D365 SCM |Let's Talk Production Control |Discrete Manufacturing |Sales Quotation & Master Planning | Part 4
Ali Danish
Microsoft D365 Solution Architect | ERP Digital Transformation Lead at Aster Digital Healthcare | D365 SCM | D365 WMS | D365 Planning Optimization | D365 Production | MCP | MBA | Blogger at Dynamics Community
Abstract
?A quotation is basically a request by a customer for a particular product at a specific price and quantity, in this Production Control blog series we are using the finished good item “M-mobile”. ??
?While running the master planning, business planning users prefer to factor in the sales quotations which are either created, sent, or confirmed by the customers. The master planning engine will propose and simulate the planned production and planned purchase orders for these items. ?
?Master planning will propose the delivery dates for the finished good items which we need to produce and the raw material items which we need to procure from the vendors.?
In this article, I will cover the following two scenarios
The above two scenarios are applicable for Make-To-Order business strategies.
Here is the high-level agenda for today
Agenda
Step by Step Process
Create a Sales Quotation
Sales Quotation Created
Inventory Transaction Status
Once the sales quotation is created, the inventory Issue status is “Quotation issue”. Physical and financial dates are not updated at this stage.
Inventory On hand
Setup Master Plans
In the master plans form, make sure to enable the following parameters
·???????Include on-hand inventory
·???????Incldue inventoyr trasnactions
·???????Include sales quotation
·???????Scheduling method “Operations scheduling”
Based on the above selection, the system will factor the on-hand inventory, inventory transaction for the item, and all the sales quotations which are created or sent to the customers.
Master planning will perform the “Operation scheduling” for the production resources. This will be helpful for the business to simulate the production orders. The system will perform the capacity reservation for the resources once the planned production order will be firmed.??
Run Master Plan
·???????The next step is to run the master plan for the finished good item.
·???????Master Planning> Run master plan
·???????Filter the finished good item “M-Mobile”.?
Planned Orders Generated by Master Plan
Since we don’t have any on-hand inventory for the finished goods and raw material items, master planning has generated the proposal for planned production orders and planned purchase orders.
Based on the availability of production resources, master planning has proposed the delivery date for the finished goods and raw material items.
The raw materials will be procured from the default vendor specified at the item master.
Once the planned orders are created, the planning manager can split or group the orders. The planning manager can also change the reference, for example, if the raw material item is available in another warehouse, the planning manager will change the planned purchase order to planned transfer order.?
Planned Production Order
Master planning has generated the planned production order. The order is scheduled from 14th March till 20th April.
In the pegging section, we can see the reference is “Quotation”. This is the reason why Master planning has generated the planned production order.
The requirement quantity is -100, which means there is no on-hand stock available for the finished good item.
The status of the order is unprocessed, the next step is to approve and firm the order.?
Planned Purchase Orders
Since we don’t have the raw materials in our inventory to produce the finished good item “M-Mobile”, the system has proposed the planned purchase orders.
In the pegging section, we can see that the reference for the planned purchase order is “BOM line”. This is the BOM line item that we need in our production/raw material warehouse before we start production.
The requirement date for the planned purchase order is 14th March.?
Sales Quotation – Sent
The next step is to send the sales quotation to the customer. The status of the quotation will be changed from created to “Sent”.?
领英推荐
Sales Quotation Print
The business user can view the sales quotation print on the screen.?
Confirm Sales Quotation
Sales Quotation Confirmed
Sales Order Created
The system has created the sales order for the customer from the sales quotation. The business user can also view the related sales quotation for the sales order.?
Sales Order Created – Inventory Transaction
In the inventory transaction, we can validate that the sales order is created with the Issue status “On order”. Since the finished good inventory is not available in the warehouse, the issue status is on order, otherwise, the status will be “reserved physical”.?
Firm the Planned Orders
The next step is to firm the planned orders. Select the “standard” in the update marking field. Enable the group by vendor and group by period(date) fields. ?Press ok
Purchase Order Created
Master planning has created the approved purchase order for the raw material items.
Since the vendor and delivery dates are the same for all the items, the system has created one purchase order.?
PO Item Registration - Item Arrival Journal
We will register the items against the PO using the item arrival journal.
Inventory management> journals> Item arrival
Create a new item arrival journal, in the reference field select the “Purchase order”, in the number field select the purchase order. Press ok and create the journal.?
Item Arrival Journal Lines
Click “Functions” and create the lines for the item arrival journal. This feature will create all the lines in the item arrival journal for the selected purchase orders. Create the batch number for each line item. Select the batch and enter the register quantity.
Finally, validate and post the item arrival journal. Once the item arrival journal is posted, the inventory transactions receipt status will be “Registered”.?
Production Order Created
Master planning has created the production order, the production order status is “Scheduled”.
When we run the master plan, only a sales quotation was created. The pegging for the planned production order was “Quotation”, the system has not updated the reference type “Sales order” with the production order. Based on the availability of production resources, the delivery date for the production order is 20th April.?
Production Order – Schedule Jobs
We have seen in the last blogs that once the planned production order is Firmed, the system has created the production order with the status “Scheduled”, while the scheduling status was “Operations Scheduled” based on our step in the master planning parameters. The production order is created with the status “Operation scheduled”. We will explore the job scheduling feature in this blog. Click “Schedule jobs” and select forward from today’s date. The scheduling status is updated to “Job scheduled”.?
Gantt Chart – Resrouce View
The Gantt chart resource view feature will only support the Job scheduling.
Since we have selected the Job scheduling, the system has scheduled the resources by start and end date with start and end time.
The start date for assembly operation 10 is 14th March(Time 9:00) and the End date is 31st March(Time 10:00).
Once the assembly will be finished, the packing process will be started on 31st March(Time 10:00) and Ended on 20th April (11:00).
Production Route
The jobs are scheduled based on the operations defined for the Production route. The primary operation 10 is for the Assembly resource, once this operation will be finished the next operation will be stated that is 20 for the Packing. Both Assembly and packing are performed by machines.?
Conclusion & Recommendations
Stay tuned for the next article, In the meantime,?Walk the Talk.
Feel free to share your feedback in the comments section.?