Day in the Life of a Proactive Maintenance Planner
WORLD CLASS MAINTENANCE
"Success in Maintenance requires Discipline and Repeatability”
Maintenance Planners (planner/scheduler) are one of the most misused resources in the maintenance organization. We must always remember that the Maintenance Planner represents that single resource in the organization who is strictly dedicated on preparing for the future.
?Sources of Maintenance Wastes:
?Without this focus, we fall victim to the typical maintenance wastes associated with a reactive organization. Reactive Maintenance Organizations have a “Low Wrench-Time” because of all the sources of Maintenance Waste.
The only method to achieve optimal and stable wrench-time is through Maintenance Planning and Scheduling. Maintenance Planning and Scheduling are two different functions which are dependent on each other.
If an organization increases by wrench-time by 10% it could make a serious impact of equipment reliability.
DEFINITIONS:
?Without definitions we are dependent on everyone's opinion.
Maintenance Planning - the process of future maintenance work which the job has been scoped, parts and material identified, # and type of maintenance craft, downtime required (if required).
Maintenance Scheduling – the process of scheduling maintenance resources with productions by day by hour.
DEFINITIONS CONTINUED:
Weekly Maintenance Scheduling Meeting – a weekly scheduled meeting with production, maintenance, engineering (if required) to ensure all stakeholders are in agreement with the preliminary schedule which was created with Production and Maintenance Leadership based on the needs of the site.
Parts Kitting – the process to identify and stage parts required for upcoming Maintenance Scheduled Work
Maintenance Rework – Rework is Corrective Work completed on previously maintained equipment that has prematurely failed due to maintenance operations, or material problems.
"Maintenance Rework is high if Planning and Scheduling is not Effective."
==================================================
Maintenance Planning and Scheduling Roles and Responsibilities is critical to success to ensure all stakeholders understand their role and responsibilities in this process. See example below of a Maintenance Planning and Scheduling RACI.
Measuring how effective and efficient Maintenance Planning and Scheduling in any organization is critical to success of Maintenance and Production.
Lord Kelvin, 1824- 1917, stated, “If you cannot measure it, you cannot manage it” and Planning and Scheduling thus must be measured, or it will not be managed.
DAILY SCHEDULE FOR MAINTENANCE PLANNER:
领英推荐
?Monday:
Armed with an inspection schedule (jobs to be planned), job inspection forms, and a camera, the planner will begin making his/her inspection of all the job sites.
The planner has established a logical route to minimize travel time and will make notes of the specific needs of the requests, any ancillary work that should be completed by the mechanics while at the job site, and all of the other applicable information required for a well-planned job.
Reviews Work Orders written over the weekend to see if additional work is needed Reviews Maintenance Ready Backlog (Ready to Schedule) to as to identify which Work Orders need to be scheduled the following week.?
Tuesday:
Armed with the information gathered during the field inspection on the previous day, processing parts needs, and updated status reports on jobs that have received some or all the parts ordered, the planner should meet with the maintenance supervisor. The planner should bring a copy of the updated planning backlog. This meeting should be short, 30 minutes or less, and its purpose is twofold:
1. Provide preliminary info to those who will be building/amending the maintenance schedule.
2. Ensure that the planner has scheduled the various jobs in his/her queue in a manner consistent with the needs of maintenance and production. The planner should share parts issue updates and the schedule for his/her planning activities.
Wednesday:
The planner reviews all “Ready to Schedule” Work Orders with Production and creates a preliminary schedule that is agreed upon for the following week.
After the meeting, the planner ensures are parts / material for next week are kitted in a secure area.
The planner continues to focus on work orders which are in the backlog which have not been “planned” to review scope of work, parts required, order parts or material as needed, etc.
Thursday:
Friday:
Schedule published for all to see in targeted locations in the plant.
=====================