Energizing the Permian Basin: ERCOT’s Plan to Power the Future

Energizing the Permian Basin: ERCOT’s Plan to Power the Future

The Permian Basin, one of the most prolific oil and gas regions in the world, is set for a major power boost. Here's how ERCOT is gearing up to serve the Permian Basin's load growth with a comprehensive reliability plan (with?an outline of planned transmission lines and costs).??

Executive Summary: In response to H.B. 5066, ERCOT has developed a robust reliability plan for the Permian Basin. This plan aims to extend transmission services, increase capacity to meet growing demand, and enhance infrastructure for faster connections. With final approvals expected by September 2024, here’s a snapshot of what’s in store.?

Key Facts:?

Legislative Mandate:?

  • H.B. 5066 requires the PUCT to direct ERCOT to create a reliability plan for the Permian Basin.?

  • Goals include expanding transmission services, boosting capacity, and improving infrastructure.?

Strategic Timeline:?

  • July 2024: ERCOT files the final reliability plan.?
  • July - August 2024: Stakeholder feedback period.?

  • September 2024: PUCT reviews and approves the plan.?

Major Projects by 2030 to serve Permian Basin Load Demand:?

  • 345kV and 138kV Lines: New lines and substations to support load growth.?

  • New Import Paths: Enhanced connections to ensure reliable power delivery.?

Future Infrastructure by 2038 to Better Connect the Permian Basin w/ ERCOT:?

  • Extended Networks: More 345kV and 138kV lines and substations.?

  • EHV Lines: Evaluating 500kV and 765kV lines to improve long-distance transmission and reduce losses.?

Transmission Models and Cost Tables from ERCOT’s “July 16th Permian Basin Reliability Plan Study – Status Update”??

2038 Planned Local Transmission Projects:?

*taken directly from July 16th Permian Basin Reliability Plan Study Update?


3 Options for connecting the Permian Basin w/ ERCOT by 2038?

Option 1: 345kv Lines?

*taken directly from July 16th Permian Basin Reliability Plan Study Update?

Option 2: 345kv Lines + 500kv Lines?

*taken directly from July 16th Permian Basin Reliability Plan Study Update?

Option 3: 765kv Lines?

*taken directly from July 16th Permian Basin Reliability Plan Study Update?


Cost Estimates:??

*taken directly from July 16th Permian Basin Reliability Plan Study Update
*taken directly from July 16th Permian Basin Reliability Plan Study Update

What’s Next??

With the final report due in July 2024 and stakeholder feedback shaping the plan, the next few months are crucial. Transmission Service Providers will soon be filing for construction permits, marking the start of a new era in the Permian Basin’s power infrastructure.?

Get Involved! Share your feedback during the stakeholder period and stay tuned for updates.?