EGL (Kadmar Group) Successfully Completed Cairo West Power Station Project

EGL (Kadmar Group) Successfully Completed Cairo West Power Station Project

EGL just completed “Cairo West Power Station 650 MW Steam Power Station” project for Cairo Electricity Production Company. The project includes one 650 MW steam thermal power plant to interconnect with the National Unified Power System (NUPS) through a 500/220 KV GIS switchyard. It comprises one Rankine cycle sub-critical turbine generator unit with a nominal rated capacity of 650 MW using natural gas instead of heavy fuel.

No alt text provided for this image

Project Execution and Completion:

During June, July, and August, September 2019, Egyptian Global Logistics (EGL), subsidiary of KADMAR GROUP completed transportation of the Cairo West Power Station project. In addition, EGL succeeded to deliver accessories and containers to the same site including the arrangement of much clearance formalities and getting approvals from the authorities to clear containers in the port. The site is about 258 km from the port of Alexandria on the west bank of the Nile river.

It was a challenging operation scheme performed and completed, despite the difficult conditions. One of the greatest difficulties, besides the Project, was the discharging of 4 x 228-ton Trafos and accessories. The same vessel delivered another 4 x 228-ton Trafos for another project. The port was congested, so special arrangement to berth the vessel alongside the container terminal and to secure sufficient storage space for unloading the units at the port of El Dekheila were made.

No alt text provided for this image

Other important activities were route survey, transport study for choosing the most economical route from the port to the site including bridges study, civil work, crossing cities during the night time, moving under electric high voltage cable, removing traffic signs, removing sidewalks, removing trees all over the route, compacting the ground to bypass bridges, site preparation, soil compacting, shifting from 16 Axles 3 Files configuration used during the transportation to 12 Axles 2 Files inside the Site due to the manoeuvring problems. The site became busy and could not be accessed with 16 Axles x 3 Files Modular Trailers.

EGL people engaged in the project:

36 staff members including: engineers, technicians, administrators, safety officers, escort staff, drivers, mechanics, electricians, riggers and custom clearing staff.

No alt text provided for this image

EGL provided the whole scope of operation and avoided increasing costs of overhead cables and gantry, completing the whole project smoothly during 28 days. The Trafos were delivered to the Site in good condition.

  • First 228-ton Trafos left the Port 06-Sep-2019
  • Last 228-ton Trafos delivered to the Site 03-Oct-2019


EGL continues to impress the market with the well-trained staff along with the latest fleet equipment and technology in Egypt. EGL achieved this success through careful planning without sacrificing safety aspects.

Please click here to watch a video for the project execution:

Contact: Haytham Hussein <[email protected]>


Read more cases: https://www.wcaprojects.com/CaseStudies/