Early Contractor Involvement - the way ahead?

Early Contractor Involvement - the way ahead?

The name ‘Early Contractor Involvement’ (ECI) first appeared around 2004 when the UK Highways Agency used it to describe an initiative which had been launched in the ‘Highways Agency Procurement Strategy 2001’ using another name, ‘Early Contractor Design’. The title 'ECI' and the Highways Agency strategy was adopted in 2005 by the Queensland Department of Main Roads in Australia where it is still in use today. 

PIANC has a working group writing a report on ECI to be published in 2021 for guidance of the use of ECI for the waterborne infrastructure sector. It defines ECI as :

ECI is a strategy (by whatever name) initiated by infrastructure owners (Clients) towards contractors, key supply chain members and stakeholders with the purpose of optimizing values in project delivery and objectives through their participation and knowledge-sharing in stages of project planning and design prior to execution contract award.

In the intervening years the application of ECI in procurement has also taken root in many other countries apart from the UK and Australia, including the US, Netherlands, Belgium, Japan, Norway, Sweden and Finland and it takes a few different forms which includes concepts of collaboration, partnering and alliancing, which are sometimes described as ‘collaborative working’.

Despite Australia being in the forefront in the use of ECI back in 2005 sadly today little use and application of ECI is seen in the construction sector and the marine infrastructure sector in particular. The last landmark projects being Port Phillip Bay Channel Deepening and Fremantle's Inner Harbour Dredging back in 2010. 

No alt text provided for this image


Marine infrastructure projects share characteristics with projects in other transportation sectors such as rail and road, including:

?   the need for consultants to develop designs to take into account construction methods and equipment?;

?   the need to identify the type of equipment to be deployed early in the permit and approval process so that any environmental permit can be tailored to the likely equipment used in the construction phase;

?   the impact of some design decisions being significant in regard to cost, time and performance?

?    the vital importance of good geotechnical information which accurately represents the project's ground conditions as this ultimately impacts on the execution of the works, the choice of materials and the type of design. So seek contractor input on the type and scale of geotechnical investigation that is needed.

It has to be realised by contractors that a wish for wholesale adoption of ECI for every marine infrastructure project is a utopian dream. It is simply not practiced by Client organisations who always strive for the lowest tender price nor do a lot of government organisations allow it in their existing Public Procurement rules.  However a two-stage procurement approach to contracting (with competition) can satisfactorily deliver what is needed, then it is unnecessary, possibly counterproductive and usually difficult to justify in terms of procurement regulations for a Client to adopt a procurement strategy based on ECI.

I would suggest that the application of ECI is particularly justified on projects where the potential project requires contractor input on the scope of the geotechnical information which is needed; where choices need to be made in the equipment defined in permitting and licencing phase; where the project involves innovative techniques or materials or if the project is to be achieved in unusual and challenging conditions.  

In such situations there is scope for ECI to achieve improvements and effectiveness during the early phase of the project which will have added benefits in the design and construction phases.  

   

Richard Hardstaff

Free thinker providing unbiased opinion

3 年

In a competitive environment it sometimes difficult for Contractors to give up ther best ideas and see them shared with other Bidders. Especially when Clients play-off a two-horse ECI process. Apart from that, agree that ECI can be important to Clients, designers and other end-users.

Chris Bailey

Senior HSE Professional: Team Leader | Assessor | Mentor | Advisor | Auditor | Investigator | Leader | Systems Manager | Technical Writer | Avid 4WDer

3 年

Especially true when the reason contractors are being engaged is because of their capability and expertise. Who better to help you understand the risks, frame your contingencies, and clearly scope the work?

回复
Ian Wright

Geologist / Client Rep / Manager BSc (Hons), MSc, PhD, FGS, Pr.Sci.Nat.

3 年

I think this makes particular sense from a geotechnical and geohazard perspective as it provides a mechanism (mostly time?) for the detailed geological model to be generated and there after all the specialist detailed design to be formulated.

Richard Patterson

BA MBA CEng FICE, NEC and Procurement Specialist at Mott MacDonald

3 年

David Kinlan good post. Thanks. It kept me up as I am giving training tomorrow specifically on ECI and more specifically on Option X22, the ECI option in the NEC Engineering and Construction Contract (ECC). ECC is one of very few standard forms with an option for ECI. Your article also had me reminiscing on the early days as I was part ot the Mott MacDonald team that helped the Higways Agency as was on an early version of ECI..... for a little project with a tunnel under Stonehenge! That must have been twenty years ago. I think the industry needs more good guidance on how to do ECI. Or perhaps I have missed it?

回复
Robert Peters

Pacific Tug Group Director

3 年

So true. (nice Tug).

要查看或添加评论,请登录

David Kinlan的更多文章

社区洞察