D365 | SCM | Planning Optimization | Auto replenishment| Scenario 1 – Coverage Code “MinMax” & Vendor Working Time Calendar
Ali Danish
Microsoft D365 Solution Architect | ERP Digital Transformation Lead at Aster Digital Healthcare | D365 SCM | D365 WMS | D365 Planning Optimization | D365 Production | MCP | MBA | Blogger at Dynamics Community
Abstract
In order to run the auto-replenishment process in D365, we need to set up the master planning module. Business users can activate and utilize the magic of "The planning optimization" feature available in D365 Supply Chain Management. I will cover all the business scenarios for the coverage codes options available in the master planning module.
We can create and associate the Vendor working time calendars with the vendor master form. We can define the Vendor working days based on business requirements from Monday to Friday with working time from 10:00 AM till 5:00 PM. The master planning engine will respect the vendor's working time calendar(days and time) and propose the planned purchase orders with delivery dates as specified in the working time calendar.
We can categorize the vendors and associate them with one working time calendar. For example, all Food vendors will deliver the items in the first shift and Non-Food vendors will deliver the items in the 2nd shift. If required, business users can also create the Calendar for individual vendors. Certain Vendors will deliver the items only on Tuesday within a specified time slot.
Introduction
Master planning can be configured to use different replenishment methods. The replenishment methods or lot-sizing methods are the techniques used by the system to determine the batch size for purchased or produced items.
Each replenishment method is assigned one of the following coverage codes:
Business Scenarios
In this blog series, I will discuss the following three business scenarios
Auto Replenishment Process Flow
The planning manager or buying department will perform the prerequisite setups and process the auto-replenishment in the master planning module.
Scenario 1 – Coverage Code “MinMax”
Prerequisite Setups and Configurations
Here is the list of prerequisite setups
Coverage Group
Select the coverage group for an item as “Min Max” on the item setup form in the plan tab.
Path: Product Information Management > Products > Released Products > Click on Item > Plan > Coverage group
Item Coverage
Path: Product Information Management > Products > Released Products > Plan > Coverage group
In the general tab select the following details
Coverage Group: In the item coverage, we define the item coverage code so that the master planning will create the plan orders according to this item coverage code.
Vendor Account: In the item coverage, we also define the vendor account call. When master planning will be run it will create plan orders according to the below-set vendor.
Note: If we set the primary vendor on the item master form and then on vendor item coverage, the plan orders will be created according to the vendor set on item coverage as per the below screenshot:
Working Time Calendar for Vendors
The vendor calendars will be created in the “Working time calendars” form, this form is available in the organization administration module.
We can create and associate the Vendor wise working time calendar. The Vendor calendar will be associated with the Vendor master form. Based on the Vendor working time calendars, master planning will generate the planned purchase orders. The delivery dates for the vendors will be based on these working time calendars.
Path: Organization Administrator > Setup > Calendars > Calendars
Select Default Vendor For ?The Item
Select the default Vendor for the item, when the master planning will run then the planned purchase order will be created for this vendor.
领英推荐
Path: Product information management > Products > Released products > Item setup > Purchase tab
Working Time Template
Create a working time template for the vendors. This vendor will operate for working days "Monday to Friday".
Path: Organisation administration > Setup > Calendar > Working time template
In the below template, I have defined the working times from Monday to Friday 10:00 AM to 05:00 PM is set. Saturday and Sunday are blanked, which means the vendor will not supply on Saturday and Sunday:
Associate Vendor with Item
On the item setup form, the vendor ID must be set. When the master planning will run then the planned orders will be made against those vendors which are saved on the item setup page as shown below:
Path: Product information management > Products > Released products > Item setup > Purchase tab
Associate Purchase Calendar with Vendor
We need to associate the vendor calendar with the vendor setup form. For this setup, we need to open the vendor setup form. When we will run the master planning, the planned orders will be made according to the calendar saved on the vendor setup. The process is shown below:
Path: Accounts payables > All vendors > Purchase order default > Purchase calendar
Step-by-Step Process
Run Master Planning - Planning Optimization
Now we will run the master planning to generate planned orders. Master planning can be run in batches automatically. But this time we are running it manually to understand the process and logic of D365.
Path: Master Planning > Master Planning > Run > Planning Optimization
Verify Planned Orders
The system has created the planned purchase orders for item 10007. The requirement quantity is 200,000. Since the item on hand is zero that's why the system has proposed the maximum quantity.
Path: Master Planning > Master Planning > Planned Orders
Firm Planned Orders
After running the master planning, we will go to the planned order form to see the system-generated planned orders. The system will generate planned orders according to the configurations of the selected items.
By selecting the planned orders, we will click on the “firm” button then the system will create purchased orders.
Path: Master Planning > Master Planning > Planned Orders
Validate and Confirm the Purchase Orders
Now we will verify the purchase orders that are created as a result of firm-planned orders. We will confirm the purchase orders after validation.
Path: Accounts Payables > Purchase Orders > All Purchase Orders
Conclusion and Recommendations
I hope you like the article, keep connected and?Walk the Talk.
Feel free to share your feedback in the comments section.?
Truly Yours,
Ali Danish?
ERP Microsoft D365FO Solution Architect | Corporate Trainer
M: +971554912688
D365 | ERP | Finance & Supply Chain | Microsoft Dynamics 365 / AX 2012 & 2009
2 年Ali Danish have you any idea about (Warehouse management> Inquiries and reports> Mobile device logs>Mobile device activity log)
SCM functional consultant |AX2012| D365FO|Production|Costing|MasterPlanning|Power BI | Project Management|
2 年Well describe Ali Danish sir
ACCA, MCP
2 年Please share article on email notifications as well