EXCAVATION OF CHAMBERS FOR SEWER MANHOLES

EXCAVATION OF CHAMBERS FOR SEWER MANHOLES

Prior to any excavation taking place, the contractor should de-marcate the area where work will take place and the area will then be marked out. Once the area is marked, excavations may begin and digging should only take place up to the correct depth and width as per drawings and specifications. All excavation to be battered to ensure for a safe working area.

The depths of excavations will be determined using a surveyor who will set out bench marks for the determination of invert levels. The invert level is the base interior level of a pipe, trench or tunnel; it can also be considered as the "floor" level.


Excavations and Sewer line installation

Take note that the invert is an important datum for determining the functioning or flow line of a piping system. Once this level is established, the contractor should level out the base for compaction as per specification and drawing i.e. 95% MOD AASHTO.

Once this is complete, there should be installation of formwork/shuttering as per drawing designs for the casting of the Manhole Bedding. Concrete cube tests to be taken on every single batch and sent to an independent lab for testing before the construction of the Manhole chamber using brickwork (Clay Bricks) is done.

Paul Matthews

CEO at PaulM Leads

5 个月

Safety of our work force as well as the public is such an important aspect to an construction or excavation site

回复

要查看或添加评论,请登录

Katlego Motlhabane的更多文章

  • Axle Factors in Pavement Design

    Axle Factors in Pavement Design

    Standard Axles The mass and number of heavy vehicles (NOT PASSENGER VEHICLES) are the biggest influence factors in the…

  • Types of Pavements

    Types of Pavements

    Roads are designed taking into consideration the type of pavement design required for a particular stretch. The most…

  • Composition of a Pavement (Pavement Structure)

    Composition of a Pavement (Pavement Structure)

    Road Prism A road is generally made up of a road bed, earth works, pavement layers and surfacing. The road bed would be…

  • Composition of a Road

    Composition of a Road

    Aim of this article · Understand the influence behind the geometry of a road, the design of its earthworks ad how to…

  • Crossing A Pipeline Across The Road

    Crossing A Pipeline Across The Road

    When installing a pipe across an existing road, one method to go about it would be to do open cuts as per pipe…

    1 条评论
  • Trenching and Excavating

    Trenching and Excavating

    Construction sequence and method GENERAL A section Foreman should be responsible for each excavation front. A…

  • Topsoil Stripping and Stockpiling (Pipe Route)

    Topsoil Stripping and Stockpiling (Pipe Route)

    After clearing and grubbing has been completed the grubbed material will be placed in designated areas. A similar…

  • Efficient HDPE Pipe Installations

    Efficient HDPE Pipe Installations

    In the event that the installation of a pipeline system is required under ground ((below the natural ground level) and…

  • Reno Mattress

    Reno Mattress

    Reno Mattresses which are also known as Revet Mattresses, are gabion type structures that are usually manufactured from…

  • Erosion Protection using Geotextiles

    Erosion Protection using Geotextiles

    In a bid to prevent erosion and subsequent flooding on roads that cut through land, KAYTECH Engineered Fabrics such us…

社区洞察

其他会员也浏览了