EFS Logistics Completed Carbon Steel Pipe Project
WCA Projects
WCA Projects is an alliance comprising many of the world’s most experienced independent project forwarders
The Carbon Steel Pipe Project involved the meticulous management and transportation of 156 carbon steel pipes, each measuring 16 meters in length, with a total weight of 1259.8 MT. The project required not only logistical precision but also a keen understanding of the complexities involved in handling such large and heavy materials.?
Route Survey: A comprehensive route survey was conducted to ensure that the transportation path was feasible and safe for the movement of the oversized pipes. This survey was critical in identifying potential obstacles and planning the best possible route to avoid delays.
Customs Clearance: Efficient handling of customs clearance at Jeddah Islamic Port was essential to keep the project on schedule. The team worked closely with customs officials to expedite the clearance process, ensuring compliance with all regulations.
Loading, Lashing, and Securing: The loading and securing of the pipes required specialized equipment and expertise. Each pipe was carefully lashed and secured to prevent any movement during transportation, minimizing the risk of damage.
Transportation Management: The transportation of the pipes from Jeddah Islamic Port to the delivery site in Al Marwa, Jeddah, was carried out over 156 trips. Each trip was meticulously planned and executed to ensure the safe and timely delivery of the pipes.
领英推荐
Outcome: Despite the challenges posed by the size and weight of the pipes, the project was completed successfully and on time. The team's proactive problem-solving approach and dedication ensured that the carbon steel pipes were delivered to the customer without compromising on quality or deadlines. Continuous and timely updates were provided to the customer, maintaining transparency and trust throughout the project.
Key Achievements: Successful transportation of 156 carbon steel pipes over 156 trips. Completion of the project within the stipulated timeline. Maintenance of high standards in quality and safety during the entire process. Achievement of customer satisfaction through transparent communication and reliable service.
For more information, please contact Mr. Nadir Kalappadan, Executive Director <[email protected]>
Read more cases: www.wcaprojects.com/CaseStudies
Managing Director @ Round the clock logistics pvt ltd
1 个月Very promising!
OPERATIONS MANAGER at ATLAS CARGO
2 个月Excellent work NAJEEB n Team.
General Manager - Business Development
2 个月