Earned Value Management : An overview

In order to be successfully applied, this technique requires the following information:

1. The Project Management Plan, in particular as regards the description of the deliverables, the cost plan and the project times

2. The cash flow over the entire duration of the project containing the outgoing (Planned Value) and incoming flows as indicated in the Plan

3. The rules for accounting for the work carried out which in turn must take into account the contractual agreements agreed with the customer or with the external or internal lender. In this sense, the bookable value (or Earned Value) is different if a criterion has been agreed as a percentage of completion or delivery deliverable (0 - 100) or with a value at the beginning of the works, one in the middle and one at the end (e.g. 20 % - 80% or 20% - 40% - 40%).

Based on this information, it will be possible to obtain the following three values at any time of the project:

? Planned value (PV) - expected cost at the date as planned;

? Actual Cost (AC) - cost actually incurred on the date as deduced from the order accounting or from extra-accounting records;

? Earned Value (EV) - cost that can actually be "tipped" to the customer or lender in the light of the agreements referred to in point 3 above).


Ultimately the EV on a certain date constitutes the cost that can be overturned on the customer if the project was interrupted on the measurement date.

This value (EV) must be periodically analyzed:

? comparing it with the Actual Cost (AC) to substantially assess whether you are spending more than you are actually earning;

? comparing it with the Planned Value (PV) to assess whether or not it is in line with what is reported in the Project Management Plan from the point of view of the time trend of costs.

To carry out this assessment, therefore, the following four values  must be taken into account, all calculated on the basis of the earned value:

? Cost Variance (CV): EV - AC | a negative value indicates that you are spending more than what you are earning

? Schedule Variance (SV): EV - PV | a negative value indicates that you are earning less than what was expected and therefore you are late with the delivery of the deliverables

? Cost Performance Index (CPI): EV / AC | a value less than one indicates a tendency to spend more than necessary

? Schedule Performance Index (SPI): EV / PV |a negative value indicates a tendency to deliver late than expected

Periodically these values  can be measured in order to have the picture of the financial performance of the project to be presented in the Work Progress Status together with other information for checking progress.

Other useful values  for this are:

? Budget at Completion (BAC): indicates the overall budget of the project as indicated in the Project Management Plan

? Estimate at Completion (EAC): BAC / CPI | indicates on the measurement date what is the estimate of the final cost that is expected to be completed on the basis of the CPI (deemed constant for the following period) which in turn depends on the earned value

Based on the previous indicators, it is possible to build others that allow you to refine the analysis or to bring out other aspects of the project to pay attention to.

In general, these values, measured from time to time, then allow you to determine trends, trends that it might be appropriate to correct to bring the project back in line with expectations as shown as an example in the graph below.

No alt text provided for this image


Here's also a schematic classification of the main traditional EVM variables :

No alt text provided for this image



要查看或添加评论,请登录

Giorgio Torre的更多文章

社区洞察

其他会员也浏览了