Dust suppression in a time of flood – when supply is not the issue.

Dust suppression in a time of flood – when supply is not the issue.

What was expected to be a straightforward dust suppression upgrade for Holcim Australia 's Albion Park Quarry, was hit by 1 in 100 year flood. Thankfully the experts at Southern Pumping were on the job and able to help steer Holcim through the unexpected turn of events.

Wetter Than Wet

Back in 2022, Holcim approached Southern Pumping about a dust issue affecting the main sales area at their Albion Park Quarry (EPL 122) that required some water suppression. Despite being ready to commence, the project came to a halt with flooding caused by the extreme weather events of 2022.?

"When the Illawarra receives these rain events, the main dam will rise and overwhelm the current pumping setup. The pump would remain underwater for some days and require replacement to bring it back into service." explains Elliott Scott, Pit Manager for Holcim's Albion Park Quarry.

Ever responsive and adaptable, Southern Pumping were quick to reassess the project, as the site initially identified for locating the pumps had been swallowed by the 1 in 100 year floods.?

Continue Reading >>