Electrical Protection Failure - $4 million Vestas Wind Turbine V120 on Fire - SEL, Vestas, Ormazabal, ETAP blamed for the incident; Wait a minute!
Thierry Julio Epassa- P.E. in Sixteen USA States
Electrical Engineer Director || Arc Flash, Short Circuit, Electrical Studies|| US Security Clearance || Linkedin Newsletter Author|| OSHA, IEEE, NFPA Expert||Contractor for 1328 US Federal Facilities Arc Flash Studies
A debacle in protection and power studies:
Preliminary investigations assigned possible blame to:
Not so fast. A headache is usually a symptom of a sickness, not the root cause. What is the root cause?
Figure 1 below is the feeder E relay event that captured the fault.
Figure 1: SEL relay event showing lack of electrical protection during the fire incident
At the end of the event, the peak of the curves starts to reduce. There is a catastrophic reason.
Why did the SEL relay never assert a trip? Moreover, where was the backup SEL relay? Why didn't the backup relay assert a trip?
I came across this long ongoing investigation via their facility electrical engineer. I proposed simulating the fault in their existing (ETAP model) model and comparing simulation results vs. real life. Numbers don't lie! The facility engineer responded:
“I have never heard of that; how is it even feasible? You don’t have enough data to simulate similar fault events in the software; What about utility data? Loading conditions before the fault? Current contributions from other turbines? Moreover, We already reviewed several times our simulation model with a competent firm and found no major issues, etc.”
I responded: "I have all the data needed! It would take less than 1 week to simulate the exact fault on your existing simulation model. Moreover, if you give me 2 additional weeks and your drawings, I can show you my modified version of your ETAP model". They did not believe me and reluctantly agreed.
Step 1: Retrieve all pre-fault current conditions and talk with site operations.
Notice in Figures 2 and 3 below, I highlighted in grey square some essential information; all the info are pre-fault conditions.
Figure 2: Relay event at Transformer T1 during the fault
Figure 3: Relay event at Feeder E during the fault
Step 2: Configure simulation software to match loading conditions pre-fault.
Run power flow in the ETAP simulation to show that loading conditions match pre-fault data in the field.
Figure 4 below shows transformer and Feeder E ampacities. 420 A and 138 A match the same current ampacity shown in Figures 2 and 3
We now have a simulation model that matched identically actual conditions in the field, nanoseconds before the fault occurred. The wind farm was operating at 20% of nominal conditions before the fault occurred.
Figure 4: ETAP model showing loading matching pre-fault conditions
Step 3: Fault the turbine in the software to simulate the real-life incident.
Place a BC fault at the Ormazabal Switchgear inside V120 and observe the fault currents in Feeder E and the Transformer main breaker. The fault occurred 24930 ft (4.7 miles / 7.6 km) from the substation. The technical detailed fault analysis will be part of another article earlier next year.
Figure 5 on the right is their current existing model. with a BC fault simulating the incident that occurred, fault current main transformer = 8,000 A. Feeder E fault current = 8,700 A
Figure 5: ETAP model showing flawed fault current values
领英推荐
Figure 6 on the right is my modification. With a BC fault simulating the incident, fault current main transformer = 6,200A. Feeder E fault current = 6,700 A. I want to stress that most data entries were the same as their previous model.
Figure 6: Modified ETAP model showing matching current values
Let's compare the values above with the real-life values during the incident at both the transformer and feeder E.
Look at figure 7 and 8 below. I removed the sinewaves' instantaneous values and inserted magnitudes values of currents and voltages. Orange time cursors show current values during the electrical fault.
Figures 7 and 8 below state:
Figure 7: Relay at the transformer showing current and voltages values during the fault
Figure 8: Relay at Feeder E showing current and voltages values during the fault
- SEL metering readings were on point. Both SEL relays (primary and backup) did not misoperate.
- ETAP software integrity is not an issue. the software works ideally and is accurate
- Vestas data were correct
- Ormazabal Switchgear and Vestas turbine had no issue; they were victims of an inadequate protection scheme. primary and backup relays were not programmed adequately because power studies and simulations were inaccurate
It is the 21st facility where I witnessed the same issues. Every power system model/simulation I tested with actual incidents has been significantly incorrect. The inaccuracies have led to significant incidents. 15,000 incidents, 600 relays reviewed or reprogrammed, 20,000 arc flash labels redone, 3 fatalities, 2 cogen generator complete rewound, 10 known wind turbine catastrophic failures, wind farms yearly production losses, etc.
Why are we one of the rare disciplines on this planet that believe that if data from electrical drawings are correctly input into software (ETAP, SKM, PSSE, Easy power, Aspen, etc.), our power system simulation must be accurate!
Let me be as loud as I could be: it is highly unfeasible to produce accurate power studies on high and medium complexity power systems SOLELY based on electrical drawings and data input in simulation software! Our current best practices are significantly flawed.
For the next 20 years, I intend to write 1,040 articles (weekly articles) on this Linkedin newsletter, and countless of those articles will show you how flawed practices are in performing power studies and verifying their accuracy.
Power studies errors are the primary reason that failures and anomalies occur in power systems; unfortunately, we have no idea because we don't even realize how significantly flawed our simulation models are. We can't even accurately prove the accuracy or inaccuracy because we SOLELY rely on theory.
"In theory, theory and practice are the same. In practice, they are not."
Albert Einstein.
"Garbage In, Garbage Out" in power systems simulation does not mean "Not Garbage In, Not Garbage Out."
Thierry Epassa
Electrical Engineering & Business Development Consultant
2 年Very good review note on fault analysis from all point of view. Thanks Mr.Thierry?for sharing the same. One has to double check the entire system integrity (including the settings of protection relays & control logics) before energizing the system. The replacement of equipments either at cost or free (on goodwill basis) is no more a solution for the problem. Of late we are seeing the engineers who are specialized only to their products or solutions and no knowledge on system as a whole. They keep on passing the blame to others and least bothered to solve the issue.
Senior Protection & Controls Engineer
2 年This seems like childs play to me. SEL relays are typically never wrong, ETAP isn't wrong unless the user did something wrong in the setup. What I would be curious to see is the TRIP equation in the SEL feeder relay. I'd have to run simulations in ETAP, but I expect I would have done something like TRIP = 67P1T + 67G1T +67QT or'ed with phase TOC, negative sequence TOC and ground TOC to see through the turbine if you will. Set the 67's at 18 cycles to protect the cable and up to the turbine, but to not see through the turbine. Let the time overcurrents see through the turbine. I suspect they didn't have any negative sequence elements set or they would have caught the L_L fault. Also keep in mind when you have a fault quite often it will start as a line to ground fault, but then it will evolve into a L_L and if not de-energized it could evolve into a 3 phase fault. This fault appears to have started as L-L, but it is more common to start L_G and then evolve into other fault conditions.
Electrical Engineer Director || Arc Flash, Short Circuit, Electrical Studies|| US Security Clearance || Linkedin Newsletter Author|| OSHA, IEEE, NFPA Expert||Contractor for 1328 US Federal Facilities Arc Flash Studies
2 年Michael Prater
Electrical Engineer Director || Arc Flash, Short Circuit, Electrical Studies|| US Security Clearance || Linkedin Newsletter Author|| OSHA, IEEE, NFPA Expert||Contractor for 1328 US Federal Facilities Arc Flash Studies
2 年Al Langland
Electrical Engineer Director || Arc Flash, Short Circuit, Electrical Studies|| US Security Clearance || Linkedin Newsletter Author|| OSHA, IEEE, NFPA Expert||Contractor for 1328 US Federal Facilities Arc Flash Studies
2 年Zachary Thompson