Driving Predecessors in MS Project

Driving Predecessors in MS Project

Driving Predecessors in MS Project

Posted on?March 26, 2019?by?Byungmin Park

No alt text provided for this image

Do you have a project schedule with over a thousand lines? Are you spending a lot of time trying to determine why a certain activity is being delayed according to your plan?

In MS Project, a?predecessor?is defined as a task which drives its successor task before it can start or finish. When scheduling projects, an individual task may have multiple?predecessors?linked to it. So, how do you know which one of those multiple?predecessors?is directly affecting the start or finish date of its?successor?task? It’s the single?predecessor?with zero-day slack driving the succeeding task and it is called the?driving predecessor.

The larger and more complex the project is, the more difficult it can be to see the logic between the activities. To assist users,?MS Project?offers some great tools that will allow users to detect which predecessor is affecting your task quickly.

Let me show you two different ways to visualize driving predecessors in an MS Project schedule.

The following is a sample project schedule. Let’s look at the milestone called “All Employees Hired.” You’ll notice that this milestone has three different?predecessors. We want to see which predecessor should be carefully examined to achieve that milestone, according to the planned finish date. There are two ways to do this.

No alt text provided for this image

Option 1: Visualize the task path and driving processors in the Gantt Chart

If you want to have a?graphical representation?of this information, you can use the highlighting option under the?Gantt Chart Format?ribbon. (Note* If you have custom formatted your Gantt chart this option may not work because your custom format will override this function.)

No alt text provided for this image


In the drop-down menu, select?Driving Predecessor. After choosing this option, select the task/milestone in the WBS table that you would like to examine. After selecting the task, the?driving predecessors?that are driving the milestone will be highlighted in orange. You can see that “Hire Cashier Employees” is the task that is actively driving the “All Employees Hired” milestone.

No alt text provided for this image

This option not only shows the driving predecessor for the selected task,?but it also shows you the entire driving path for the selected milestone. You can also see from the?Gantt Chart?that the “Hire Cashier Employees” task is actively driven by “Order Bulk Ingredients.”

To remove the highlighted tasks, deselect the?driving predecessors?in the task path drop-down menu.

Option 2: Visualize the driving Predecessors in the Work Breakdown Structure using Task Inspector

You may be thinking “I have over a thousand lines in my schedule, using the Gantt chart will not help me! I need to quickly be able to identify which specific task is driving the selected tasks!” This can be remedied simply by using the task inspector.

To use this function, in the Task ribbon, there is an option called the?Inspect. In the drop-down menu select?Inspect Tasks.

No alt text provided for this image

You can now see?Task Inspector?as a pane that is placed on the left of the?WBS Table?screen. This pane will show you the?predecessor?that will have a direct impact on task’s start or finish date. See image below.

No alt text provided for this image

By clicking the link under the Predecessors, you will be able to navigate through the?driving predecessors.

If the users’ schedule contains dated?constraints, Task Inspector may also show?constraints?as the driving predecessor.

Follow us on Instagram and LinkedIn for more?for more MS Project tips.

This entry was posted in?Gantt Chart,?Microsoft Project?and tagged?Driving Predecessor,?Gantt Chart,?Inspector Tool,?MS Project 2016,?Multiple Driving Predecessor. Bookmark the?permalink.