Facts and Common Sense

Facts and Common Sense

I'm often asked to explain how I put together a delay analysis based on facts and common sense. This is my usual response.

Assemble the following facts and place on a gantt chart..

1. The time slot where the contactor planned to carry out the delayed task. Set ALAP

2. The duration of the remaining work set as a single bar and terminating at the completion date. This is the Contractor's time entitlement to complete the work. It may contain a critical path but that does not matter.

3. The as built duration of the delayed task. This has to be accurate and based on recorded facts.

4. Add the duration established in line 2 above to show the delayed end date.

5. Establish the duration of the delay event which is then placed somewhere between line 1 & 3. I colour this line bright scarlet based on the "Doberman's balls" principle.

6. Now apply your experience and common sense to explain how and why the delay event filled the gap and caused the delay - or not.

This method can be used for every event listed in your schedule and in whatever order you choose to present.

It has the advantage that every event has the potential to delay the completion date – and not just use up float – will be considered as viable in your analysis.

I'm available for commissions as expert delay analyst on either referral or response. Please send a private message so that we can chat.

Or telephone (01986) 892345 or email [email protected]

Matiwos Tsegaye

Planning Engineer_Practicing Construction Engineer in Project Management-Licensed/Primavera P6 Trainer/PM trainer

5 年

Hi Mike! p6, Asta, TILOS do not have programming feature to levelling resources while resource curve is considered. is there add on you know? Regards!

回复
Jonathon Winter MRICS

Chartered Building Surveyor specialising in Project Management and Building Defects

5 年
回复

要查看或添加评论,请登录

Mike Testro的更多文章

  • THE SCHEME - How to save the Construction Industry

    THE SCHEME - How to save the Construction Industry

    THE SCHEME A Suggestion For Future Construction Projects. This Scheme will ensure that future construction projects are…

    6 条评论
  • KEY Milestones

    KEY Milestones

    Key Milestones to use when planning. Multi Storey Structures 1 Introduction.

    5 条评论
  • Collapsed Critical

    Collapsed Critical

    Collapsed Critical An Alternative to TIA 1 The fundamental difference. 1.

    7 条评论
  • Prolongation Costs Explained

    Prolongation Costs Explained

    Prolongation costs? Delay analysts and quantum experts often discuss the topic of prolongation costs after an extension…

    4 条评论
  • Offer - Acceptance - Consideration

    Offer - Acceptance - Consideration

    Fred and Bill were best mates. Scenario 1 Fred noticed that there was a shop in town with a computer that he…

    7 条评论
  • Collapsed Critical

    Collapsed Critical

    A simple method of analysing delays using every relevant event. Note: this method only works using ASTA PowerProject 1…

    2 条评论
  • Certificate of Competence

    Certificate of Competence

    Of the many candidates that have subscribed to and studied my 10 modules on the Basic Principles of Delay Analysis…

  • Entitlement - Need - Calculate

    Entitlement - Need - Calculate

    Comparisons of meaning of three different forms of contract. 1 Extensions of time.

  • A solution to the EOT problem.

    A solution to the EOT problem.

    Currently Main Contractors compete mainly on price. The biggest risk that all parties face is delayed completion.

    4 条评论
  • Ban These Planning Abominations

    Ban These Planning Abominations

    In 2009 I posted this article on Planning Planet, it caused a bitter controversy then but it is still applicable today,…

    4 条评论

社区洞察

其他会员也浏览了