The Final Chapter of 2024: Preparing for the Future
As the year comes to a close, we’ve made significant progress on multiple fronts! Around the same time we began drilling for geothermal energy, work started inside the building to prepare for a new substation for the heat pumps, a fresh ventilation room, and a dedicated area for our future packing stations.
Creating space for these developments was no small feat. In a tightly packed property, our logistics team faced the challenge of clearing valuable storage areas to make way for construction. They excelled, quickly dismantling pallet racks, storage shelves, and even two ventilation units to get the project rolling ahead of schedule.
We’re optimizing the room’s high ceilings by building a CLT (cross-laminated timber) loft. The upper level will house the new ventilation room and unloading areas for packaging materials, while the ground floor will feature the new geothermal substation and state-of-the-art packing stations.
This smart use of space offers two major benefits:
This room is set to become the beating heart of our facility—not only as the central hub for key building technologies but also as the home base for our logistics team, the heart of our operations.
We’ll be back with more updates in 2025!