Difference Between Submittal and Transmittal

What is the Difference Between Submittal and Transmittal

The?main difference between submittal and transmittal?is that submittal is a document, sample, or any other information that is presented for review or consideration, whereas transmittal is a document that is sent along with other documents or files.

Submittals and transmittals are two types of documents that transfer between parties. People working on construction projects frequently uses two types of documents. Although both play an important role, there is a distinct difference between submittals

What is a Submittal

Submittal refers to documents, samples, and any other information that should be delivered to engineers, architects, consultants, and others involved in a project, even before starting the project. Submittals are essential for any construction project since these types of projects run on specs and plans. Construction projects are often very complex and involve input from various professionals. For example, architects make drawings; then subcontractors decide what materials they are going to use; the construction manager adds these to the Project Manual, which can contain thousands of pages. A project manual can have many types of information like plans, drawings, selected products,?quality assurance, testing information, and other documents.

Submittals can make up many types of documents, including samples, shop drawings, product data (e.g., blueprints, product manuals, etc.).

What is a Transmittal

A transmittal is a document that is sent along with other documents and files. It allows everyone to keep track of all communications that occur between everyone in the project. It provides evidence that the documents, samples, or files were sent, and records when they were sent and who they were sent to. If a question arrives, they can refer to the transmittal later on. Therefore, transmittals ensure no one overlooks anything during a complex communication process. Moreover, transmittals become very important during legal disputes.

In construction projects, it’s always important to know when someone sent the information and who received it. For example, the date of sending the document, and who received it? Transmittals help to record the information needed to prove delivery.

Information in a Transmittal

A transmittal typically contains the following information:

  • Date
  • Information about the sender and recipient (name, company, and address)
  • Name, number, and address of the project
  • The reason for sending the document
  • List of documents sent
  • Record of the actions that a receiver must take and when those actions are due

Difference Between Submittal and Transmittal

Definition

A submittal is a document, sample, or any other information that is presented for review or consideration, whereas a transmittal is a document that is sent along with other documents or files.

Stage of Construction

Submittals are the first step in a construction project. In contrast, transmittals can be sent at any stage.

Use

Moreover, submittals can be samples, shop drawings, product data (e.g., blueprints, product manuals, etc.), whereas transmittal is a document that records the transmission of other documents or files between parties.

Conclusion

A submittal is a document, sample, or any other information that is presented for review or consideration, whereas a transmittal is a document that is sent along with other documents or files. Thus, this is the main difference between submittal and transmittal. Furthermore, submittals can be samples, shop drawings, product data (e.g., blueprints, product manuals, etc.), whereas transmittals record the transmission of other documents or files between parties. Both are equally important in a construction project.

要查看或添加评论,请登录

Amit Prajapati的更多文章

  • Amit Prajapati – Document Controller (Information Management Specialists) List of my completed projects in last 15 years Total Completed Project = 23

    Amit Prajapati – Document Controller (Information Management Specialists) List of my completed projects in last 15 years Total Completed Project = 23

    BECHTEL INDIA PVT LTD (7 projects) Port Arthur LNG for Sempra Aug 2022 - Present · Rio Grande LNG Project for…

  • Stages of Project Handover

    Stages of Project Handover

    The stages of project handover As with all processes, the project handover can be viewed and discussed in terms of…

  • Document v/s Record

    Document v/s Record

    Main Difference – Document vs Record Although document and record mean the same in general usage, they have specific…

  • General Tips for Document Storage

    General Tips for Document Storage

    General Tips for Document Storage Whichever way you choose to store your documents, there are certain good practices…

  • What is project handover?

    What is project handover?

    What is project handover? Project handover is the point in the project management lifecycle when the completed tasks…

  • Project Handover Checklist

    Project Handover Checklist

    Project Handover Checklist Step 1: The prep work or the pre-handover stage The pre-handover stage is mainly about…

  • What’s a project handover?

    What’s a project handover?

    What’s a project handover? A project handover is when you pass on control of a project to another person—whether that’s…

  • Electronic Prepared Documentation

    Electronic Prepared Documentation

    Electronic Prepared Documentation Compiled documents such as Manufacturer Record Books and Fabrication Record Books are…

  • Electronic Project Delivery Documentation

    Electronic Project Delivery Documentation

    Electronic Project Delivery Documentation All drawings and technical documents delivered to the Owner will be in…

  • Final As-Built Documentation

    Final As-Built Documentation

    Final As-Built Documentation The Contractor must certify that all Final Documentation in each of the foregoing areas…