Contractor’s Entitlement to Suspend Work in EPC Contracts

Contractor’s Entitlement to Suspend Work in EPC Contracts

Contractors in EPC (Engineering, Procurement, and Construction) projects often face situations where suspension of work becomes a necessary remedy. This right is governed by specific contractual terms, local laws, and industry practices. Below is an in-depth discussion of the contractor's entitlement to suspend work, supported by real-life examples for better context.


1. Sources of Suspension Rights

Contractual Provisions

EPC contracts are typically governed by comprehensive agreements that outline suspension rights in detail. Commonly included grounds for suspension are:

Non-Payment by the Employer: A frequent trigger for suspension is the Employer's failure to make payments as per the contract’s payment schedule.

  • Project: A highway construction project in India.
  • Issue: The Employer failed to release interim payments for three consecutive months, despite the contractor completing milestones as per the contract.
  • Action: After repeated requests, the contractor issued a suspension notice citing non-payment. The Employer resolved the issue by releasing payments within the cure period, allowing work to resume without significant delays.

Failure to Provide Access or Approvals: If the Employer delays providing site access, design approvals, or other prerequisites for work, suspension may be justified.

  • Project: A power plant construction in Africa.
  • Issue: The Employer delayed handing over a critical portion of the site due to unresolved land acquisition disputes.
  • Action: The contractor suspended all work on related project sections until access was granted. The delay led to an extension of time (EoT) and additional costs, which the contractor successfully claimed.

Force Majeure Events: Events beyond the control of the parties, such as natural disasters, pandemics, or government actions, may make suspension necessary.

  • Project: An oil refinery project in the Middle East.
  • Issue: During the COVID-19 pandemic, travel restrictions and supply chain disruptions prevented the contractor from mobilizing workers and materials.
  • Action: The contractor suspended work, citing the force majeure clause. Both parties negotiated terms for resumption once restrictions eased.

Employer’s Breach: Any material breach of the contract by the Employer, such as failing to supply materials or fulfill critical obligations, may justify suspension.

  • Project: A metro rail construction in Southeast Asia.
  • Issue: The Employer failed to approve detailed engineering designs within the contractual timeframe.
  • Action: The contractor issued multiple notices before suspending work. The suspension pressured the Employer to expedite the approval process, minimizing project disruption.

Legal Principles

In addition to contractual provisions, local legal principles may support the right to suspend work:

  • Frustration of Purpose: If the purpose of the contract is temporarily hindered due to the Employer’s actions or external circumstances.
  • Breach of Payment Obligations: Common law or statutory provisions in many jurisdictions recognize non-payment as valid grounds for suspension.


2. Procedure for Suspension

Notice Requirements

The contractor must serve a formal notice to the Employer, clearly stating:

  • Reason for Suspension: The specific breach or issue prompting the action.
  • Cure Period: A reasonable timeframe for the Employer to remedy the issue before suspension begins.
  • Intention to Suspend: A declaration that work will be suspended if the issue remains unresolved.

Compliance with Contractual Terms

  • Contractors must strictly adhere to the notice and procedural requirements outlined in the EPC contract.
  • Failure to comply with these terms could result in claims of wrongful suspension or breach of contract.


3. Limitations on Suspension

Proportionality

The suspension must be proportional to the issue at hand. For instance, non-payment of a minor invoice may not justify halting all work on a major project.

Mitigation of Harm

Contractors are obligated to mitigate the impact of suspension on the project. This may include keeping critical systems operational or safeguarding materials and equipment.

Good Faith and Fair Dealing

Suspension must be exercised in good faith and should not be used as a strategy to coerce or pressure the Employer.


4. Consequences of Suspension

Impact on Project Timeline

Suspension typically entitles the contractor to a time extension for project completion.

The revised timeline must account for both the suspension period and the time required to resume work.

Entitlement to Compensation

Contractors may claim compensation for additional costs incurred due to suspension, including: Idle labor and equipment costs. Costs of demobilization and remobilization. Storage and preservation of materials.

Potential for Termination

If the underlying issue remains unresolved for an extended period, the contractor may escalate to contract termination, as per the provisions in the EPC agreement.


5. Legal and Practical Considerations

Jurisdictional Variances

The enforceability of suspension rights varies by jurisdiction. Contractors must ensure their actions align with local laws and regulations.

In civil law jurisdictions, good faith obligations are often more stringent than in common law systems.

Risks of Wrongful Suspension

If the contractor suspends work without valid grounds or fails to follow contractual procedures, the Employer may claim damages for wrongful suspension.

Contractors should carefully evaluate the contractual and legal basis for suspension before taking action.


6. Best Practices for Contractors

Thorough Documentation

Maintain comprehensive records of the events leading to suspension, including correspondence with the Employer, site logs, and financial data.

Engage Legal Counsel

Legal advice is crucial to ensure the contractor's suspension rights are properly exercised and defensible in case of disputes.

Negotiation and Communication

Before suspending work, contractors should attempt to resolve issues amicably through negotiation or mediation. Open communication can prevent escalation and preserve relationships.

Safeguarding Assets

During suspension, contractors should take measures to protect on-site materials, equipment, and partially completed works to minimize further losses.


7. Common Clauses in EPC Contracts

Many EPC contracts, including those based on standard forms such as the FIDIC Yellow Book, include clauses addressing suspension. Key features often include:

  • Specific events or breaches entitling the contractor to suspend work.
  • Notice periods and procedural requirements.
  • Employer obligations to mitigate the consequences of suspension.
  • Contractor entitlements to compensation and extensions of time.


The right to suspend work is an essential tool for contractors in EPC projects to address breaches or unforeseen circumstances without immediately resorting to termination. To exercise this right effectively, contractors must ensure strict compliance with the contract terms, maintain transparency, and act in good faith. Proper management of suspension rights protects both parties’ interests and minimizes the potential for disputes.


Emanuel Moshi

Civil Engineer (PE) & Contract Management and Procurement Expert. Experienced in Fidic Contracts and PPRA Contacts

2 个月

I wish to emphasize on the fact that suspension right must be exercised in good faith. Parties should never use this provisions as a strategy to earn some things. Dispute Avoidance and adjudication board should always strive to create harmony between the parties and encouraging communication and amicable discussion when events that may attract suspension surface into the project

Emanuel Moshi

Civil Engineer (PE) & Contract Management and Procurement Expert. Experienced in Fidic Contracts and PPRA Contacts

2 个月

Other suspension claims submitted by the Contractor were determined negotiated and paid accordingly

Emanuel Moshi

Civil Engineer (PE) & Contract Management and Procurement Expert. Experienced in Fidic Contracts and PPRA Contacts

2 个月

Another case STUDY Project name. Design and build of mixed used apartment; Contract type. Fidic 1999 yellow book Cause for suspension: Employer fail to pay three consecutive IPCs plus other variations claims for almost 5 years when the project was at 25% progress. Suspension duration. The project was suspended from 2018 to 2023. The Contractor claimed for price escalation of the costs due to prolonged suspension of more than 5 years. The staff member of the Employer was appointed to as the Engineer. Resolution. The Employer paid the contractor and negotiate with the contractor for the price escalation. Finally agreed and the contractor resume the works.

要查看或添加评论,请登录

Pragmatic Project Consilium的更多文章

社区洞察

其他会员也浏览了