Dry Shotcrete

Dry Shotcrete

Dry Shotcrete, then known as “gunite”, was invented in 1907 by American taxidermist Carl Akeley to repair the crumbling facade of the Columbian Museum in Chicago. He used the method of blowing dry material out of a hose with compressed air, injecting water at the nozzle as it was released.

In the Dry Shotcrete process, dry materials are combined in a "pot" and transported pneumatically to a nozzle where water, any liquid admixtures, and an accelerator are introduced into the stream-feed. This mixture is immediately sprayed onto the target surface by compressed air.

The interior of the nozzle is fitted with a water ring, which uniformly injects water into the mixture as it is being discharged from the nozzle and propelled against the receiving surface.

The cementitious material and aggregates are thoroughly mixed and either bagged in a dry condition or mixed and delivered directly to the gun.


Advantages of Dry Shotcrete vs. Wet Shotcrete

a)     Instantaneous control over mixing water and consistency of mix at the nozzle to meet variable field conditions.

b)     Better suited for placing mixes containing lightweight aggregates, refractory materials, and shotcrete requiring early and higher strength properties.

c)     Capable of being transported longer distances. Start and stop placement characteristics are better with minimal waste and greater placement flexibility.

d)     Lower equipment and maintenance costs.

e)   Bond strengths of new shotcrete to existing materials are generally higher with dry-mix shotcrete.


Disadvantages

a)     Limited to accelerator as the only practical admixture.

b)     Air-entraining admixtures have little effect on dry-mix shotcrete since there is no mixing of admixture water and aggregate until impact on the shooting surface. Some contractors prefer to add an air-entraining admixture to a mix to improve workability.

c)     Applied at a much slower rate than wet-mix shotcrete. Dry-mix shotcrete is often applied at a rate of 1 or 2 cubic yards per hour compared to up to 7 or 8 cubic yards per hour for wet-mix shotcrete.

d)     Wet-mix shotcrete rebounds somewhat less than dry-mix shotcrete. Rebound is the material that "bounces" off the shooting surface. Rebound for conventional dry-mix shotcrete, in the best of conditions, can be expected to be at around 20 percent of the total material passed through the nozzle.


Equipment

Dry process equipment typically includes compressed air, water (preferably potable), shotcrete pot, accelerator dosing device, and robotized placer (for larger jobs).

Water supply booster pumps for dry-mix should be capable of supplying at least a 10-gallon/minute flow at 60 psi at the nozzle for standard nozzles. The water pressure must be constant and 15 to 30 psi above operating air pressure.

It is advantageous to pre-moisturize this material to three to six percent, by dry mass, prior to entering the shotcrete gun. A pre-moisturizer is a piece of equipment staged just before the shotcrete gun that uniformly distributes and mixes water to a continuous feed of dry materials.

A dry-mix nozzle typically consists of a tip, water ring, control valve, and nozzle body arranged in a wide variety of configurations.


Operation

It is common practice in dry-mix shotcrete projects to pre-bag all the materials together in a dry condition at the site. In the dry-mix process, dry (powder) admixtures are usually introduced into the mixture during batching. If a continuous feed gun is being used, they may also be added directly into the gun hopper by a special dispenser.

The batched water-cement ratio for coarse aggregate dry-mix shotcrete typically varies between 0.30 to 0.40.

Typically, a performance specification of 12-hour, 7-day and/or 28-day compressive strengths will be specified, along with a grading for the aggregate.

Test panels are particularly important as laboratory mixtures cannot duplicate as-shot dry-mix shotcrete.

The quality of dry-mix shotcrete is particularly dependent on the skill of the nozzleman, because his or her ability to control the amount of water being added to the mixture is essential.

Shotcrete can be produced by either the dry-mix or wet-mix process. However, differences in the equipment cost, maintenance requirements, operational features, placement characteristics, and product quality may make one or the other more attractive for a particular application.

Putzmeister (one of the leading companies in Shotcrete technology) lists these 3, as top mistakes made during the shotcreting process:

1. Adding water in excess

2. Dosing the accelerator uncontrollably

3. Forgetting to clean the surface

To find more in-depth information, the author recommends: European specification for Sprayed Concrete (Guidelines), Shotcrete - Elements of a System (E.S. Bernard), and Engineering Properties of Shotcrete (W.R. Lorman).

Alex He

Overseas Sales Manager at China Railway Construction Heavy Industry Co., Ltd.

4 年

now the wet concrete spraying is more popular, you can try it, we CRCHI are the wording leading manufacturer, you can refer to our website: en.crchi.com

回复
Tufail Aziz

Construction Manager @ NEOM Projects | Approved Construction Manager in 4 Regions of the NEOM

4 年

More power to you. Keep writing and sharing.. Thanks a ton :-)

回复

要查看或添加评论,请登录

Keivan Rafie的更多文章

  • Slurry TBMs

    Slurry TBMs

    Slurry TBMs are considered “soft ground” tunnel boring machines (along with earth pressure balance TBMs) that use…

    2 条评论
  • Horizontal Directional Drilling (HDD)

    Horizontal Directional Drilling (HDD)

    In the tunnel and civil engineering world, finding better methods to complete projects with minimal impact on the…

    5 条评论
  • Shaft Construction and Support Methods

    Shaft Construction and Support Methods

    The importance of minimizing public impact and need to avoid interfering with other structures and utilities in the…

    2 条评论
  • Trenchless Methods: which one works best for your project?

    Trenchless Methods: which one works best for your project?

    Trenchless methods are ways to install, repair, and renew underground pipes, ducts, and cables with minimal or no…

    1 条评论
  • Sequential Excavation Method Tunneling (SEM)

    Sequential Excavation Method Tunneling (SEM)

    Sequential Excavation Method (SEM) is a type of tunnel design and construction that started to gain popularity in the…

    4 条评论
  • Auger Boring

    Auger Boring

    Horizontal auger boring, also known as auger boring, horizontal earth boring, or jack and bore, is one of the most…

    4 条评论
  • Tunnel Survey and Alignment Control

    Tunnel Survey and Alignment Control

    Survey and alignment control is an essential part of tunnel projects all around the world. Projects need to apply such…

    5 条评论
  • Tunnel Lighting

    Tunnel Lighting

    The safety of a transportation tunnel depends highly on the ability of the motorists to see the interior and objects in…

    1 条评论
  • Understanding Dust in Tunneling and Underground Projects

    Understanding Dust in Tunneling and Underground Projects

    The natural atmosphere that we breathe contains not only gaseous components but also large numbers of liquid and solid…

    5 条评论
  • Risk Management for Tunnels

    Risk Management for Tunnels

    All tunnel projects face unknowns and uncertainties during planning, design, construction, and/or operation. With…

    11 条评论

社区洞察

其他会员也浏览了