Everything You Need to Know About N/A

Everything You Need to Know About N/A

Not Applicable N/A

1????????Standard contract.

1.1??What happens when N/A is used.

1.1.1????It is common practice for the employer or the contractor to strike out an applicable clause with the term N/A believing that is therefore not applicable to their agreement.

1.1.2????What they have actually done in practice is ?to declare that this particular clause forms no part of their agreement.

1.1.3????If they intended that the risk should be borne by either the contractor or subcontractor then a specific phrase should be used to denote this is the case.

1.1.4????If the person who’s draft of the contract had amended it by stating phrase such as “All At Contractor’s Risk” then that would have been sufficient for the purpose.

1.1.5????It will need such specific words to make it binding on the contracting parties.

2????????Result of N/A when used.

2.1??On non-risk clauses.

2.1.1????If the clause is merely explanatory and does not convey any risk to either party then it is clear that the contracting parties consider it unnecessary.

2.1.2????Typically they would apply to descriptions of such things as:

2.1.2.1???Sectional completion.

2.1.2.2???Insurance options.

2.1.2.3???Fixed price or fluctuation options.

Etc

2.2??Risk clauses including time and money.

2.2.1????If a particular clause is no longer applicable to the contracting parties then the party that struck it out as being N/A would normally be accountable when that risk arises.

2.2.2????This is based on the principle of Contra Preferentum, where he who makes the changes bears the risk.

2.3??Time Risk.

2.3.1????This is particularly applicable where relevant events causing delay are struck out as N/A such as:

2.3.1.1???Exceptionally adverse weather conditions.

2.3.1.2???Works carried out by statutory undertakers.

Etc.

2.4??Money Risk.

2.4.1????Any divergence between Employer’s requirements and Contractor’s proposals.

3????????Conclusion.

3.1??N/A does not mean “not applicable”.

3.1.1????In practice it means the start of a dispute whereby the contractual risk can be applied to the party that drafted the contract in the first place.

3.1.2????It will take clear and specific wording in the contract to transfer the risk to either the contractor or the subcontractor involved.

3.2??Disclaimer.

3.2.1????There are no recent cases that I can call on to substantiate this opinion of mine.

3.2.2????The earliest case that mentions “not used” is Inglis v Battery 1878 where is decided that the term “not used” meant that the clause was completely obliterated.

3.2.3????My opinion therefore is that if the clause was completely obliterated than the risk should fall on the party that obliterated it.


Contact:

Mike Testro

01986892345

[email protected]


Peter Holroyd

Nearly Retired at BROOKSON (5409) LIMITED

3 年

Mike, any thoughts on blank?

回复

要查看或添加评论,请登录

Mike Testro的更多文章

  • THE SCHEME - How to save the Construction Industry

    THE SCHEME - How to save the Construction Industry

    THE SCHEME A Suggestion For Future Construction Projects. This Scheme will ensure that future construction projects are…

    6 条评论
  • KEY Milestones

    KEY Milestones

    Key Milestones to use when planning. Multi Storey Structures 1 Introduction.

    5 条评论
  • Collapsed Critical

    Collapsed Critical

    Collapsed Critical An Alternative to TIA 1 The fundamental difference. 1.

    7 条评论
  • Prolongation Costs Explained

    Prolongation Costs Explained

    Prolongation costs? Delay analysts and quantum experts often discuss the topic of prolongation costs after an extension…

    4 条评论
  • Offer - Acceptance - Consideration

    Offer - Acceptance - Consideration

    Fred and Bill were best mates. Scenario 1 Fred noticed that there was a shop in town with a computer that he…

    7 条评论
  • Collapsed Critical

    Collapsed Critical

    A simple method of analysing delays using every relevant event. Note: this method only works using ASTA PowerProject 1…

    2 条评论
  • Certificate of Competence

    Certificate of Competence

    Of the many candidates that have subscribed to and studied my 10 modules on the Basic Principles of Delay Analysis…

  • Entitlement - Need - Calculate

    Entitlement - Need - Calculate

    Comparisons of meaning of three different forms of contract. 1 Extensions of time.

  • A solution to the EOT problem.

    A solution to the EOT problem.

    Currently Main Contractors compete mainly on price. The biggest risk that all parties face is delayed completion.

    4 条评论
  • Ban These Planning Abominations

    Ban These Planning Abominations

    In 2009 I posted this article on Planning Planet, it caused a bitter controversy then but it is still applicable today,…

    4 条评论

社区洞察

其他会员也浏览了