefits. First, the contractor should encounter fewer objections to payment. Second, any disputes should be resolved sooner. Finally, any disputes should be resolved on better terms—that is, the contractor will see more money.
Marine Operations Manager at McDermott International Inc.
5 年Well done!
Retired from Missouri Department of Transportation after 27 1/2 years
5 年Mr. Roberts, two issues stand out in my mind as having huge potential for legal pitfalls with potentially expensive remedies: the lack of adequate advance geotechnical information on a job and failure to make precise and accurate one-call notification. Accurate bidding is made possible by a concise geotechnical report in advance of bidding.? Boring information from a qualified geologist/geotechnical engineer enables a contractor to bring the correct equipment to the site and have some ballpark idea of speed of completion.? Failure to have or provide for this information is an open invitation to a claim of conditions not being adequately represented in the contract. The person in charge of performing the work should ALWAYS make the one-call notification. to identify and mitigate any potential utility conflicts; a contract should make sure that this practice is followed.? It's the law in all 50 states to CALL BEFORE YOU DIG.? Underground damage may not only be the root cause of death or injury, it might also be the reason for expensive and time-consuming repair.? Failure to make the notification is the leading cause of damage in many states.