The DWMP blog – Episode 13.  How much flood risk is too much?

The DWMP blog – Episode 13. How much flood risk is too much?

If you haven’t already seen the earlier episodes in this series, they are all here (https://tinyurl.com/MartinOsborneArticles) I suggest that you start from Episode 1 (https://tinyurl.com/DWMP-blog).

For people who suffer the trauma of being flooded, any risk of flooding is too much.?But how should we convert that into performance targets?

The National Audit Office report of 2004 discussed the then key metrics of sewer flooding of those at risk with an annual probability of more than 1:10.?Water companies were then also reporting properties at risk at 1:20 and had a design target of 1:30.?The new flood risk metric introduced alongside the DWMPs is to report 1:50.?This shows the change in attitudes to flood risk and the progress that we have made, but where should we stop??Is the long-term target 1:100, 1:200, 0?

Causes of flooding

There are two main causes of flooding from sewerage systems: blockages and excess flow due to intense rainfall.?(Sewer collapses and pumping station failures are much less of a problem.) ?Most sewer flooding is now due to blockages, partly because of investment to increase sewer capacity to cope with rainfall and partly because of the increasing use of wet wipes that do not break down in the sewers and contribute to blockages.?However, climate change is increasing rainfall intensities and the flooding that it causes.

Both of these causes of flooding are random in time and to some extent in location.?Properties in low spots will always be at some risk of flooding from either cause and will tend to suffer repeat flooding.?If they are in areas with limited sewer capacity or an area with a lot of wet wipes or fats discharged to the sewer (for example just downstream of a badly run chip shop) then that flood risk will be greater.?

Performance measures

There are two measures of flood performance: how many properties have actually been flooded each year, and what predictive modelling shows as the probability of future flooding.?Actual performance will vary from year to year depending on rainfall and blockages.?The predictive modelling will give the average probability over many years.

Normal practice is to use measurements of actual flooding for both blockages and lack of capacity but to use predictive modelling only for lack of capacity.?This means that we are not trying to predict the future for the biggest cause of flooding.?Using analysis of past incidents and sewer flow conditions we can predict where blockages are likely to be a problem; and most companies do this to help plan their sewer cleansing programmes.?I think that we should try to map which properties have a 1:50 probability of flooding from both causes to give the full picture of flood risk.?It is difficult to predict how the risk from blockage will change in the future as this depends on changing behaviour with fat and wet wipes and with changing cleansing programmes.

What is flood risk?

By flood risk we mean the combination of the probability of an event happening and the damage or impact that it will cause.?The damage could be measured as the financial cost or as the number of properties affected.?A graph of flood probability against impact is something like the graph below.

At the left-hand end is a catastrophic event that would flood many properties, but may never happen.?At the right-hand end is an event that will happen frequently but will not cause any impact.?The total flood risk is given by adding every bit of the graph to get the area under the curve.?This gives the number of properties expected to flood on average each year.

It is useful to redraw the graph as the risk (that is probability times impact) against probability.?This now shows that the catastrophic event poses little risk as it will probably never happen.?The biggest contribution to the overall risk is the band of events in the middle.?

Investments that we make in the sewerage system will push the right-hand end of the graph inwards and push the middle part of the graph down.?Improving the sewerage system will have little effect on the left-hand end of the graph.?This risk in extreme events will only be significantly reduced by protection measures for the individual properties that are at risk or modifying the ground slope to keep overland flow away from properties.

Summary

So, measuring risk to very extreme events is not useful to assess or plan sewerage system investments.?It is the middle range events of about 1:30 or 1:50 that we should be targeting and where we should measure performance.?However, we should also assess 1:100 or 1:200 probability events to plan the wider drainage system including flood protection and overland flood pathways.

Richard Ashley

Emeritus Professor of Urban Water

2 年

Martin your blogs are great but this one could have usefully referred to the 4 points approach we recommended in the revisited CIRIA exceedance guidance. Strange how this and the earlier design report are continually ignored.

Interesting article. When in comes to out of sewer flooding I tend not to speak to customers in terms of return periods, probabilities or sources of brown water. Given the major drainage system is above ground and the minor drainage system below ground a strong case for source control of ‘leaky’SuDs and design for exceedance. Co creation of blue green surface infrastructure along flow paths with drainage partners is important principle of reducing flood risk. Not sure there a willingness to pay or tolerate the impact of this type of infrastructure.

Robert Dickinson

Autodesk Water Technologist for Storm Sewer and Flood | Expert in ICM InfoWorks ICM SWMM/Ruby | 18 Years at Innovyze/Autodesk | 51 Years with EPASWMM

2 年

Interesting and thought provoking past, many thanks!

回复

要查看或添加评论,请登录

Martin Osborne的更多文章

  • 129 What are words worth?

    129 What are words worth?

    Last week I commented on what I considered an error in a UK published guide to sewerage and drainage systems. The guide…

    8 条评论
  • 128 History repeating down the highway drain

    128 History repeating down the highway drain

    I saw a post on LinkedIn about a tool to investigate the pollution impact of highway drainage on watercourses in…

    23 条评论
  • 127 Red teams and the water sector

    127 Red teams and the water sector

    The recent inquiry into the UK response to Covid19 identified ““an acute problem of advice, scientific advice in…

    11 条评论
  • 126 The law is an ass

    126 The law is an ass

    Everyone knows that the famous quote originally comes from Oliver Twist by Charles Dickens, published in 1838, and many…

    14 条评论
  • 125 Building houses for a water future

    125 Building houses for a water future

    In the last couple of weeks, I have seen three reports about how to build new houses so that they are resilient to…

    24 条评论
  • 124 Of fish and hippos

    124 Of fish and hippos

    In the last episode of the blog I discussed the legal case brought by the Pickering Fisheries Association about poor…

    4 条评论
  • 123 Environmental guard dogs

    123 Environmental guard dogs

    OK, they are not dogs, but Ethiopian hyenas. They are let into the city of Harar every night to scavenge rubbish.

    1 条评论
  • 122 Communicating with communities

    122 Communicating with communities

    So last week we suffered an interruption to our water supply and collapse of the road outside the house. The water…

    18 条评论
  • 121 History repeats itself

    121 History repeats itself

    Woke up, fell out of bed, dragged a comb across my head. Found my way downstairs and drank a cup and looking up I…

    19 条评论
  • 120 You might think that, I couldn’t possibly comment

    120 You might think that, I couldn’t possibly comment

    In Episode 116 I gave some initial comments on the current consultation document from Defra on “Draft information and…

    12 条评论

社区洞察

其他会员也浏览了