DILO Proactive Maintenance Planner

DILO Proactive Maintenance Planner

Maintenance Planners (planner/scheduler) are one of the most misused resources in the maintenance organization. We must always remember that the Maintenance Planner represents that single resource in the organization who is strictly dedicated on preparing for the future.

?Sources of Maintenance Wastes:

  1. ?Waiting for Instructions or Drawings
  2. ?Winging it Without Instructions or Drawings
  3. Waiting for Parts
  4. ?Looking for Supervisors for Instructions ?
  5. Making Multiple Trips to the Job Site ?
  6. Looking for the Right Tools
  7. ?Making the Wrong Tools Work ?
  8. Waiting for Approval/Permits
  9. ?Waiting for the Equipment to be released ?
  10. Waiting on equipment to be Shutdown, Cooled Down, Drained, etc.
  11. Waiting on a Crane Lift
  12. Having too many/ too few craft-workers per job ?
  13. Not placing the right craft / skill for the job
  14. Repeat Repairs and Rework

Without this focus, we fall victim to the typical maintenance wastes associated with a reactive organization. Reactive Maintenance Organizations have a “Low Wrench-Time” because of all the sources of Maintenance Waste.

World-class wrench time is 55-65%; most companies have a wrench time between 15-25%.

The only method to achieve optimal and stable wrench-time is through Maintenance Planning and Scheduling. Maintenance Planning and Scheduling are two different functions which are dependent on each other.

If an organization increases by wrench-time by 10% it could make a serious impact of equipment reliability.

DEFINITIONS:

?Without definitions we are dependent on everyone's opinion.

?Maintenance Planning - the process of future maintenance work which the job has been scoped, parts and material identified, # and type of maintenance craft, downtime required (if required).

?Maintenance Scheduling – the process of scheduling maintenance resources with productions by day by hour.

?Weekly Maintenance Scheduling Meeting – a weekly scheduled meeting with production, maintenance, engineering (if required) to ensure all stakeholders are in agreement with the preliminary schedule which was created with Production and Maintenance Leadership based on the needs of the site.

?Parts Kitting – the process to identify and stage parts required for upcoming Maintenance Scheduled Work

Maintenance Rework – Rework is Corrective Work completed on previously maintained equipment that has prematurely failed due to maintenance operations, or material problems.

MAINTENANCE PLANNING AND SCHEDULING ROLES AND RESPONSIBILITIES:

Maintenance Planning and Scheduling Roles and Responsibilities is critical to success to ensure all stakeholders understand their role and responsibilities in this process. See example below of a Maintenance Planning and Scheduling RACI.

Measuring how effective and efficient Maintenance Planning and Scheduling in any organization is critical to success of Maintenance and Production. Lord Kelvin, 1824-1917, stated, “If you cannot measure it, you cannot manage it” and Planning and Scheduling thus must be measured, or it will not be managed.

DAILY SCHEDULE FOR MAINTENANCE PLANNER:

Monday:

Armed with an inspection schedule (jobs to be planned), job inspection forms, and a camera, the planner will begin making his/her inspection of all the job sites.

The planner has established a logical route to minimize travel time and will make notes of the specific needs of the requests, any ancillary work that should be completed by the mechanics while at the job site, and all of the other applicable information required for a well-planned job.

Reviews Work Orders written over the weekend to see if additional work is needed.

Focuses on Work Orders that need to be Planned based on Intercept Ranking model (see below)

Tuesday:

Armed with the information gathered during the field inspection on the previous day, processing parts needs, and updated status reports on jobs that have received some or all the parts ordered, the planner should meet with the

maintenance supervisor. The planner should bring a copy of the updated planning backlog. This meeting should be short, 30 minutes or less, and its purpose is twofold:

1. Provide preliminary info to those who will be building/amending the maintenance schedule

2. Ensure that the planner has scheduled the various jobs in his/her queue in a manner consistent with the needs of maintenance and production. The planner should share parts issue updates and the schedule for his/her planning activities.

Wednesday:

?The planner reviews all “Ready to Schedule” Work Orders with Production and creates a preliminary schedule that is agreed upon for the following week.

After the meeting, the planner ensures parts / material for next week are kitted in a secure area.

The planner continues to focus on work orders which are in the backlog which has not been “planned” to review scope of work, parts required, order parts or material as needed, etc.

?Thursday:

?Planner prepares for Maintenance Scheduling meeting by producing the agreed upon schedule with production for the following week.

Attendees: Maintenance Planner, Production Leader, Maintenance Supervisor, Contractor (if work they are performing may impact the schedule) Maintenance Planner facilitates the Scheduling meeting (30 minutes max)

??> A timekeeper ensures everyone stays focused and gives a 5-minute warning and times up announcement.

> At end of meeting maintenance supervisor and production leader shake hands and tell each other, “We do the best we can to meet this schedule next week”

Friday:

Schedule published for all to see in targeted locations in the plant.

>?In the Maintenance Shop

>?In the Cafeteria

>?In the Production Office

> In the Maintenance Supervisor Office

Join me for Maintenance Planning and Scheduling Best Practices in Nashville, TN - If you are interested send me an email at [email protected]


Aminat Buraimoh

Maintenance Planner | Industrial Engineer | SAP PM | Maintenance and Reliability Professional

8 个月

The maintenance waste is the reality in many industrial organisations. If they could be mitigated or if possible completely eradicated. The performances of equipment will be optimised and failures between maintenance will be reduced. Thanks Ricky for sharing this information.

Anolt Musekiwa

Printing Technician

8 个月

Unfortunately this is not what it looks like in as many organizations I know and have worked with. Thanks for sharing this article.

Madi Hakim, CMRP

Maintenance and Reliability Professional, Vibration Analyst CAT-II, MLA-I

8 个月

Such a complete explanation about scope, roles and responsibilities of Maintenance Planning & Scheduling. Daily schedule may custom for each different organization. Sometime Planning has to involve Engineering for those activities not like to like. Thank you for the article, Mr. Ricky Smith. ??

James Craigg

Maintenance Planner | Leveraging CMMS & Maintenance Scheduling | Boosting Asset Reliability and Performance

8 个月

This definitely does not resemble what a day in my life looks like as a maintenance planner.

Bernhard Heindl

AI@Maintenance Facilitator ... ich mache das, was ein sehr guter Leiter Instandhaltung bzw. Technik tut & helfe am Weg dorthin.

8 个月

impressive!

要查看或添加评论,请登录

社区洞察

其他会员也浏览了